Permit: T16CM02176
Permit Details
Apply Date:
03/23/2016
Applicant:
BRIAN HAGEDON
Description:
NEW HOSPITAL
Architects:
- WATSON, ANGELA
Contractors:
- D P R CONSTRUCTION A GENERAL PARTNERSHIP
Permit Reviews
Permit Number - T16CM02176
Permit Status: C of o
Permit Description: NEW HOSPITAL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/15/2017 | REVISION - - 2ND | 03/13/2017 | COMPLETED |
| 03/13/2017 | REVISION - - 3RD | 11/16/2017 | ACTIVE |
| 03/23/2016 | PLANS OK TO SUBMIT - COMM | 03/23/2016 | COMPLETED |
| 03/23/2016 | COMMERCIAL - NEW | 05/31/2016 | COMPLETED |
| 05/31/2016 | RESUBMITTAL | 06/28/2016 | COMPLETED |
| 06/28/2016 | RESUBMITTAL | 07/05/2016 | COMPLETED |
| 07/06/2016 | REVISION - - 1ST | 08/26/2016 | COMPLETED |
| 08/26/2016 | REVISION - - 1ST | 10/04/2016 | COMPLETED |
| 10/04/2016 | REVISION - - 1ST | 10/31/2016 | COMPLETED |
| 10/31/2016 | REVISION - - 1ST | 11/03/2016 | COMPLETED |
| 11/03/2016 | REVISION - - 2ND | 11/07/2016 | COMPLETED |
| 11/07/2016 | REVISION - - 2ND | 12/22/2016 | COMPLETED |
| 12/22/2016 | REVISION - - 2ND | 02/15/2017 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM02176
Permit Status: C of o
Permit Description: NEW HOSPITAL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/23/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM02176
Permit Description: NEW HOSPITAL
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/28/2016 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | LEVEL #4 - 15 CONDUITS (3/4" TO 3 1/2") IN TWO RACKING SYSTEMS AT GL: 7/F - H |
| 12/28/2016 | SHEET ROCK NAILING | JBURGE | Approved | LEVEL #4 MAIN CORRIDOR - SOUTH WALL TWO HOUR RATED AT 12' DOWN FROM DECK ABOVE - GL: F.5/4.5 - 9.5; LEVEL #3 SHAFT ELECTRIC ROOM #035980; LEVEL #2 ELECTRIC ROOMS #0259801 AND 0259802, INTERIOR/EXTERIOR - OK TO TAPE. |
| 12/28/2016 | BUILDING - PROGRESS | JBURGE | Approved | LEVEL #R-2; SLAB - CLEAN AND PLACE CHAIRS - OK TO PLACE CONCRETE |
| 02/24/2017 | ELECTRIC - UFER | JBURGE | Approved | LEVEL #4: FEEDER #5 AT GL: G - M; RACK #4 AT GL: F - M; IDF AT GL: F-M. (7 CONDUITS) |
| 03/23/2017 | ELECTRIC - TEMPORARY SERVICE | JBURGE | Approved | PDU AT LEVEL 8, K; OK TO ENERGIZE UNIT. |
| 04/05/2017 | ELECTRIC - PROGRESS | JBURGE | Approved | CONTINUING CONDUITS (1" - 4") AT NORMAL ELECTRIC ROOM; EMERGENCY ELECTRIC ROOM; FIRE PUMP ROOM; CORRIDOR #0450610. |
| 07/21/2017 | BUILDING - FINAL | JBURGE | Approved | MASONRY PRE-GROUT: STEM WALLS FOR EQUIPMENT PADS: LEVEL #4, GL: 4.2/H - L. ENSURE ALL LOOSE CMU BLOCKS ARE SECURED WITH MORTAR. |
| 10/13/2017 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | LEVEL #1, 2" VACUUM LINES, 1" OXYGEN LINE, 1" MED GAS AT AMBULANCE BAY, EVS HALLWAY: TESTED AT 150 psi. LEVEL #3, 2" VACUUM LINES, 1" OXYGEN LINE, 1" MED GAS LINE: TESTED AT 150 psi (PEDIATRIC ROOMS). |
| 10/13/2017 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | LEVEL #1, TRAUMA AREA, GL: G.5/9 - 13, 10" HEATED HOT WATER SUPPLY AND RETURN. |
| 10/27/2017 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | PRIVATE WATER LINES (2 @ 12" AND 1 @ 8") FROM WARREN AVENUE NORTH APPROXIMATELY 150' TO AREA OF AMBULANCE CANOPY. |
| 11/08/2017 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | EQUIPMENT PAD CURBS (6 AREAS) ON LEVEL #4 - REBAR TO BE EPOXIED. OK TO GROUT PROGRESS AREAS. |
| 12/05/2017 | PLUMBING - ROOF DRAINS | JBURGE | Approved | ROOF DRAIN LINES IN THE AMBULANCE CORRIDOR AND THE FUTURE TRAUMA AREA (6" - 8" LINES). |
