Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T16CM02176

Parcel: 12310001H


Addresses:

1625 N CAMPBELL AV

Inspection Status: Approved

Inspection History: ELECTRIC - UNDERGROUND

Date Description Inspector Results Comments
02/07/2019 ELECTRIC - UNDERGROUND Approved
12/19/2018 ELECTRIC - UNDERGROUND Partial Approval 1" conduits for 7 light pole caissons - South parking lot. Ok to cover progress areas.
12/13/2018 ELECTRIC - UNDERGROUND Partial Approval 1" conduits and ufers for 4 light pole caisson footings. C.U.P. parking area. Ok to cover.
11/13/2018 ELECTRIC - UNDERGROUND Partial Approval SW lift station, South of loading dock; 4 each 1" conduits. Ok to cover progress area.
10/02/2018 ELECTRIC - UNDERGROUND Partial Approval Ring Road Project): 4 each conduits (3/4"- 1") in each wall for lighting - Ok to cover.
08/29/2018 ELECTRIC - UNDERGROUND Partial Approval EAST LOADING DOCK AREA: 8 EACH 1" CONDUITS; 2 EACH 1 1/4" CONDUITS; 1 EACH 3" CONDUIT (TO VAULT). OK TO COVER PROGRESS AREA.
05/17/2018 ELECTRIC - UNDERGROUND Partial Approval NORTHWEST CORNER OF BUILDING TO NORTHWEST PARKING GARAGE: CONDUITS: 2 @ 2" AND 2 @ 4", APPROXIMATELY 50' ON U OF A SIDE OF FENCE. OK TO COVER TRENCH.
05/15/2018 ELECTRIC - UNDERGROUND Partial Approval NORTH WEST AREA FROM MAIN BUILDING TO NORTHWEST GARAGE (SOUTH SIDE) 2 @ 2" CONDUITS ; 2 @ 4" CONDUITS: APPROXIMATEL 50 FEET. OK TO COVER PROGRESS AREA..
05/04/2018 ELECTRIC - UNDERGROUND Partial Approval 2 EACH 4" CONDUIT LINES (APPROXIMATELY 240') FROM WEST SHAFT TO SOUTH EAST AREA OF NORTH WEST PARKING GARAGE. TRENCHING APPROXIMATELY 4' DEEP. OK TO BACK-FILL.
03/13/2018 ELECTRIC - UNDERGROUND Partial Approval LEVEL #1, PHARMACY AREA - 2 EACH 1 1/4" CONDUITS AT GL: H/9-10. OK TO COVER PROGRESS AREA.
07/26/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUITS AND FRAMES FOR ELECTRIC ROOMS: 0159804, AND 1590805; 2" CONDUIT AT GL: M - N/11 - 12. OK TO COVER PROGRESS AREAS.
07/25/2017 ELECTRIC - UNDERGROUND Partial Approval 25 EACH 1" CONDUITS AT GL: K - L/5 - 6; LEVEL #1. OK TO COVER PROGRESS AREA.
07/21/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUITS (13 AT 1") GL: J - M/8 - 10; 3" JUMPER CONDUITS (6) FOR ROOMS #159804, 159805. LEVEL #1. OK TO COVER PROGRESS AREAS.
07/20/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUITS FOR ELECTRIC ROOM #159804, 159805 (3 CONDUITS AT 1 1/2", 15 CONDUITS AT 3", 2 CONDUITS AT 4") MAIN FEEDERS AT GL: J - K/5 -6. OK TO COVER PROGRESS AREA.
07/17/2017 ELECTRIC - UNDERGROUND Partial Approval TWO EACH 4" ELECTRIC CONDUITS AT GL: H/6 - 10. OK TO COVER PROGRESS AREA.
07/14/2017 ELECTRIC - UNDERGROUND Partial Approval IDF ROOM (1", 2", 4") CONDUITS AT GL: G/5 - 11. OK TO COVER PROGRESS AREAS.
07/13/2017 ELECTRIC - UNDERGROUND Partial Approval IDF ROOM (1" - 4" CONDUITS), AT GL: 5 - 11/H - G; MAIN FEEDERS AT GL: 8 - 9/I - J. OK TO COVERPROGRESS AREAS.
07/11/2017 ELECTRIC - UNDERGROUND Partial Approval IDF ROOM #0149902; MAIN FEEDER AT GL: J/10 - I/9. OK TO COVER 1 1/2" CONDUIT.
07/07/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUIT LINES (3/4" - 3") AT GL: 10/F - L; 12/H - M. OK TO COVER PROGRESS AREAS.
06/29/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUITS AT 1" - 4" AT GL: 9 - 11/G - I. OK TO COVER PROGRESS AREA.
06/27/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUITS AT GL: K - L/5 - 6: CONDUITS: 14 @ 1", 3 @ 1 1/2", 1 @ 2 1/2", 15 @ 3", 2 @ 4". OK TO COVER PROGRESS AREAS.
06/21/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUITS (1 @ 1 1/2", 1 @ 2 /1/2") FOR IDF ROOM AT GL: 5/E. OK TO COVER PROGRESS AREA..
06/20/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUIT LINES: 1 @ 6"; 1 @ 1 1/2"; 2 @ 4" AT GL: 4.2 - 5/D - G. OK TO COVER PROGRESS AREAS.
06/16/2017 ELECTRIC - UNDERGROUND Partial Approval FIRST FLOOR BOTH ELECTRICAL ROOMS JUMPERS OK TO COVER. ELEVATOR CONDUITS FROM G-10 TO G-12 OK TO COVER.
06/15/2017 ELECTRIC - UNDERGROUND Partial Approval UNDERGROUND ELECTRIC COLUMN LINE D5 THROUGH G10 OK TO BACKFILL.
06/09/2017 ELECTRIC - UNDERGROUND Partial Approval 3/4" CONDUIT LINES (6) AT DOCK LEVELERS, FOR POWER. OK TO COVER PROGRESS AREAS.
06/08/2017 ELECTRIC - UNDERGROUND Partial Approval ELECTRIC ROOM #150801 - 5 MAIN POWER CONDUITS (3") IN TRENCH UP TO RACK - OK TO COVER: GL: 9/F - G.
06/07/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUIT LINES ( 14 AT 1", 1 AT 1 1/2") AT GL: D - F/9 -10
06/05/2017 ELECTRIC - UNDERGROUND Partial Approval CONDUIT LINES AT LEVEL #1; GL: C - D/6 - 10: 4 LINES EACH AT 2 1/2"; 4 LINES AT 1" EACH; 2 LINES EACH AT 2" - OK TO COVER PROGRESS AREAS.
03/13/2017 ELECTRIC - UNDERGROUND Partial Approval VAULT (SOUTH) AREA: 6 @ 6" LINES OUT; 4 EACH CONDUIT LINES SET AT 45 DEGREE ANGLES. OK TO COVER PROGRESS AREA.
03/12/2017 ELECTRIC - UNDERGROUND Partial Approval TEP VAULT: 2 @ 6" CONDUITS INTO VAULT; 2 @ 6" OUT OF VAULT (SOUTH); EAST 4 @ 6" AND 5 @ 1" CONDUITS OUT OF VAULT. SOUTH VAULT: 6 @ 6" IN/OUT OF VAULT. OK TO COVER CONDUITS.
03/08/2017 ELECTRIC - UNDERGROUND Partial Approval SOUTH AREA OF TEP VAULT: CONDUITS: 2 EACH 6"; 5 EACH 4"; 5 EACH 1". OK TO COVER PROGRESS AREAS.
03/07/2017 ELECTRIC - UNDERGROUND Partial Approval SOUTH EAST CORNER OF BUILDING: GL: N/12 - 14: 4 EACH 6" CONDUIT LINES. OK TO COVER PROGESS AREAS.
03/06/2017 ELECTRIC - UNDERGROUND Partial Approval EAST SIDE OF TEP VAULT - CONDUITS AND STUB-UPS: CONDUITS: 7 EACH 6"; 5 EACH 4"; 16 EACH 1". OK TO PLACE SLURRY IN PROGRESS AREA.
02/27/2017 ELECTRIC - UNDERGROUND Partial Approval ELECTRIC CONDUITS: 14 @ 1"; 1 @ 5"; 1 @ 4"; 5 @ 1": SOUTH WEST CORNER AT TEP VAULT. OK TO PLACE SLURRY.

