Permit: T16CM02176

Parcel: 12310001H


Addresses:

1625 N CAMPBELL AV

Inspection Status: Approved

Inspection History: FRAMING

Date Description Inspector Results Comments
02/25/2019 FRAMING Approved
01/16/2019 FRAMING Partial Approval Level #4; Blood Bank area. Ok to one side sheetrock office areas. Level #9; Tower #4, patient rooms from GL: J to South. Ok to top out sheetrock at 4' below deck above
01/11/2019 FRAMING Partial Approval Level #3. Tower $5, PACU Bay area; Rooms #0350110-0350126.. Ok to sheetrock drop down areas at 10 feet below deck above
11/16/2018 FRAMING Partial Approval Level #2. IR- Lab #1, ceiling. Ok to cover
11/15/2018 FRAMING Partial Approval Lab #3 control room ceiling. Ok to cover when electric has been completed.
11/13/2018 FRAMING Partial Approval Level #2, IR Lab #3 ceiling. Ok to cover ceiling
11/07/2018 FRAMING Partial Approval Level #2, EP1 - ceiling. Ok to cover ceiling. EP2, ceiling framing is complete - do not cover until Electric Above ceiling is complete
09/19/2018 FRAMING Partial Approval LEVEL #2, CATH LABS #1 AND #2; IP ROOMS #1 AND #2. OK TO COVER WALLS.
09/07/2018 FRAMING Partial Approval LEVEL 1. ATRIUM AREA, CEILINGS AND SOFFITS . OK TO COVER PROGRESS AREAS.
07/20/2018 FRAMING Partial Approval LEVEL #2, RESTROOM CEILINGS IN ROOM #0240403, 0240404, 020405, 020406
07/18/2018 FRAMING Partial Approval LEVEL #2, WON DOOR. FRAMED, FIRE CAULKED - OK TO SHEETROCK PROGRESS AREAS.
07/06/2018 FRAMING Partial Approval LEVEL #1, PHARMACY AREAS AT GL: C-F/10-13; H-I/7-10. OK TO INSULATE AND COVER WALLS.
06/25/2018 FRAMING Partial Approval LEVELS #5 - 9, QUIET ROOMS IN KNUCKLE AREAS (CEILINGS AND SOFFITS). OK TO SHEET ROCK PROGRESS AREAS.
06/22/2018 FRAMING Partial Approval LEVEL #3; SOFFITS AT EXTERIOR OF OPERATING ROOMS #21 AND #22. SOILED MAIN ROOM, ABOVE CEILING. OK TO COVER PROGRRESS AREAS.
06/20/2018 FRAMING Partial Approval LEVEL #1, DINNING AREA SOFFITS - OK TO SHEETROCK PROGRESS AREAS.
06/15/2018 FRAMING Partial Approval LEVEL #2, DINNING/CAFE AREA SOFFITS AND CEILINGS.
05/31/2018 FRAMING Partial Approval LOADING DECK CEILING. OK TO SHEETROCK (DENS-GLAS) PROGRESS AREA.
05/22/2018 FRAMING Partial Approval LEVEL #2, EACH MRI ROOMS. OK TO TOP-OUT SHEET ROCK EACH ROOM.
05/07/2018 FRAMING Partial Approval LEVEL #3, SHAFTS IN ROOMS #0350568 AND #0350568; INTERIOR COVERED AND FIRE CAULKED. OK TO SHEETROCK EXTERIORS (PHASE II)
04/27/2018 FRAMING Partial Approval LEVEL #1, DINNING AREA, KITCHEN OFFICES, COLUMNS. OK TO INSULATE AND COVER WALLS. AREAS OF SHEET ROCK NAILING (TOP-OUT AT 10' FROM DECK ABOVE)
04/25/2018 FRAMING Partial Approval LEVEL #8, TOWER #4, WINDOW FRAMING FOR ROOMS: 1, 3, 10, 17, 20, 22, 24. LEVEL #7 TOWER #4; ROOM #19. OK TO INSULATE AND COVER WALLS.
