Permit: T16CM02176

Parcel: 12310001H


Addresses:

1625 N CAMPBELL AV

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
04/10/2019 BUILDING - PROGRESS Approved
04/08/2019 BUILDING - PROGRESS Partial Approval Information only, pre-C of O conference. Proposed C o O application 10 April 2019.
04/05/2019 BUILDING - PROGRESS Partial Approval Information for open permits and current status
04/03/2019 BUILDING - PROGRESS Partial Approval Information for exterior lighting and completion of DP Plan
03/22/2019 BUILDING - PROGRESS Not ready for Inspection Exterior exit to stairway #4; hand and guard rails are incomplete.
03/20/2019 BUILDING - PROGRESS Partial Approval Plumbing intermediate; Level #3, Cold section, 3/4” water line tapped into 2” waste line for bone saw. Ok to cover progress areas
03/19/2019 BUILDING - PROGRESS Not ready for Inspection No inspections for today.
03/13/2019 BUILDING - PROGRESS Not ready for Inspection Permit update.
03/12/2019 BUILDING - PROGRESS Partial Approval C of O meeting with Banner construction staff
03/11/2019 BUILDING - PROGRESS Partial Approval Scheduling for pre certificate of occupancy meeting at 2:00 p.m.
12 March. 201. N Stone
03/08/2019 BUILDING - PROGRESS Not ready for Inspection No inspection performed
03/05/2019 BUILDING - PROGRESS Partial Approval Information only. Pre certificate of occupancy meeting. (Out door lighting ) 14 caisson light pole footings: North parking lot, West service area, South of loading dock on Cherry Road. Ok to place concrete.
03/04/2019 BUILDING - PROGRESS Partial Approval Site wall/screen wall footing for S.W.Gas at Ring Road and Warren Avenue. Ok to place concrete.
03/01/2019 BUILDING - PROGRESS Partial Approval Electrical information for laundry room at loading dock area
02/22/2019 BUILDING - PROGRESS Partial Approval Information for Temporary Certificate of Occupancy.
02/21/2019 BUILDING - PROGRESS Partial Approval Pre-temp certificate occupancy. Reschedule for 26 February.
02/20/2019 BUILDING - PROGRESS Partial Approval Information only. Will make request for TCO on 21 February.
02/12/2019 BUILDING - PROGRESS Not ready for Inspection Work incomplete
02/08/2019 BUILDING - PROGRESS Partial Approval Room check on Level #2.
Electric: Circuits without power: 2NBBL1-17, 19, 2CAAL3-1, 3, 4; CR30 - missing light switch, CR34 - light switch on west wall does not work.
Doors: Adjust closers: 240795, 240731, 240504, 240601, 240602, 240604.
250795 door drags on jamb, CR33 drags in top track. Restroom near 250730A needs closer. Hinges binding: 240504, 240611, door binging on vinyl threshold 240604. Adjust strike plate - 240605, 240606.
02/06/2019 BUILDING - PROGRESS Partial Approval Level #2 Electric: Circuits without power: 2NBAL4-63; 2NBBL1-74; 76; 45; 2CAAL1-6, 30, 34, 38, 68, 79, 81; 2NBBL3 1, 7; 2CABL2-13, 15, 17, 19, 20, 21, 29, 74; 2CABL3-8. 240712 Staff restroom (South) needs light switch. Control Room A (North) check operation of switch - works backwards. Doors: Adjust closers: 240404 stairwell #1, 240402, 240612, 240504, IR3 (West), IR2 (West). Adjust strike plate CI2. Need closers: CT1, 2, 3; IR1, IR2 (West), IR3 (East), CI6, CI1 (West), 240404, 240405. Missing wall door stop 240412. Binding hinges: 240613, 240612, 240504, 250133. MISC: 240403 need partitions and ADA grab bars.
02/04/2019 BUILDING - PROGRESS Partial Approval Level #1 - All areas except Kitchen area. Electric: circuits without power: 1NBBL1-9; 2 at Northwest micro-wave cabinet; 1NBBL1-27; corridor North of kitchen area; 1CAA1-2; 4; 6, 8, 10, 12, 19, 21, 25, 27, 29, 39, 65, 67, 69, 71, 73, 75, 77, 79, 81, 83; 1NBAL1-3, 11, 42, 46, ; Bulk storage #150502 (2 outlets); 1NBBL1-4, 1NBBL1-6; 1NBAL1-36 reset outlet in wall; light switch does not work in 140803. Doors: Adjust closers: Electric Room across from stair #4 door; Ante Room 157460; 150504 East; 150505 both doors; double doors West of women’s locker room; double doors next to conference room #150450; 140710; 140720 (2); 140724 (2); 150725 A & B. Pharmacy receiving West door will not close in the jamb; 150520 door drags on jamb; 150538 hinges bind. HVAC: Hazardous compounding room - no air flow.
01/31/2019 BUILDING - PROGRESS Not ready for Inspection Not ready for inspection (Level #2). Will begin inspections on Level #1 p 1 Feb 19.
01/30/2019 BUILDING - PROGRESS Partial Approval Level #3 - Southeast Quadrant Electric: 340731A - light switch required at South entry; CT Pump room 350588, no light switch at East entry. No power: 3CNAL1-70; 3CAAL1-72; 3CAAL3-30, 32, 34, 36; 3NBBL2-40 (open neutral); 3NBAL3-13; 3CAAL1-34; 30; 28. Doors: Adjust closers: 340634B, 340711 (East), 340713B, 350555, 350545 (East); 340726 - adjust open tension. 340732B (South) drags on jamb, will not close; 340725 door drags on jamb; 350588 West - drags on jamb, 350518 both doors drag on jamb (South); 350524A (West) drags on jamb; 350532B adjust strike plate on frame (West); 350532 East hinged bind. MISC: 350518 - floor requires lead shielding.
