| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/07/2019 | ELECTRIC - UNDERGROUND | Approved | ||
| 12/19/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 1" conduits for 7 light pole caissons - South parking lot. Ok to cover progress areas. | |
| 12/13/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 1" conduits and ufers for 4 light pole caisson footings. C.U.P. parking area. Ok to cover. | |
| 11/13/2018 | ELECTRIC - UNDERGROUND | Partial Approval | SW lift station, South of loading dock; 4 each 1" conduits. Ok to cover progress area. | |
| 10/02/2018 | ELECTRIC - UNDERGROUND | Partial Approval | Ring Road Project): 4 each conduits (3/4"- 1") in each wall for lighting - Ok to cover. | |
| 08/29/2018 | ELECTRIC - UNDERGROUND | Partial Approval | EAST LOADING DOCK AREA: 8 EACH 1" CONDUITS; 2 EACH 1 1/4" CONDUITS; 1 EACH 3" CONDUIT (TO VAULT). OK TO COVER PROGRESS AREA. | |
| 05/17/2018 | ELECTRIC - UNDERGROUND | Partial Approval | NORTHWEST CORNER OF BUILDING TO NORTHWEST PARKING GARAGE: CONDUITS: 2 @ 2" AND 2 @ 4", APPROXIMATELY 50' ON U OF A SIDE OF FENCE. OK TO COVER TRENCH. | |
| 05/15/2018 | ELECTRIC - UNDERGROUND | Partial Approval | NORTH WEST AREA FROM MAIN BUILDING TO NORTHWEST GARAGE (SOUTH SIDE) 2 @ 2" CONDUITS ; 2 @ 4" CONDUITS: APPROXIMATEL 50 FEET. OK TO COVER PROGRESS AREA.. | |
| 05/04/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 2 EACH 4" CONDUIT LINES (APPROXIMATELY 240') FROM WEST SHAFT TO SOUTH EAST AREA OF NORTH WEST PARKING GARAGE. TRENCHING APPROXIMATELY 4' DEEP. OK TO BACK-FILL. | |
| 03/13/2018 | ELECTRIC - UNDERGROUND | Partial Approval | LEVEL #1, PHARMACY AREA - 2 EACH 1 1/4" CONDUITS AT GL: H/9-10. OK TO COVER PROGRESS AREA. | |
| 07/26/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUITS AND FRAMES FOR ELECTRIC ROOMS: 0159804, AND 1590805; 2" CONDUIT AT GL: M - N/11 - 12. OK TO COVER PROGRESS AREAS. | |
| 07/25/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 25 EACH 1" CONDUITS AT GL: K - L/5 - 6; LEVEL #1. OK TO COVER PROGRESS AREA. | |
| 07/21/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUITS (13 AT 1") GL: J - M/8 - 10; 3" JUMPER CONDUITS (6) FOR ROOMS #159804, 159805. LEVEL #1. OK TO COVER PROGRESS AREAS. | |
| 07/20/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUITS FOR ELECTRIC ROOM #159804, 159805 (3 CONDUITS AT 1 1/2", 15 CONDUITS AT 3", 2 CONDUITS AT 4") MAIN FEEDERS AT GL: J - K/5 -6. OK TO COVER PROGRESS AREA. | |
| 07/17/2017 | ELECTRIC - UNDERGROUND | Partial Approval | TWO EACH 4" ELECTRIC CONDUITS AT GL: H/6 - 10. OK TO COVER PROGRESS AREA. | |
| 07/14/2017 | ELECTRIC - UNDERGROUND | Partial Approval | IDF ROOM (1", 2", 4") CONDUITS AT GL: G/5 - 11. OK TO COVER PROGRESS AREAS. | |
| 07/13/2017 | ELECTRIC - UNDERGROUND | Partial Approval | IDF ROOM (1" - 4" CONDUITS), AT GL: 5 - 11/H - G; MAIN FEEDERS AT GL: 8 - 9/I - J. OK TO COVERPROGRESS AREAS. | |
| 07/11/2017 | ELECTRIC - UNDERGROUND | Partial Approval | IDF ROOM #0149902; MAIN FEEDER AT GL: J/10 - I/9. OK TO COVER 1 1/2" CONDUIT. | |
| 07/07/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUIT LINES (3/4" - 3") AT GL: 10/F - L; 12/H - M. OK TO COVER PROGRESS AREAS. | |
| 06/29/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUITS AT 1" - 4" AT GL: 9 - 11/G - I. OK TO COVER PROGRESS AREA. | |
| 06/27/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUITS AT GL: K - L/5 - 6: CONDUITS: 14 @ 1", 3 @ 1 1/2", 1 @ 2 1/2", 15 @ 3", 2 @ 4". OK TO COVER PROGRESS AREAS. | |
| 06/21/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUITS (1 @ 1 1/2", 1 @ 2 /1/2") FOR IDF ROOM AT GL: 5/E. OK TO COVER PROGRESS AREA.. | |