04/18/2018 FRAMING Partial Approval LEVEL #2, CAFE AREA (NORTH WEST) COLUMN AT LEVEL #2 TO #3; SOFFITS AT GL: D/11 AND B/13. OK TO COVER WALLS.
04/16/2018 FRAMING Partial Approval LEVEL #3, NORTH EAST KNUCKLE AREA (ON-CALL RESTROOM CEILINGS) - 7 BATHROOM CEILINGS. OK TO COVER WHEN FIRE CAULKING HAS BEEN COMPLETED. LEVEL #1, PHARMACY AREA AT GL: F/10. OK TO COVER WALLS (TOPPED OUT AT 8 ' BELOW DECK)
04/12/2018 FRAMING Partial Approval LEVEL #2, PRE-POST, MRI, CT BATHROOM HARD LID CEILINGS. STAIRWELL #4, LEVELS #1 - #9: SOUTH, WEST AND NORTH WALLS. OK TO SHEET ROCK PROGRESS AREAS.
04/11/2018 FRAMING Partial Approval LEVELS: #5, 6, 7, 8 KNUCKLE AREA: BATHROOMS AND SHOWERS - HARD LID CEILINGS. PLEASE INSURE THAT ALL BATHROOM AND SHOWER CEILING AREAS ARE PROPERLY FIRE CAULKED. RECALL FOR ABOVE CEILINGS WHEN ELECTRIC AND MECHANICAL ARE COMPLETE.
03/28/2018 FRAMING Partial Approval LEVEL #3, SHAFT WALLS AT CLEAN AND DIRTY ELEVATORS, WON DOOR SOFFIT. OF TO COVER PROGRESS AREAS.
03/26/2018 FRAMING Partial Approval OVER-HEAD IN PATIENT ROOMS #1, 2, 23, 24 ON LEVEL #8, TOWER #4. OK TO COVER WHEN ELECTRIC WORK IS COMPLETE.
03/21/2018 FRAMING Partial Approval LEVEL #3, OR'S #10-17 HARD LIDS. OK TO SHEET ROCK WHEN ALL TRADES ARE COMPLETE.
03/13/2018 FRAMING Partial Approval LEVEL #3, ROOM #0340634 A AND B: CONFERENCE ROOM PARTITION SOFFIT. OF TO COVER.
03/12/2018 FRAMING Partial Approval LEVEL #1, STAIRWELL #4 AREA. EXTERIOR WALLS - OK TO INSULATE AND COVER WALLS.
03/08/2018 FRAMING Partial Approval OPERATING ROOMS #2 - 8, LEVEL #3, CEILINGS; SCRUB SINK AREAS IN HALLWAYS. OK TO COVER PROGRESS AREAS.
03/07/2018 FRAMING Partial Approval LEVEL #1, BATHROOM #0150509, AND #0150506 - FRAMING ABOVE CEILINGS (ELECTRIC INCLUDED_. OK TO COVER WHN ALL PENETRATIONS HAVE BEEN FIRE CAULKED.
03/05/2018 FRAMING Partial Approval EXPANSION JOINT AT GL: 15, TUNNEL AREA AT LEVEL #4 - BUILDING TIE-IN.
03/02/2018 FRAMING Partial Approval LEVEL #4, KNUCKLE AREA. OK TO COVER WALLS.
03/01/2018 FRAMING Partial Approval LEAD PROTECTION FOR ELECTRIC AND PLUMBING (IN WALLS) IN ROOMS 240103, 250104, 250301, 250302, 250303.
02/27/2018 FRAMING Partial Approval CEILINGS IN ROOMS #0105504, 010505 - EQUIPMENT REPAIR ROOMS ON LEVEL #1. OK TO COVER CEILINGS.
02/22/2018 FRAMING Partial Approval COLUMNS IN CORRIDOR #0350530 ON LEVEL #3 AT GL: 4.2/H - M. STAFF ON CALL AREA: OFFICES, RESTROOMS, SHOWERS.
02/21/2018 FRAMING Partial Approval CAFE AREAS; SHAFT AT GL: F/4.2 - LEVEL #2.