01/29/2019 BUILDING - PROGRESS Partial Approval Sheetrock nailing, Level #1, Future trauma area: East and North East walls - Ok to tape progress areas.
01/28/2019 BUILDING - PROGRESS Partial Approval Building progress: Level #3 (partial)
Note: All numbering listed below reflects the numbering as shown shown on the architectural plans.
Elecrtic: Outlets without power: 3NBBLI-57, 3CABLI-63, 3CABLI-67, 3NBBLI-8; 3NBBLI-6; 3NBBLI-4; 3NBAL7-82; 3CAAL7-17. 3CAAL7-57; PACU bay 350210-2 Emergency outlets (not labeled); 3NBAL7-35, 3CAALI-1; 3NBAL2-43; 3CABL6-57; 3NBAL2-41
Lighting: PRO3 (31404)-adjust can light for turn -on 3CAAHI-35; PRO1-can light does not turn-on (31406)
Doors: Adjust closer: 31024 (ADA). Quiet room 340200; 31450; 0351 stairs #1 (south, 340200 corridor North;
350330 West; 350380 restroom, 350291 restroom; 350314A, 350393, 350256, 350364 East,; 350501 South and adjust strike plate; 350504 South door; 350545 East and West, 350509 South; 350506; 350507. 31563 adjust doors to close
Binding: 350501 North East top hinge; 350508 top hinge; 31484 door drags on jamb; PR05-door drags in track.
350675 East in jamb; 350517 binds in jamb
Doors: Corridor 350010 double doors need closers; 350360 needs a door; Attach closers; 350502; 503, 506, 507, 511, 516
Misc: 350506 finish flooring; 340735 finish flooring and walls
01/25/2019 BUILDING - PROGRESS Not ready for Inspection Work incomplete.
01/24/2019 BUILDING - PROGRESS Partial Approval Building Progress-Partial: Room check, level #4
Electric:motion lights will not come on:450201, 450202, 450203
Doors: Adjust closers: Elevator lobby 440201-East 44301 (South). Rooms need doors: 440206, 450301; strive plate; 450302B-door near elevator binds on jamb; 450314B-Instrument storage pass through door; binds on jamb (East to West travel)
Automatic doors-no power
Misc: No signage
Room 440205-206: instal grab bars
01/23/2019 BUILDING - PROGRESS Partial Approval Building Progress: Partial; Room check, Level #5, Tower #4
Eletric:Circuit #5NBBL2-12, secure outlet to cabinet; open neutral; 5NBBL2-23, 5NBBL1-45 circuits without power: Room #50114, west wall unlabeled emergency outlet; 5NBBLI-29, 30, 31,33.
Room #109-motion light will not turn on, Room 54007 light (motion) will not turn on.
Doors: no pwer to automatic doors: Adjust cloers: 54001, 002, 005, 109; 50408- top hinge binds; stairwells #2, door sweep drags on concrete flooring; 540122-binds on jamb.
Misc: no room signage thorughout tower
01/22/2019 BUILDING - PROGRESS Partial Approval Level #5, Tower #5; Knuckle area.
Misc-no signage in knuckle area.
Electric: Circuits with no power: 9NBAL2-76, 5NBAL2-76
Patient rooms-bathrooms; motion activated lighting, turns on but will not reset;5101 Ante Room, 5106, 5117, 5122.
5118 bathroom-replace; 5119 south lighting (West lamp will not come on)
Doors: 5406 Attach closer; 5101 door binds on jamb; 5102-middle hinge binds; 5118 adjust side sweep-gouges flooring; double doors near 5128-south door-adjust closer; 5124 leaf-bottom sweep is off
01/18/2019 BUILDING - PROGRESS Partial Approval Room check, Level #6, Tower #4
Electric: Circuit #6NBBLI-29-no power. Bathroom motion lights do not turn on: 511, 513
Bathroom motion lights turn-on; will not reset: 502, 505, 517, 522.
Mechanical: Adjust air in isolation rooms and anti rooms.
Doors: 501 adjust closer will not close, 502 binds on the jamb, 503 leaf latch is broken; 505 top hinge binds, 5116 cart storage hinge binds, adjust closer; 5111 nourishment room binds on jamb; 508 closer drags on arm; 5108 staf toilet-adjust closer; 514 leaf hinge binds, 521 leaf binds on jamb.
01/17/2019 BUILDING - PROGRESS Partial Approval Room check, level #6, Tower #5
Electric: Emergency Lighting/exit lights are operational at power shutdown--Towers #4 & 5, knuckle are.
Circuits without power: 6NBALI-52; 6NBAL2-12, 14,15,16,17,18,19,21,22,25,29,42,45,46,48,52,59
Install can lighting in bathrooms 619, 623
Plumbing; no water in toilet staff bathroom (North)
Electric: All rooms with motion activated lighting, lights will turn on but will not reset; except for the following rooms: 614, 618, 619, 621, 622, 624.
Doors: Hinges binding: Knuckle waiting area door; 622, 624. Will not close: 601, 615, 613. Leaf latch is broken 606
Mechanical-Adjust air in rooms: 601, 601 ante room; 624, 624 ante room
Missing all signage
01/15/2019 BUILDING - PROGRESS Partial Approval Room Check, Level #7; Tower #4.

