Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/10/2019 | ENGINEERING - FINAL | Approved | FINAL WORK UNDER ACTIVITY DP15-0185 | |
| 04/09/2019 | ENGINEERING - FINAL | Partial Approval | THIS SITE HAS BEEN CHECKED FOR THE FULL RELEASE OF THE BUILDING FOR OCCUPENCY. IT IS FOUND TO BE ACCEPTABLE AT THIS TIME, ANY REMAINING ITEMS WILL BE TRANSFERED TO THE DEVELOPMENT PACKAGE DP15-0185 AND WILL BE INSPECTED AND APPROVED PRIOR TO THE FINAL APPROVAL OF THE DP. | |
| 04/08/2019 | ENGINEERING - FINAL | Partial Approval | SITE TO CONGESTED FOR A SITE INSPECTION AT THIS TIME, WILL PERFORM THE INSPECTION TOMORROW 4/9/19. | |
| 04/05/2019 | ENGINEERING - FINAL | Partial Approval | DROVE THROUGH THE SITE AND LOOKED AT WHAT WORK IS REMAINING. THEY ARE SETTING UP FOR THE WEEKEND EVENTS AT THIS TIME AND HAVE FENCED OFF ALL AREAS THAT ARE UNDER CONSTRUCTION BEST AS POSSIBLE. I WILL REINSPECT THIS SITE FULLY ON 4/8/19 IF POSSIBLE DEPENDING HOW CLEAR THE SITE IS AT THAT TIME FROM THE WEEKEND FESTIVITIES. |