Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/25/2019 | MECHANICAL - INTERMEDIATE | Approved | ||
| 03/01/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | PUMPING AND RETURN SYSTEMS FOR PCW (TESTED AT 135 PSI), ERW TESTED AT 150PSI. | |
| 01/17/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | CHILLED BEAM WATER (SUPPLY AND RETURN); HEATED HOT WATER (SUPLY AND RETRUN); 1 1/2" LINES - LEVEL #5, KNUCKLE AREA. OK TO INSULATE PROGRESS AREAS. LEVEL #2, AREAS #2, 3, 5, 6 - HARD LID AREAS - DUCT SYSTEM. OK TO INSULATE PROGRESS AREAS. | |
| 01/16/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | IN WALL ELECTRIC ON LEVEL #8, TOWER #4, PATIENT ROOMS #13 - 24. OK TO COVER WALLS. IDF ROOM LEVEL #3, #0359901. | |
| 10/13/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | LEVEL #1, TRAUMA AREA, GL: G.5/9 - 13, 10" HEATED HOT WATER SUPPLY AND RETURN. | |
| 09/20/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | LEVEL #4, SHAFT #9; DUCT SYSTEM IS INSULATED. | |
| 09/06/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | TWO 10" RISER LINES FROM LEVEL #1 - LEVL #4. LINES TESTED FOR 24 HOURS. | |
| 08/31/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | LEVEL #4; SHAFT #14: INSULATION WRAP AT GL: 12/M. SHAFT #13 WAS NOT READY FOR INSPECTION. | |
| 08/30/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | HEATED HOT WATER LINES: TESTED AT 160 psi. CHILLED WATER LINES, TESTED AT 150 psi ON LEVEL #3, AREAS # 1 - 6. | |
| 08/28/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | LEVEL #8, TOWER #5; MEDIUM PRESSURE LINES/EXHAUST LINES; LEVEL #6, LOW PRESSURE LINES; LEVEL #5 LOW PRESSURE LINES. | |
| 07/27/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | HYDRO TEST ON HEATED AND CHILLED WATER LINES AT 155 psi; CONDENSATION LINE TESTED AT 40 psi: SHAFT #13, LEVEL 4. | |
| 07/18/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | LEVEL #5, TOWER #5 (HIGH PRESSURE LINES) OK TO INSULATE. | |
| 06/21/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | ||
| 06/21/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | CHILLED WATER RETURN LINE (12" EAST LINE) CONNECTED TO MAIN RETURN LINE AT GL: 14.5/I - L; TESTED AT 158 psi. OK TO COVER PROGRESS AREA. | |
| 06/14/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | STORM RISER AT COLUMN 6-F FROM LEVEL 2 UP TO LEVEL 4 OK. ALL HORIZONTAL STORM DRAIN (PRIMARY AND OVERFLOW) OK. HEAT AND CHILL WATER SUPPLY AND RETURN TESTED AT 150 PSI ON LEVEL 5 OK. |
|
| 06/07/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | SHAFTS # 6A, 6B, 7, AND 8: INSULATED AT LEVEL #4. CHILLED WATER LINES (LIEVEL #4) - 4 LINES AT GL: D.5/5 - 6; D.5/9.5 - 11; 11/E.5 - I; J/7 - 8. OK TO CMPLETE INSULATION OF PROGRESS AREAS. | |
| 05/19/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | SHAFT 6B, LEVELS 4 - 3: HANGERS AND SUPPORTS ARE IN PLACE. OK TO INSULATE PROGRESS AREA | |
| 05/11/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | LEVEL #2, SHAFT #1 - INSULATED, SHAFT #2, FIRE DAMPER, SHAFTS #4 & 5 FIRE DAMPERS. lEVEL #3: SHAFT #1: INSULATED; SHAFT #2, FIRE DAMPER, #4 & 5 INSULATED. LEVEL #4: SHAFT #2 - FIRE DAMPER, #4 INSULATED; #5 INSULATED. | |
| 05/10/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | SHAFT #1A, DUCT WORK AT LEVEL #4 - INSULATION OK. | |
| 04/21/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | LEVEL #7, PATIENT ROOMS #1 - 12, VENTS AND WASTE LINES (3" - 4"). LEVEL #8 PATIENT ROOMS #1 - 12, CARRIER LINES TO VENT LINES (2 1/2" - 4"). | |
| 04/12/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | HHW LINES PRESSURE TESTED AT 90 AND 118 PSI FROM BUILDING TO CUP | |
| 04/10/2017 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | STORM DRAIN IN SHAFT #4 - NOT READY - NO WATER ON SITE TO TEST DRAINS. | |
| 04/05/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | TOWER #4 SHAFT, LEVELS #2 - 10; MID BRACING ADDED AT EACH LEVEL. | |
| 03/26/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | LEVEL #4, SHAFT FRAMING - SHAFTS #2,4,5. CALL FOR INSULATION INSPCTION | |
| 03/08/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | HIGH PRESSURE DUCT SYSTEM INSULATION AT LEVELS 5 - 9. | |
| 03/07/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | HIGH PRESSURE DUCT SYSTEM (INSULATION) AT LEVELS 5 - 9. | |
| 03/06/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | SHAFT #10 AT LEVELS 5 - 9; HIGH PRESSURE DUCT SYSTEM: NEED TO TAPE ALL GAPS, SECURE INSULATION FROM LEVEL TO LEVEL. | |
| 02/16/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | STAIRWELL PRESSURIZATION TEST IN STAIRWELL #1, LEVELS 9 - 4: TESTING PERFORMED BY JENSEN HUGHES TESTING SERVICES. | |
| 02/12/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | ROOF DRAINS (NE) - 4" - 6" LINES; RISERS 6" - 8" AT LEVELS 9 - 4. | |
| 02/01/2017 | MECHANICAL - INTERMEDIATE | Partial Approval | ROOF DRAINS (PRIMARY AND SECONDARY) IN SHAFTS #10 AND #11 FROM LEVEL #9 TO LEVEL #4. WALK THROUGH INSPECTION, TO BE GRAVITY TESTED ON 2-2-17 |