Electric: Emergency lighting/Exit signage in Towers 4 & 5; Knuckle area: operational during power shut down. Corrections of directional arrows to be effected when materials are received. Tower 4; patient bathrooms motion activated lighting turns on but will not shut off automatically: Rooms 726, 726 ante room, 727, 729, 731, 735, 739, 740, 741, 744, 746, 747, 747 ante room, 748 ante room.

Doors: Rooms 747, 748. Adjust leaf closers. Hall door to patient rooms - East door (South of ante room 147) middle hinge is binding.

Mechanical: Adjust air in isolation rooms 7125, 7128.

Misc: Room 146, patch screw holes in NE corner
01/14/2019 BUILDING - PROGRESS Partial Approval Building Progress: Room check on Level #7, Tower #5 (#1)
Electric: Emergency outlet (North of elevators)- no power.
Patient rooms-motion lighting in rooms 702, 722 does not work; room across from 722- light does not work. Finish outlet in room 701, Room 708 light above sink will not turn-on. Room #710, can light above door does not work; 718 night light will not work.
General; Room #701, finish tile; repair wall tile near sinks of both staff restrooms
Flooring: Finish/replace flooring in rooms 703, 705, 706, 709, 711, 713, 716, 717, 722
Doors: #706, 711 top hinge binding; 710 adjust closer-slow down; 708 door will not close; 710 door drags on leaf; 723, 720, 724A, 721 top hinge binding.
Plumbing-no water to toilets; 707; staff restrooms
All patient rooms need shower heads
01/11/2019 BUILDING - PROGRESS Partial Approval information only: Level 7, Tower 5 scheduled for 14 Jan 19.
01/10/2019 BUILDING - PROGRESS Partial Approval Room Check, Level #8, Tower #4.