02/14/2018 FRAMING Partial Approval LEVEL #7, TOWER #4; ROOMS 740001, 740002, 740023, 740024; PATIENT ROOM SHOWER CEILINGS. ENSURE ALL PENETRATIONS ARE SMOKE CAULKED. ROOM 740024; 1/2" COPPER LINE NEED A SUPPORT HANGER.
02/08/2018 FRAMING Partial Approval LEVEL #2, STAIRWELL #4 AREA; IDF ROOM, STAIRWELL CORRIDOR. OK TO SHEETROCK.
02/05/2018 FRAMING Partial Approval LEVEL #3, GL: 14/E.2 - H, SHAFT WALL. OK TO INSULATE AND SHEETROCK PROGRESS AREAS.
01/29/2018 FRAMING Partial Approval LE#1, AREA #4: RESTROOMS #505, 507, 508 (CEILINGS). LEVEL #8, TOWER #4, PATIENT BATHROOM CEILINGS #3 - 24. LEVEL #5, ROOMS: 102, 103, 104, 105 (CEILINGS)
01/26/2018 FRAMING Partial Approval SHAFT #1A AT STAIRWELL #4, OK TO SHEETROCK.
01/24/2018 FRAMING Partial Approval LEVEL #1, AAREA #4, ROOM #507; LEVEL #1, AREA #1 - TWO HOUR RATED WALL AT GL: B/8. LEVEL #2, AREA #1 WALL AT GL: D/12. OK TO COVER WALLS.
01/23/2018 FRAMING Partial Approval LEVEL #1, AREA #4 (BOTTOM PORTION OF WALLS) AT GL: I/4.2 -8, L/4.2 - 8. SHAFT #7 BOTTOM. OK TO SHEET ROCK PROGRESS AREAS.
01/18/2018 FRAMING Partial Approval LEVEL #8, TOWER #4, CENTER ROOMS. LEVEL #1, ROOM #0150505, SHAFT FURR-OUT. OK TO SHEET ROCK PROGRESS AREAS.
01/16/2018 FRAMING Partial Approval LEVEL #3, OR #1, (CEILING), LEVEL #7, TOWER #4 PATIENT ROOM CEILINGS (TOILET AREAS). *NOTE: ROOMS #002, 021, 024 - COMPLETE FIRE CAULKING. ROOM #12 - REMOVE TEMPORARY ELECTRIC FROM CEILING.
01/10/2018 FRAMING Partial Approval LEVEL #8, TOWER #4: EAST ROOMS ONLY - OK TO COVER WALLS.
01/10/2018 FRAMING Partial Approval SHAFT #7 AT LEVEL #1, OK TO FRAME AND SHEET ROCK BOTTOM OF SHAFT
01/09/2018 FRAMING Partial Approval LEVEL #2, GL: C - H/4.2 - 13. LEVEL #1, MAIN LOBBY ENTRANCE (3 COLUMNS ) AT GL: C/9 - 10. ED CORRIDOR - NORTH WALL, OK TO SHEET ROCK PROGRESS AREAS.
01/05/2018 FRAMING Partial Approval LEVEL #8, TOWER #4, WEST SIDE ROOMS AND WESTSIDE OF HALLWAY.
01/04/2018 FRAMING Partial Approval HARD LID CEILINGS ON LEVEL #3; GL: B - H/4.2 - 13.5. NOTE:
ROOM #485 NEEDS METAL FLANGE AROUND DUCT PENETRATION. ROOM #286 - MOVE ACCESS PANEL TO ALLOW ACCESS TO VALVES ABOVE. ROOM #386 - PATCH PENETRATION ABOVE FRAMING; APPROXIMATELY 3" DIAMETER.
12/21/2017 FRAMING Partial Approval LEVEL #1, LOBBY AREA, COLUMNS AT MAIN ENTRY. LEVEL #7, TOWER #4, PATIENT BATHROOM CEILINGS. ALL BATHROOMS NEED TO BE CHECKED FOR FIRE CAULKING AROUND ELECTRIC CONDUITS. ADA ROOMS NOT READY (4 ROOMS).