| 12/21/2017 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | LEVEL #4, GL: N/12; EDGE OF SLAB: FIRE CAULKED - TWO INCHES FROM TOP OF SLAB. LEVEL #3, AREAS #3, 6, 8, 10; FLOOR PENETRATIONS |
| 12/21/2017 | FRAMING | JBURGE | Approved | LEVEL #1, LOBBY AREA, COLUMNS AT MAIN ENTRY. LEVEL #7, TOWER #4, PATIENT BATHROOM CEILINGS. ALL BATHROOMS NEED TO BE CHECKED FOR FIRE CAULKING AROUND ELECTRIC CONDUITS. ADA ROOMS NOT READY (4 ROOMS). |
| 12/26/2017 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | LEVEL #4, TOWER #4, GL: H - K/8 - 10. ROUND DUCT SYSTEM AT 12" - 24" SYSTEM - OK TO INSULATE PROGRESS AREAS. |
| 12/28/2017 | PLUMBING - MEDICAL GAS/TEST | JBURGE | Approved | LEVEL #8, TOWER #4 (3/4" - 2" LINES); MEDICAL GAS, MEDICAL VACUUM, OXYGEN (PATIENT BURN ROOMS). LEVEL #2, TOWER #4, 6 PATIENT ROOMS (3/4" - 2" LINES), OXYGEN, MEDICAL VACUUM, MEDICAL AIR. |
| 12/29/2017 | PLUMBING - ABOVE CEILING | JBURGE | Approved | LEVEL #3, AREAS #7 - 10; DOMESTIC HOT AND COLD LINES (SUPPLY ONLY), LINES AT 1/2" T0 6", SHAFT #7, LEVEL #3 DOWN TO LEVEL #1. ALL LINES TESTED AT 150 PSI. OK T O INSULATE PROGRESS AREAS. |
| 12/29/2017 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | MAIN ELECTRIC ROOM: PANEL #4NBBL-S1, ATS-36; SWITCH GEAR # 4CABH-S2, S4ABH-S-1, 4CAAH-S2, 4CCAAH-S1; EMERGENCY SWITCH GEAR - ESS-4A; BUSS CDUCT AND TAP BOX AT LEVELS #4 TO LEVEL #1. |
| 07/20/2018 | FIRE - FINAL | JPEELDAVIS | Approved | Perfomed the commissioning of the fire pump. Test was performed by control head manufacturer representative, pump manufacturer representative and Kazal Fire. We could not verify the fire alarm signals from the fire pump.Electrical wiring was approved. |
| 08/03/2018 | BUILDING ABOVE CEILING | JBURGE | Approved | LEVEL #4, CSPD ROOMS; RT OFFICES, MEDITATION ROOM. OK TO SET CEILING TILES. |
| 12/19/2018 | ELECTRIC - UNDERGROUND | JBURGE | Approved | 1" conduits for 7 light pole caissons - South parking lot. Ok to cover progress areas. |
| 12/26/2018 | PLUMBING - INTERMEDIATE | JBURGE | Approved | Level #4. Blood Bank; waste and vent lines (2" - 4"), 4 each floor drains under air test. |
| 12/28/2018 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | Retention Basin #3: footings and rebar for retaining walls at 4' 9" - 5' 2". Ok to place concrete. |
| 02/07/2019 | PLUMBING - PROGRESS | JBURGE | Approved | |
| 02/07/2019 | SITE - SEWER | JBURGE | Approved | |
| 02/07/2019 | PLUMBING - MD GAS/PRECONST MTG | JBURGE | Approved | |
| 02/07/2019 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | |
| 02/07/2019 | ELECTRIC - TEMP POWER FOR TEST | JBURGE | Approved | |
| 02/07/2019 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | |
| 02/07/2019 | U VALUE FOR WINDOW | JBURGE | Approved | |
| 02/07/2019 | STUCCO MESH | JBURGE | Approved | |
| 02/25/2019 | MECHANICAL - HOODS | JBURGE | Approved | |
| 02/25/2019 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | |
| 04/05/2019 | PLUMBING - FINAL | JBURGE | Approved | |
| 04/05/2019 | PLUMBING - MEDICAL GAS/FINAL | JBURGE | Approved | |
| 04/05/2019 | ELECTRIC - FINAL | JBURGE | Approved | |
| 04/05/2019 | MECHANICAL - FINAL | JBURGE | Approved | |
| 04/10/2019 | HEALTH DEPT - FINAL 724-7908 | CTREVIL | Approved | |
| 04/10/2019 | ENGINEERING - FINAL | CTREVIL | Approved | FINAL WORK UNDER ACTIVITY DP15-0185 |