West,

Electric; Patient bathroom motion lighting needs to be reset: Ante room 8125,
8125- 8130, 8132 - 8135. Emergency outlet, circuit #8CABL-32: no power. Nourishment Room “D”, could not reset GFCI outlet #8NBBL-40. Work stations at mid floor, no power.

Mechanical: Isolation Rooms and Ante Rooms (East and West) adjust air flow into rooms,

Plumbing: Staff restroom, no water to toilet.

EAST:

Electric:

Patient bathrooms, motion lighting needs to be reset: 8137, 8139, 8143 - 8148.
Install GFCI outlet in room 8143 bathroom. Nourishment Room “C” - no power in walls.

Plumbing: no water in break room.

General: complete tile work in 8143 bathroom. Ceiling tiles missing in rooms 8143 and 8145.

Note: Testing of Emergency lighting and Exit signage needs to be completed on Levels #9 and #8.
01/09/2019 BUILDING - PROGRESS Partial Approval Room Check: Level #8, Tower #5
All entries are to be under 1075 Building Progress.
East Knuckle Area, Electric: no power to wall outlets. East and North restrooms,
Motion activated lighting does not work.
North Patient Rooms: bathroom motion activated lighting does not work: 8102, 8104, 8112. Work stations (mid-floor) - no power. West corridor between North and South patient rooms - no power in walls; staff restrooms, motion lighting does not work.
Plumbing: no water to toilet in room 8109.
Flooring: finish flooring in rooms 8112 and 8113.
South Patient Rooms:
Electric: Patient bathrooms - motion lighting not working in rooms 8113 through 8124 ante room.
Doors: Room 8124, adjust closer, door closes too quickly
01/08/2019 BUILDING - PROGRESS Partial Approval Room Check, Level #9, Tower #5 (South); Patient Rooms : bathroom motion light activators do not work, #9113-9123. North wing patient rooms - bathroom light motion activators do not work: Rooms 9101-9105, 9107-9112. Nourishment room “B” motion lights do not work. East Knuckle area : no power in wall outlets in rooms: 207, 208, 403; 405, 407,410, 412-418.
Staff restroom West (North restroom), security lock is missing. Rooms 9106 and 9112: door latches stick, hard to open. Isolation Room #9124, door closer needs to be adjusted, does not fully close
Need to check emergency and exit lighting.
Pre TCO Floor check
11/27/2018 BUILDING - PROGRESS Partial Approval Level #4, single bathrooms (2) framing and MEP complete. Ok to sheetrock walls and ceilings.
10/24/2018 BUILDING - PROGRESS Partial Approval CMU. Site wall at South East corner of loading dock area: approximately 150 feet at 0' - 4' above stem wall. Ok to place grout.
09/24/2018 BUILDING - PROGRESS Partial Approval RING ROAD PROJECT: RETAINING WALL FOOTINGS: NORTH TO NORTH EAST, APPROXIMATELY 200 FEET; SOUTH TO NORTH (CENTRAL) APPROXIMATELY 50 FEET; BENCH WALL FOOTINGS, SOUTH - TO SOUTH WEST, APPROXIMATELY 100 FEET. LIGHT POLE CAISSON FOOTINGS (8) - OK TO PLACE CONCRETE IN PROGRESS AREAS.
08/10/2018 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: LEVEL #1, LOADING DOCK; DRAIN CURBS. OK TO PLACE CONCRETE