12/19/2017 FRAMING Partial Approval LEVEL #1, AREAS 1, 3, 4 AND BOTTOM OF SHAFT #3.
12/14/2017 FRAMING Partial Approval LEVEL #5, KNUCKLE AREA (WALLS) AT GL: C - H/11 - 13.5. LEVEL #9, TOWER #5 - PATIENT ROOMS ( BATHROOM CEILINGS); #1 - 24. OK TO SHEET ROCK CEILINGS PENDING ELECTRIC LIGHTING COMPLETION.
12/11/2017 FRAMING Partial Approval LEVEL #6, TOWER #4, PATIENT BATHROOMS (CEILINGS). ROOMS #1 - 24, OK TO SHEETROCK PROGRESS AREAS.
11/20/2017 FRAMING Partial Approval LEVEL #6, TOWER #4, LEVEL #8, TOWER #5 - ROOMS COMPLETE. OK TO COVER WALLS.
11/15/2017 FRAMING Partial Approval SOFFIT AT GL: 14/B - E; B/11 - 14. OK TO INSULATE AND COVER.
11/09/2017 FRAMING Partial Approval LEVEL #5, TOWER #4, ROOM #540001, CEILING - OK TO SET TILES.. LEVEL #1, GL: K -L/7 - 8.6; I - K/10.5 - 11. OK TO TOP-OUT SHEETROCK AT 10' BELOW DECK ABOVE.
11/07/2017 FRAMING Partial Approval BATHROOM HARD CEILINGS ON LEVEL #8, TOWER #5: ROOMS 1 - 12; LEVEL #6, TOWER #5, ROOMS #8 - 12 (NEED CAN LIGHTING INSTALLED.).
11/01/2017 FRAMING Partial Approval NORTH SIDE CANOPY: GL: B/6 - 8. OK TO SHEETROCK PROGRESS AREAS (CEILING)
10/27/2017 FRAMING Partial Approval LEVEL #1, TRAUMA CORRIDOR; OK TO SHEETROCK PROGRESS AREAS.
10/26/2017 FRAMING Partial Approval LEVEL #1, GL: I - K/8 - 11; K - M/11 - 13. LEVEL #3; GL: 4.2 - 12/C -M; OK TO TOP-OUT PRIORITY WALLS AT 10' BELOW DECK ABOVE; OK TO BEGIN ONE-SIDE SHEETROCKING.
10/12/2017 FRAMING Partial Approval LEVEL #1, GL: 4.25 - 6.5/I.5 - J; 6.5 - 8; 6.5 - 8/I - J; CORRIDOR AT I.5 -K/8; 7/I.5 - K, 4.2 - 5.5/I.5 - M.
10/11/2017 FRAMING Partial Approval EXTERIOR FRAMING AT GL: 4/E - F. OK TO INSULATE AND COVER.
10/10/2017 FRAMING Partial Approval EXTERIOR FRAMING AT GL: 4/G - F; LEVELS 1 - 6. OK TO INSULATE AND COVER WALLS.
09/21/2017 FRAMING Partial Approval SOUTH SIDE OF BUILDING AT GL: N/13 - 15, LEVELS 1 - 10. OK TO COVER PROGRESS AREA.
09/12/2017 FRAMING Partial Approval ELECTRIC AND IDF ROOMS; GL: G/10 - 10.5; H/10 - 10.5, J/7. LEVEL #2 GL: D - K/7 - 14.
08/30/2017 FRAMING Partial Approval LEVEL #1 - 2: DANCE FLOOR AREA AT GL: 12 - 15/G - N. OK TO COVER PROGRESS AREA
08/28/2017 FRAMING Partial Approval LEVEL #4, GL: 11/H.8 - I.8, PT BLOWER ROOM; ACCESSIBLE SHAFT "B", ACCESSIBLE SHAFT "C".
08/24/2017 FRAMING Partial Approval LEVEL #10, PONY WALLS SOUTH OF PENTHOUSE. OK TO COVER.