| 06/20/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUIT LINES: 1 @ 6"; 1 @ 1 1/2"; 2 @ 4" AT GL: 4.2 - 5/D - G. OK TO COVER PROGRESS AREAS. | |
| 06/16/2017 | ELECTRIC - UNDERGROUND | Partial Approval | FIRST FLOOR BOTH ELECTRICAL ROOMS JUMPERS OK TO COVER. ELEVATOR CONDUITS FROM G-10 TO G-12 OK TO COVER. | |
| 06/15/2017 | ELECTRIC - UNDERGROUND | Partial Approval | UNDERGROUND ELECTRIC COLUMN LINE D5 THROUGH G10 OK TO BACKFILL. | |
| 06/09/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 3/4" CONDUIT LINES (6) AT DOCK LEVELERS, FOR POWER. OK TO COVER PROGRESS AREAS. | |
| 06/08/2017 | ELECTRIC - UNDERGROUND | Partial Approval | ELECTRIC ROOM #150801 - 5 MAIN POWER CONDUITS (3") IN TRENCH UP TO RACK - OK TO COVER: GL: 9/F - G. | |
| 06/07/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUIT LINES ( 14 AT 1", 1 AT 1 1/2") AT GL: D - F/9 -10 | |
| 06/05/2017 | ELECTRIC - UNDERGROUND | Partial Approval | CONDUIT LINES AT LEVEL #1; GL: C - D/6 - 10: 4 LINES EACH AT 2 1/2"; 4 LINES AT 1" EACH; 2 LINES EACH AT 2" - OK TO COVER PROGRESS AREAS. | |
| 03/13/2017 | ELECTRIC - UNDERGROUND | Partial Approval | VAULT (SOUTH) AREA: 6 @ 6" LINES OUT; 4 EACH CONDUIT LINES SET AT 45 DEGREE ANGLES. OK TO COVER PROGRESS AREA. | |
| 03/12/2017 | ELECTRIC - UNDERGROUND | Partial Approval | TEP VAULT: 2 @ 6" CONDUITS INTO VAULT; 2 @ 6" OUT OF VAULT (SOUTH); EAST 4 @ 6" AND 5 @ 1" CONDUITS OUT OF VAULT. SOUTH VAULT: 6 @ 6" IN/OUT OF VAULT. OK TO COVER CONDUITS. | |
| 03/08/2017 | ELECTRIC - UNDERGROUND | Partial Approval | SOUTH AREA OF TEP VAULT: CONDUITS: 2 EACH 6"; 5 EACH 4"; 5 EACH 1". OK TO COVER PROGRESS AREAS. | |
| 03/07/2017 | ELECTRIC - UNDERGROUND | Partial Approval | SOUTH EAST CORNER OF BUILDING: GL: N/12 - 14: 4 EACH 6" CONDUIT LINES. OK TO COVER PROGESS AREAS. | |
| 03/06/2017 | ELECTRIC - UNDERGROUND | Partial Approval | EAST SIDE OF TEP VAULT - CONDUITS AND STUB-UPS: CONDUITS: 7 EACH 6"; 5 EACH 4"; 16 EACH 1". OK TO PLACE SLURRY IN PROGRESS AREA. | |
| 02/27/2017 | ELECTRIC - UNDERGROUND | Partial Approval | ELECTRIC CONDUITS: 14 @ 1"; 1 @ 5"; 1 @ 4"; 5 @ 1": SOUTH WEST CORNER AT TEP VAULT. OK TO PLACE SLURRY. EMERGENCY SHP CONDUIT AT GL: GL: 4.2 - 5/ K - L; 15 @ 3"; 2 @4"; 3 @ 1 1/2"; 1 @ 2 1/2"; 14 @ 1". OK TO BACK FILL PROGRESS AREA. |
|
| 02/21/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 4 EACH 4: CONDUIT STUB-UPS, 1 EACH 6" CONDUIT AT GL: L.5/M.5. SOUTH AREA: 5 EACH 5" CONDUITS; 4 EACH 4", 10 EACH 3", AND 12 EACH 1" CONDUITS. | |
| 02/13/2017 | ELECTRIC - UNDERGROUND | Partial Approval | 16 EACH 4" STUB-UP CONDUITS AT GGL: 4/L.25. OK TO COVER PROGRESS AREA. | |
| 02/08/2017 | ELECTRIC - UNDERGROUND | Partial Approval | APPROXIMATELY 25' OF ELECTRICAL CONDUITS; 16 EACH AT 4", 1 AT 5": GL4/L - M. OK TO COVER PROGRRESS AREA. | |
| 02/06/2017 | ELECTRIC - UNDERGROUND | Not ready for Inspection | WILL RECALL FOR 7 FEB 07 | |
| 02/03/2017 | ELECTRIC - UNDERGROUND | Partial Approval | COLUMN LINE J TO K AND 20' SOUTH OK TO POUR OVER 4'' CONDUITS. | |
| 02/01/2017 | ELECTRIC - UNDERGROUND | Partial Approval | DUCT BANK SYSTEM: 16 @ 4" CONDUITS AT GL: 3.8/G - I. (WEST DUCT BANK) OK TO PLACE CONCRETE. | |
| 01/27/2017 | ELECTRIC - UNDERGROUND | Not ready for Inspection | DUCT BANK AT GL: 4.2. NOT READY. ADDITIONAL SHORING (BOX) AT AREA WHERE TRENCH MAKES A 90 DEGREE TURN. | |
| 01/20/2017 | ELECTRIC - UNDERGROUND | Partial Approval | WEST DUCT BANK AREA: 14 EACH 6" CONDUITS (20') AT GL: H/1 - 2. OK TO PLACE CONCRETE. |