07/19/2018 BUILDING - PROGRESS Partial Approval STEM WALL/RETAINING WALLS. LEVEL #1, SOUTH LOADING DOCKS. 2 EACH RETAINING WALLS, 2 EACH RAMP WALLS. OK TO PLACE CONCRETE.
07/17/2018 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: ENTRANCE PAVALION: FOOTING AT GL: 4.7/A2.5 - A.5. DETAIL #13, PAGE S05.02. OK TO PLACE CONCRETE.
07/16/2018 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT - REBAR - LEVEL #1 (SOUTH) LOADING DOCK AREA - 3 BAY FOOTINGS. OK TO PLACE CONCRETE.
07/16/2018 BUILDING - PROGRESS Partial Approval
04/03/2018 BUILDING - PROGRESS Partial Approval NOTE: THIS INSPECTION WAS PERFORMED IN THE PARKING LOT NORTH OF THE CHILDREN'S CENTER: 8 LIGHT POLE CAISSON FOOTINGS. OK TO PLACE CONCRETE.
ELECTRIC UNDERGROUND: CONDUITS AND UFERS FOR 8 LIGHT POLE CAISSON FOOTINGS IN NORTH PARKING LOT.
01/08/2018 BUILDING - PROGRESS Partial Approval LEVEL #5, TOWER #5: ABOVE CEILING INSPECTIONS: ELECTRIC, PLUMBING, MECHANICAL. ENSURE ALL "J" BOXES ARE CLOSED UP AND TRASH REMOVED (MASKING PAPER).
11/13/2017 BUILDING - PROGRESS Partial Approval EXCVATION/LAYOUT REBAR: PIER CAPS AT AMBULANCE CANOPY - 9 EACH FOOTINGS. ENSURE FOOTINGS ARE FREE OF DEBRIS AND EXCESS DIRT BEFORE PLACEMANT OF CONCRETE.
10/30/2017 BUILDING - PROGRESS Not ready for Inspection AMULANCE CANOPY CAISSONS, NEED TO BE DRILLED.
10/27/2017 BUILDING - PROGRESS Partial Approval AMBULANCE CANOPY AREA: 9 CAISSON CAGES AT 26' 6" X 28"; FOOTINGS TO BE DRILLED.
10/11/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: SLAB ON GRADE AT GL: B - C/8 - 11. OK TO PLACE CONCRETE.
10/04/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: LEVEL #1, SLAB AT GL: M.5 - N/12 -13. OK TO PLACE CONCRRETE IN PROGRESS AREAS.
09/28/2017 BUILDING - PROGRESS Partial Approval ISO FOOTING, D AND B: GL: G/5.25 - 6.5
09/21/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: LEVEL #1, DEPRESSION AREAS (3 AREAS), GL: G/8 - 10; G/4.5 - 5.5; G/7.5 - 8. OK TO PLACE CONCRETE.
09/12/2017 BUILDING - PROGRESS Partial Approval LEVELS #2 - 4, SHAFT #3: M.E.P. - OK TO FRAME SHAFT.
09/05/2017 BUILDING - PROGRESS Partial Approval LEVEL #1, WEST SLAB IN AREA #1: INSPECTED 1 SEP17.
08/30/2017 BUILDING - PROGRESS Partial Approval STEM WALLS: LEVEL #1; GL: 4.2, AREA 3A POUR BACK WALL. LEVEL #4, GL: 9 - 10/J.7 - K.5 EQUIPMENT PAD...GROUTED.
08/25/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: FOOTING AT GL: 4.2/G - H: NEED DOWELING TO BE EPOXIED.
08/24/2017 BUILDING - PROGRESS Partial Approval PRE-SLAB DEPRESSIONS ON LEVEL #1: POUR BACK AT GL: G - H/11 - 12; I - I.5/10.5 - 12; I - J/8.5 - 9; L - L.5/9 - 10.
08/21/2017 BUILDING - PROGRESS Partial Approval LEVEL #4, STEM WALL FOR EQUIPMENT PAD AT GL: K/8 - 10, K/9.2 TO SHAFT #7. OK TO PLACE GROUT.
08/18/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: AREA 1-A; 3 DEORESSION POUR-BACKS. AREA #5, GL: I/4.2 - 8, 4.2/I - M; 8/I - K; M - J.5/7; M/7 - 4.2. OK TO PLACE CONCRETE. MEP'S ON LEVEL #5,TOWER #5 (ALL ROOMS). OK TO INSULATE AND SHEETROCK WALLS AND HARD LID CEILINGS.