08/03/2017 FRAMING Partial Approval LEVEL #4; ELECTRIC ROOM AT GL: G/9.5. OK TO COVER WALLS.
07/28/2017 FRAMING Partial Approval NE SECTION OF BUILDING GL: 10 - 11.4/B - C. ESTERIOR WALL AT GL: 12/G - H.
07/25/2017 FRAMING Cancelled
07/21/2017 FRAMING Partial Approval TOWER #4, LEVEL #5; ROOMS 0540002, 0540002A, 0540002B; NURSES STATIONS BETWEEN ROOMS # 11 - 12
07/20/2017 FRAMING Partial Approval LEVELS 1 & 2, GL: C/14 - 15. OK TO INSULATE AND COVER WALLS.
07/17/2017 FRAMING Partial Approval EXTERIOR, STAIRWELL #2 AREA AT LEVELS 5 - 10; LEVEL #1 EAST WALL AT GL: 12/I - N.
07/11/2017 FRAMING Partial Approval OPERATING ROOMS (LEVEL #3) #10, 20, 21, 22, 23 - OK TO TOP-0UT SHEET ROCK (PRIORITY WALLS)
06/30/2017 FRAMING Partial Approval EXTERIOR; LEVEL #4; GL: N/11 - 14. LEVEL #3 INTERIOR AT GL: H - M/10 - 13. OK TO TOP-UT SHEET ROCK - ONE SIDE.
06/22/2017 FRAMING Partial Approval LEVEL #3, CAFE AREA UPPER WALLS (2 HOUR RATED) - GL: C - E/12 - 14. OK TO HANG SHEET ROCK.
06/19/2017 FRAMING Partial Approval EXTERIOR FRAMING AT GL: H/13 - 15 AT LEVELS #2 - 4.5. OK TO COVER WALLS.
06/13/2017 FRAMING Partial Approval COLUMN POP-OUTS (7 EACH). WEST SIDE OF LEVEL #4. OK TO SHEET ROCK PROGRESS AREAS.
05/30/2017 FRAMING Partial Approval EXTERIOR FRAMING AT GL: 13/G - N; LEVELS #5 AND #6. OK TO COVER WALLS.
05/29/2017 FRAMING Partial Approval EXTERIOR FRAMING ON GL: 4.2/G - L. OK TO COVER PROGRESS AREAS.
05/19/2017 FRAMING Partial Approval EXTERIOR FRAMING AT GL: 12/H - N ON LEVELS 2 - 4
05/11/2017 FRAMING Partial Approval ELECTRIC ROOMS #0949804, 0948903, O8949904, 08949803. NON - AMICO (HEAD WALLS) WALLS AT GL: 5.5 - 8/C - H ON LEVEL #3. OK TO PLACE HEAD WALLS.
05/09/2017 FRAMING Partial Approval EXTERIOR FRAMING AT GL: 4.2/G - H. INTERIOR RESTROOMS AT LEVELS 8 AND 9.
05/01/2017 FRAMING Partial Approval ELECTRIC ROOMS AND IDF ROOMS ON LEVELS 5 - 8.
05/01/2017 FRAMING Partial Approval
04/28/2017 FRAMING Partial Approval STAIRWELL AREA/IDF AREA AT GL: 4.2/M.1 - M.8. OK TO SHEET ROCK; 8' DOWN FROM CEILING (2 LAYERS)
04/26/2017 FRAMING Partial Approval EXTERIOR AT GL: 4.2/1 - 5; N/4.2 - 5. STAIRWELL #1, LEVELS 5 - 10. OK TO COVER PROGRESS AREAS.
04/21/2017 FRAMING Partial Approval COLUMNS AT GL: 7 - 8/B. OK TO COVER PROGRESS AREA.
04/20/2017 FRAMING Partial Approval EXTERIOR AT GL: 4.2/G - L, N/G - L ON LEVELS 2 - 5. OK TO COVER PROGRESS AREAS
04/17/2017 FRAMING Partial Approval EXTERIOR FRAMING AT GL: 10/G - N; (LEVEL 10), 13.5/C - I; LEVERS 8 - 10.
