| 02/25/2019 |
MECHANICAL - ABOVE CEILING |
|
Approved |
|
| 02/14/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Level #4, Mechanical rooms: 10" steam lines (under test at 148 psi); Domestic water chilled supply and return lines, tested at 48 psi. Ok to insulate all lines |
| 01/14/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Blood Bank area. Flex and Hard duct systems. Level #4. Ok to insulate progress areas |
| 06/22/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #3, OPERATING ROOMS #18 AND #21. |
| 04/25/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #1, KITCHEN AND DINNING AREA; HIGH AND LOW PRESSURE DUCT SYSTEMS; OK TO INSULATE. LEVEL #4, HARD LID AREAS (CENTER SECTION) - OK TO INSULATE DUCT WORK SYSTEM. |
| 04/03/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #2 TO LEVEL #3 (HIGH AREA); LOW PRESSURE DUCT SYSTEM; OK TO INSULATE. |
| 03/25/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVELS #7, 8, 9: CHILLED BEAM WATER, HEATED HOT WATER LINES AT 3/4" - 1 1/2" - 2". TESTED AT 160 PSI. OK TO INSULATE PROGRESS AREAS. |
| 03/21/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #2, AREAS #7 AND NORTH HALLWAY OF AREA #9, LOW PRESSURE CUST SYSTEMS. OK TO INSULATE PROGRESS AREAS. |
| 03/06/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #1, PHARMACY AREA SOUTH TO LOADING DOCK AREA; LOW PRESSURE DUCT SYSTEMS - OK TO INSULATE. |
| 02/28/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
HIGH/LOW PRESSURE DUCT SYSTEMS AT LEVEL #1, GL: 5-13/G-M. OK TO INSULATE PROGRESS AREAS. |
| 02/22/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVELS #2 AND #3, AREA #7 AND #8; LOW PRESSURE DUCT SYSTEMS: OK TO INSULATE PROGRESS AREAS. |
| 02/15/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #2, AREAS #1 AND #4; LOW PRESSURE DUC SYSTEMS. OK TO INSULATE PROGRESS AREAS. |
| 02/14/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
KITCHEN AREA: HIGH/LOW PRESSURE DUCT SYSTEMS - OK TO INSULATE |
| 01/30/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #5, KNUCKLE AREA; LEVEL #2, AREAS #2 AND #5 - LOW PRESSURE DUCT SYSTEM - OK TO INSULATE PROGRESS AREAS. |
| 01/23/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #2, AREAS #3 AND #6; LOW PRESSURE DUCT SYSTEM AT GL: B - H/ 10 - 14. |
| 01/22/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
DUCT SYSTEM ON LEVEL #4, TOWER #4: GL: G/8 - 10. OK TO INSULATE PROGRESS AREAS. |
| 01/16/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #2 AND LEVEL #9, TOWER #4; CHILLED BEAM WATER LINES; HEATED HOT WATER LINES AT 1 1/2" - 3" - ALL TESTED AT 150 PSI. |
| 01/11/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #1, KITCHEN AREA, GL: G/4.2 - 10, F/4.2 - 10. LEVEL #2 AT GL: C - H/4.2 - 14: OK TO INSULATE PROGRESS AREAS. LEVEL #1 AT G/7 - REPAIR DAMAGED DUCT. |
| 01/09/2018 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
CHILLED WATER LINES; HOT WATER LINES: SUPPLY AND RETURN LINES AT 3/4" - 2"; GL: H - N/4.2 - 14; OK TO INSULATE PROGRESS AREAS. |
| 12/26/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #4, TOWER #4, GL: H - K/8 - 10. ROUND DUCT SYSTEM AT 12" - 24" SYSTEM - OK TO INSULATE PROGRESS AREAS. |
| 12/21/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVE #8, TOWER #4, LOW PRESSURE DUCT SYSTEM - ALL AREAS EXCEPT FOR NORTH WEST AREA. |
| 12/21/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVELS #1 - 4, CHILLED WATTER SYSTEM AT 6" - 18" LINES (SUPPLY AND RETURN) - BOOSTED CHILLED WATER SYSTEM. LEVEL 1 - 2, LOBBY AREA - HEATED HOT SUPPLY AND RETURN.. |
| 12/18/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
ED CORRIDOR, SUPPLY AIR DUCT SYSTEM - OK TO INSULATE LINES. |
| 12/05/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LOW PRESSURE DUCT SYSTEM AT LEVEL #9, TOWER #4; LEVEL #8, TOWER #5, TOWER #4 (EAST AND WEST PATIENT ROOMS 0NLY); LEVEL #7 - TOWER #4. OK TO INSULATE PROGRESS AREAS. |
| 11/14/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #3, LOW PRESSURE AND MEDIUM PRESSURE DUCT SYSTEMS: AREAS #1 - 6; OR'S #1 - 12. |
| 10/19/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LOW AND MEDIUM PRESSURE DUCT SYSTEMS: LEVEL #5, TOWER #4. |
| 10/04/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
HARD LID AREAS AT LEVEL #5, TOWER #4. |
| 10/03/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
MEDIUM PRESSURE LINES; LEVEL #8, TOWER #5 (NORTH AND SOUTH AREAS) |
| 09/14/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LOW PRESSURE AND MEDIUM PRESSURE DUCT SYSTEM ON LEVELS #5, 6: TOWER #4. LEVEL #7, MEDIUM PRESSURE DUCT SYSTEM - TOWER #4. |
| 09/07/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #7, TOWER #5, LOW PRESSURE DUCTS: SEALED. OK TO INSULATE PROGRESS AREA. |
| 08/24/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #8; MECHANICAL TOWER #4, EATING HOT WATER SUPPLY AND RETURN ( 3/4" - 2" LINES). |
| 08/03/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LEVEL #5, TOWER #4: HEATING HOT WATER LINES (3/4" - 2 1/2") LINES. |
| 07/26/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
LOW PRESSURE DUCT SYSTEM AT TOWER #5; LEVELS #6 AND 7 -SEALED JOINTS |
| 06/05/2017 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
MAKE-UP AIR DUCT SYSTEM (SEALED) AT GL: C - G/5 - 10. OK TO INSULATE PROGRRESS AREAS. |