08/17/2017 BUILDING - PROGRESS Partial Approval AREA 10AM STEEL COLUMNS DRY-PACKED. OK TO COVER
08/07/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB. LEVEL #1, AREA #3, GL: 9.5 - 12/G - K; 8 - 9/I - K. OK TO PLACE CONCRETE.
08/01/2017 BUILDING - PROGRESS Not ready for Inspection AREA #1 - 4 POUR-BACK AREAS; REBAR NOT IN PLACE.
07/31/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB AT LEVEL #1; AREA #1, 5 EACH POUR-BACKS INTO DEPRESSION AREAS. OK TO PLACE CONCRETE.
07/28/2017 BUILDING - PROGRESS Partial Approval PATIENT MOCK-UP ROOMS #10 AND 11 ON LEVEL #5 (ABOVE CEILING INSPECTIONS). OK TO COVER CEILINGS.
07/25/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: SLAB IN AREA #2, GL: C.5 - G/8 - 12; 8 - 8.6/E - G. OK TO PLACE CONCRETE.
07/24/2017 BUILDING - PROGRESS Partial Approval AREA #2; PRE-SLAB (DEPRESSION AREA CORRECTED) - OK TO PLACE CONCRETE.
07/17/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB IN AREA #1, AT GL: 4.2 - 8/E - G; OK TO PLACE CONCRETE.
07/12/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: LEVEL #1 SLAB AREA AT GL: 4 - 5/B - D; B - E/5 - 8, SLAB ON GRADE: OK TO PLACE CONCRETE.
07/06/2017 BUILDING - PROGRESS Partial Approval SHAFT #1; MEP IN PLACE. OK TO CLOSE UP SHAFT.
06/12/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR - PARTIAL - LOADING DOCK AREA SLAB AT GL: L.5 - N/4.2 - 10. OK TO PLACE CONCRETE IN PRGRESS AREA.
05/25/2017 BUILDING - PROGRESS Not ready for Inspection WORK INCOMPLETE. LOADING DOCK 6 BAYS
05/24/2017 BUILDING - PROGRESS Partial Approval MASONRY EQUIPMENT CURBS AT LEVEL #4, GL: L/9. OK TO EPOXY REBAR AND GROUT.
05/23/2017 BUILDING - PROGRESS Not ready for Inspection EXCAVATION/LAYOUT REBAR. 6 LOADING DOCK BAYS NOT READY. WORK INCOMPLETE.
05/22/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT - REBAR: STEM WALL AT GL: C/14 - 16. OK TO PLACE COCRETE.
05/19/2017 BUILDING - PROGRESS Partial Approval STEM WALLS AT GL: C/13 - 14; GL: G/14 - 16. OK TO PLACE CONCRETE
05/18/2017 BUILDING - PROGRESS Not ready for Inspection STEM WALL AT GL: G/14 - 16 NOT READY, WORK IS INCOMPLETE.
05/17/2017 BUILDING - PROGRESS Partial Approval STEM WALL FOOTING AT GL: 4.2/L.5 - N. OK TO PLACE CONCRETE.
05/17/2017 BUILDING - PROGRESS Partial Approval VISITORS ELEVATORS (#13 AND #14), LEVELS 4 - 8, EAST AND NORTH WALLS. LEVEL #3, ELECTRIC ROOMS #0359810, 0359903,; LEVEL #2, ELECTRIC ROOMS; 0259903, 0259810. LEVEL #2; PRIORITY WALLS FOR ROOMS #025011 - 0250703, 0250715 - 2050723. OK TO ONE SIDE SHEET ROCK AND TAPE PROGRESS AREAS..
05/16/2017 BUILDING - PROGRESS Partial Approval STEM WALL AT GL: 12/L - N; OK TO PLACE CONCRETE
05/15/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: STEM WALL FOOTINGS AT GL: C/14, G/14. OK TO PLACE CONCRETE IN PROGRESS AREAS.