EMERGENCY SHP CONDUIT AT GL: GL: 4.2 - 5/ K - L; 15 @ 3"; 2 @4"; 3 @ 1 1/2"; 1 @ 2 1/2"; 14 @ 1". OK TO BACK FILL PROGRESS AREA.
02/21/2017 ELECTRIC - UNDERGROUND Partial Approval 4 EACH 4: CONDUIT STUB-UPS, 1 EACH 6" CONDUIT AT GL: L.5/M.5. SOUTH AREA: 5 EACH 5" CONDUITS; 4 EACH 4", 10 EACH 3", AND 12 EACH 1" CONDUITS.
02/13/2017 ELECTRIC - UNDERGROUND Partial Approval 16 EACH 4" STUB-UP CONDUITS AT GGL: 4/L.25. OK TO COVER PROGRESS AREA.
02/08/2017 ELECTRIC - UNDERGROUND Partial Approval APPROXIMATELY 25' OF ELECTRICAL CONDUITS; 16 EACH AT 4", 1 AT 5": GL4/L - M. OK TO COVER PROGRRESS AREA.
02/06/2017 ELECTRIC - UNDERGROUND Not ready for Inspection WILL RECALL FOR 7 FEB 07
02/03/2017 ELECTRIC - UNDERGROUND Partial Approval COLUMN LINE J TO K AND 20' SOUTH OK TO POUR OVER 4'' CONDUITS.
02/01/2017 ELECTRIC - UNDERGROUND Partial Approval DUCT BANK SYSTEM: 16 @ 4" CONDUITS AT GL: 3.8/G - I. (WEST DUCT BANK) OK TO PLACE CONCRETE.
01/27/2017 ELECTRIC - UNDERGROUND Not ready for Inspection DUCT BANK AT GL: 4.2. NOT READY. ADDITIONAL SHORING (BOX) AT AREA WHERE TRENCH MAKES A 90 DEGREE TURN.
01/20/2017 ELECTRIC - UNDERGROUND Partial Approval WEST DUCT BANK AREA: 14 EACH 6" CONDUITS (20') AT GL: H/1 - 2. OK TO PLACE CONCRETE.