04/14/2017 FRAMING Partial Approval STAIRWELL #1 - LEVELS 1 THROUGH 9. OK TO APPLY FIRST LAYER OF SHEET ROCK.
04/13/2017 FRAMING Partial Approval INTERIOR: LEVEL #5; MID SECTION GL: 4.2 - 11/F - G. OK TO ONE SIDE SHEET ROCK. EXTERIOR: GL: 14/G - G (LEVELS 2 - 4); GL: 14/B - G (LEVELS 5 - 10)
04/12/2017 FRAMING Partial Approval FRAMING AT GL: 10.75/G - M; M/5 - 12; 5/M - N; 4.5/L.5 - N; L.5/4 - 5; N/4 - 5.
04/12/2017 FRAMING Partial Approval LEVEL #5, NORTH PATIENT ROOMS #1 - 12. OK TO ONE SIDE SHEET ROCK. EXTERIOR FRAMING AT GL: 10/G - N. OK TO COVER.
04/05/2017 FRAMING Partial Approval LEVEL #7 - 10; GL: 13/B - F; OK TO COVER PROGRESS AREAS.
03/29/2017 FRAMING Partial Approval LEVELS 6 AND 7; GL: 10/J - N. OK TO COVER.
03/23/2017 FRAMING Partial Approval EXTERIOR AT LEVELS 2 - 5, GL: G - L/9 - 10; LEVELS 9 - 10 (WEST) GL: 10, LEVELS 6 - 8, LEVELS; LEVELS 2 - 5 GL: 4.5 - 9.5. LEVEL #3 (HEAD WALLS) GL: 5.5/C.8 - G.5; 7.5/C.8 - 6.5; 9/D.5 - G.5; C/4.2 -9. OK TO INSULATE AND SHEET ROCK HEAD WALLS.
03/19/2017 FRAMING Partial Approval EXTERIOR FRAMING AT GL: 5 - 9.5/N (LEVELS 2 - 3); 10/D - B.2 (LEVELS 7 -8)
03/12/2017 FRAMING Partial Approval NORTH EAST CORNER: GL: B/9 - 10; LEVEL 6- 7, GL: 9/G - J. OK TO COVER PROGRESS AREAS.
03/01/2017 FRAMING Partial Approval EXTERIOR FRAMIG GL: 13/B - G, LEVELS 4 - 7; B/11 - 13 LEVELS 4 - 7; B/10.5 LEVELS 1 - 2. PENTHOUSE LOWER LEVEL; FIR-OUT WALLS. OK TO COVER.
02/24/2017 FRAMING Partial Approval LEVEL #4; GL: B/11- 13; 13/A.5 -F.
02/14/2017 FRAMING Partial Approval LEVELS #5 - 10 AT GL: B/10.5; LEVELS #3 - 8 AT GL: B.3/11.4 12.
02/09/2017 FRAMING Partial Approval FRAMING AT GL: M/7 - 9, 8/G - K. OK TO SHEETROCK FROM DECK ABOVE TO 12' AFFE.
02/06/2017 FRAMING Partial Approval #4 CORRIDOR AT GL: F/4.2 - 10. OK O SHEET ROCK BOTH SIDES DOWN TO 10' AFFE.
01/31/2017 FRAMING Partial Approval ELECTRIC ROOMS AT LEVEL #4 - OK TO COVER WALLS.
01/18/2017 FRAMING Partial Approval N.W. STAIRWELL AT LEVELS 4 THROUGH LEVEL 10 - OK TO COVER EXTERIOR WALLS.
01/12/2017 FRAMING Partial Approval EXTERIOR FRAMING AT LEVEL 6 TO LEVEL 7. GL: G/4.2 - 8.5. OK TO COVER PROGRESS AREAS.
01/08/2017 FRAMING Partial Approval LEVEL #5 - AREA #4 (LEVEL 5 TO LEVEL 6) GL:N/4.2 -8.
12/18/2016 FRAMING Partial Approval ESTERIOR FRAMINGAT LEVELS 6 & 7 GL: 4.2 - 9.5/B. OK TO COVER PROGRESS AREAS.