05/10/2017 BUILDING - PROGRESS Partial Approval SEPARATION WALL IN LEVEL #4 ELECTRIC ROOM AT GL: 7/M - N. OK TO COVER WALL (2 LAYERS OF SHEET ROCK REQUIRED).
05/03/2017 BUILDING - PROGRESS Not ready for Inspection STEM WALL (REBAR AND FORMS) AT GL: L.5/9 - 12
05/02/2017 BUILDING - PROGRESS Partial Approval STEM WALL AT GL: L.5 - M/9 - 12. OK TO PLACE CONCRETE.
04/28/2017 BUILDING - PROGRESS Partial Approval STEM WALL AT GL: L.5/4 - 9. OK TO PLACE CONCRETE.
04/25/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: FOOTINGS AT GL: L.5/5 - 10, 12/L - N. OK TO PLACE CONCRETE IN PROGRESS AREAS.
04/24/2017 BUILDING - PROGRESS Not ready for Inspection NOT RREADY AT FOOTING ON GL: 5 - 10/M. PLEASE RECALL FOR 25 APRIL.
04/21/2017 BUILDING - PROGRESS Partial Approval 6" STEM WALL T GL: I.5 - L/12. OK TO PLACE CONCRETE.
04/18/2017 BUILDING - PROGRESS Partial Approval LOADING DOCK STEM WALL AT GL: M/7 - 10; 10/M - N. OK TO PLACE CONCRETE.
04/17/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR - PARTIAL - FOOTING AT STAIRWELL #2.
04/13/2017 BUILDING - PROGRESS Partial Approval LEVEL #4, STAFF ELEVATOR SHAFT: EAST, WEST, NORTH WALLS, FIRE CAULKED: SOUTH WALL TO BE COMPLETED.
04/12/2017 BUILDING - PROGRESS Partial Approval COLUMN WRAPS (4) AT GL: 13/J - M. OK TO WRAP AND POUR COLUMNS.
04/02/2017 BUILDING - PROGRESS Partial Approval GRADE BEAM AT LINE I; OK TO POUR. COUMN WRAPS AT GL: G/13, G/13.5, I/13.
03/29/2017 BUILDING - PROGRESS Partial Approval EXCAVATION/LAYOUT REBAR: LOADING DOCK FOOTING AT GL: M/4.2 - 7. LEVEL #4: RAMP TO EXISTING BUILDING AT GL: G/14. OK TO POUR PROGRESS AREAS. GRADE BEAM AT GL: J IS NOT READY.
03/16/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: POUR BACK SLABS AT LEVELS 2 AND 3; GL: E - G/14; 14/E - G. LEVEL #4 AT GL: 14.6/E.2 - H. NOTE: ANGLE IRON AT GL: 14.6/G NEEDS TO BE CUT DOWN BELOW THE FLOOR HEIGHT (OVER 5 3/4".
03/15/2017 BUILDING - PROGRESS Partial Approval LEVEL #10, SLAB #10.3, GL: 9 -13/G - N.2. CLEAN AND PLACE CHAIRS WHERE NEEDED. NOTE: WEST WALLS - NORTHWEST AREA; DOWELS NEED TO BE BENT DOWN BELOW 6" SLAB HEIGHT.
03/14/2017 BUILDING - PROGRESS Partial Approval SLAB #9.3 WAS INSPECTED ON 3-13-17 (SEE PREVIOUS INSPECTION RESULTS).
03/13/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: LEVEL #9, SLAB 9.3: CLEAN AREA, CHAIRS TO BE IN PLACE; TRIM REBAR EXTENDING INTO OPENING AT GL: L.5/10 - 11. OK TO PLACE CONCRETE.
03/08/2017 BUILDING - PROGRESS Partial Approval BUILDING PRE-SLAB: LEVEL #8; AREA 8.3: GL: 9- 13/G - N. OK TO PLACE CONCRETE.
03/07/2017 BUILDING - PROGRESS Partial Approval INSULATION SECURED BYWIRE AT PARAPET WALLS (LEVEL 4; GL: B/4.2 - 7). THREE EACH DOGHOUSES.
02/28/2017 BUILDING - PROGRESS Partial Approval LEVEL #7, SLAB #7.3 AT GL: G - N/10 - 14. CORRECTIONS REQUIRED: OPENINGS (CORNERS) AT GL: 5.13; 11/11.25 - PATCH METAL DECKING AT LOCATIONS.
02/21/2017 BUILDING - PROGRESS Partial Approval COLUMNS (5) FORMS IN PLAE: GL N/6 - 10. OK TO POUR. GRADE BEAM IS NOT READY FOR INSPECTION.
