Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 04/10/2019 |
BUILDING - FINAL |
|
Approved |
A DPR representative will be coming to pick up their CERTIFICATE OF OCCUPANCY |
| 02/26/2019 |
BUILDING - FINAL |
|
Partial Approval |
Ok to make application for Temporary Certificate of Occupancy. Building inspections; Fire inspections; Engineering Inspections meet required criteria for this application. |
| 02/07/2019 |
BUILDING - FINAL |
|
Not ready for Inspection |
information only |
| 01/11/2019 |
BUILDING - FINAL |
|
Not ready for Inspection |
Called in by error. |
| 01/10/2019 |
BUILDING - FINAL |
|
Not ready for Inspection |
|
| 07/21/2017 |
BUILDING - FINAL |
|
Partial Approval |
MASONRY PRE-GROUT: STEM WALLS FOR EQUIPMENT PADS: LEVEL #4, GL: 4.2/H - L. ENSURE ALL LOOSE CMU BLOCKS ARE SECURED WITH MORTAR. |