Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date |
Description |
Inspector |
Results |
Comments |
| 02/25/2019 |
PLUMBING - GAS PRESSURE TEST |
|
Approved |
|
| 06/15/2018 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
LEVEL #2, TOWER #4, MRI CORRIDOR: OXYTEN AND MEDICAL AIR. |
| 03/26/2018 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
GAS LINES (LOW AND MEDIUM PRESSURE) 2", 3", 1 1/2", 4" FROM LEVEL #4 BOILERS TO LEVEL #1 KITCHEN AREA. |
| 10/13/2017 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
LEVEL #1, 2" VACUUM LINES, 1" OXYGEN LINE, 1" MED GAS AT AMBULANCE BAY, EVS HALLWAY: TESTED AT 150 psi. LEVEL #3, 2" VACUUM LINES, 1" OXYGEN LINE, 1" MED GAS LINE: TESTED AT 150 psi (PEDIATRIC ROOMS). |