02/16/2017 BUILDING - PROGRESS Partial Approval LEVEL 5, SLAB 5.4: GL: G-I/10-13, G - G.5/13 - 14, G/13 - 14, G/9 - 10. PATCH DECK AREAS AT OPENING CORNERS AT GL: L,75/11 - 12. OK TO PLACE CONCRETE.
02/15/2017 BUILDING - PROGRESS Partial Approval LEVEL #4, EQUIPMENT PAD AT GL: M.5 - 11.25. OK TO PLACE CONCRETE
02/13/2017 BUILDING - PROGRESS Partial Approval REBAR CAGES FOR COLUMNS AT GL: M/7 - 9 (3); N/5 - 9 (5). OK TO SET COLUMN FORMS AND PLACE CONCRETE.
02/09/2017 BUILDING - PROGRESS Partial Approval LEVEL 4, SLAB AT AREA 4.7: GL: 8.25 - 13/H - J. SLABS AT LEVEL #5, AREA 5.4 IS NOT READY FOR INSPECTION.
02/08/2017 BUILDING - PROGRESS Partial Approval LEVEL #3, SLAB 3.7 AT GL: 8/J -M; J/8 - 13: NEED TO PATCH DECK AT GL: G/8; DOWELS ARE TOO HIGH AT GL: J/8.5, LOWER DOWELS IN SOUTH WEST CORNER.
02/01/2017 BUILDING - PROGRESS Partial Approval STEM WALL AT GL: 4.2/G - K. OK TO PLACE CONCRETE.
01/31/2017 BUILDING - PROGRESS Partial Approval SLAB AT LEVEL #2; 2.7 GL: N - J/ 8.75 - 13. COLUMN M/13 (SOUTH SIDE) PATCH GAP IN DECKING. DOWELS AT GL: 11/N NEED TO BE TURNED DOWN - ABOVE FINISHED FLOOR LEVEL
01/25/2017 BUILDING - PROGRESS Partial Approval LEVEL 1, S.O.G. AT ELEVATOR AREAS AT GL: 10.75 - 13/ C - G; 10.75/E.75; E.75/ 10.75 - 12.5; 10.75 - 12/B.5 - C; 12 - 13/C - G. OK TO PLACE CONCRETE IN PROGRESS AREAS.
01/24/2017 BUILDING - PROGRESS Partial Approval LEVEL #4, SLAB 4.5 - CLEAN, SET CHAIRS AND DISPLACE REAIN WATER. OK TO PLACE CONCRETE
01/18/2017 BUILDING - PROGRESS Partial Approval LEVEL #5; SLAB #5.6: GL: 9 - 10/G - J. CLEAN DECK AREA; REMOVE STANDING WATER; PATCH DECK AT AREAS WHERE ANGLE IRON POSTS FOR SECURITY BARRIER WERE REMOVED.
01/05/2017 BUILDING - PROGRESS Partial Approval LEVEL #2: AREA 2.5 SLAB: CORRECTIONS TO BE MADE 1. COLUMN #13/G - PATCH DECK ON EAST SIDE. 2. RE-WELD NELSON STUD - BROKEN LOOSE AT GL: 13/I.5. 3. REMOVE WATER AT LOCATION H/9.
01/04/2017 BUILDING - PROGRESS Partial Approval SLAB ON LEVEL #4 (4.6) AT GL: 4.2 - 8.25/J - N: GENERAL CLEAN UP; REMOVE WATER AT GL: K/5 - 8.25.
12/28/2016 BUILDING - PROGRESS Partial Approval LEVEL #R-2; SLAB - CLEAN AND PLACE CHAIRS - OK TO PLACE CONCRETE
12/21/2016 BUILDING - PROGRESS Not ready for Inspection lEVEL 10.2, SLAB NOT READY TO PLACE CONCRETE
10/04/2016 BUILDING - PROGRESS Partial Approval 4TH LEVEL SLAB AT GL: B - F.75/ 4.2 - 7.5. OK TO PLACE CONCRETE IN PROGRESS AREA.
10/03/2016 BUILDING - PROGRESS Partial Approval LEVEL 3 SLAB: GL: B - F.75/ 4 - 7.5. OK TO PLACE CONCRETE
09/09/2016 BUILDING - PROGRESS Partial Approval METAL DECK SYSTEM ON LEVEL #2; GL: 4.2 - 7/B - G. OK TO POUR PROGRESS AREA.
08/18/2016 BUILDING - PROGRESS Not ready for Inspection CONTRACTOR CANCELLED.
08/03/2016 BUILDING - PROGRESS Partial Approval INFORMATION ONLY; RESULTS OF BOLT INSPECTIONS BY WESTERN TECH.
08/02/2016 BUILDING - PROGRESS Partial Approval INFORMATION ONLY - STEEL ERRECTION SCHEDULE
08/01/2016 BUILDING - PROGRESS Partial Approval INFORMATION ONLY