Permit: T16CM02176

Parcel: 12310001H


Addresses:

1625 N CAMPBELL AV

Inspection Status: Approved

Inspection History: SHEET ROCK NAILING

Date Description Inspector Results Comments
02/25/2019 SHEET ROCK NAILING Approved
01/24/2019 SHEET ROCK NAILING Partial Approval Level #4, Blood Bank area; X-ray office on Level 2. Ok to tape progress areas
11/27/2018 SHEET ROCK NAILING Partial Approval Level #2, IR Labs $1 & 2: walls and ceilings. Ok to tape throughout.
11/20/2018 SHEET ROCK NAILING Partial Approval Level #2, IR- Control Room: walls and ceiling. Ok to tape progress areas.
11/15/2018 SHEET ROCK NAILING Partial Approval Level #2, Lab #3, walls and ceiling. Ok to tape throughout.
11/13/2018 SHEET ROCK NAILING Partial Approval Level #2, EP1 - EP2; walls and ceilings. Ok to tape progress areas
10/24/2018 SHEET ROCK NAILING Partial Approval Level #2, CATH LAB #3. Control Room, RF-1, RF-2 Walls and ceilings. Ok to tape progress areas
10/16/2018 SHEET ROCK NAILING Approved Level #2, MRI Room #3. Ok to tape progress areas
10/10/2018 SHEET ROCK NAILING Partial Approval Level #2, CATH Rooms #1 & #2; walls and ceilings
10/04/2018 SHEET ROCK NAILING Partial Approval Level 1, Autopsy Room- walls and ceiling. Ok to tape.
10/01/2018 SHEET ROCK NAILING Partial Approval Level #2, Cath Labs #1, 2,3, Cath Control rooms restricted corridor, transfer alcove, IR Control room, MRI. OK to tape progress areas.
09/13/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, ATRIUM CEILINGS AND SOFFITS; OK TO TAPE PROGRESS AREAS.
09/07/2018 SHEET ROCK NAILING Partial Approval LEVEL #2, ELEVATOR LOBBY AREAS WALLS AND SOFFITS. OK TO TAPE PROGRESS AREAS.
08/17/2018 SHEET ROCK NAILING Partial Approval LEVEL #2, CAFE AREA WALLS AND CEILINGS, SOFFITS. RESTROOM CEILINGS - OK TO TAPE PROGRESS AREAS.
08/14/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, OPERATING ROOMS #18 AND #22; WALLS AND CEILINGS. OK TO TAPE PROGRESS AREAS.
07/30/2018 SHEET ROCK NAILING Partial Approval LEVEL #4, QUIET ROOM, VISITOR ELEVATOR AREA SOFFITS. **EXIT SIGNAGE FROM QUIET ROOM MUST BE MOVED DOWN TO ABOVE DOOR JAMB HEIGHT.
07/24/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, PHARMACY AREA (WEST) - OK TO TAPE WALLS AND CEILINGS.
07/18/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, PATIENT PHARMACY/OFFICES - OK TO TAPE PROGRESS AREAS.
06/29/2018 SHEET ROCK NAILING Partial Approval IVRS - Inspection :*
06/29/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, DINNING AREA (NORTH WEST). OK TO TAPE PROGRESS AREAS.
06/27/2018 SHEET ROCK NAILING Partial Approval LEVEL #2, CT ROOMS #1 - 3 (LEAD LINED WALLS). OK TO TAPE PROGRESS AREAS.
06/19/2018 SHEET ROCK NAILING Partial Approval LEVEL #2, TOWER #4 - WEST CORRIDOR AT GL: G-L/4.5. OK TO TAPE PROGRESS AREAS.
06/15/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, WEST CORRIDOR; DINNING AREA. OK TO TAPE PROGRESS AREAS.
06/08/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, LOADING DOCK CANOPY - DENS-GLAS SYSTEM. OK TO COVER PROGRESS AREA.
06/04/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, TOWER #5, SERVING AREA AT GL: C-E/8-11. LEVEL #3, TOWER#4: ROOMS #: 0340626, 0340625, 0340624, 0340623, 0350560, 0350556, 030555. OK TO TAPE PROGRESS AREAS.
05/25/2018 SHEET ROCK NAILING Partial Approval SHAFT AT WOUTH WEST CORNER OF OPERATING ROOM #22, LEVEL #3 - OK TO TAPE PROGRESS AREA.
05/24/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, DINNING AREA OFFICES; KITCHEN COOKING AREAS. OK TO TAPE PROGRESS AREAS.
05/14/2018 SHEET ROCK NAILING Partial Approval STAIRWELL #4, LEVELS #1 - 9: ALL AREAS EXCEPT FOR EXPOSED BEAM ON WEST WALL (LEVELS #1 - 9). OK TO TAPE PROGRESS AREAS.
05/08/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, PHARMACY - TOP OUT AT 12' BELOW THE DECK ABOVE. OK TO TAPE PROGRESS AREAS.
04/23/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, KITCHEN AREA - NORTH: NORTH WALL AREAS ATGL: G/4-9. OK TO TAPE PROGRESS AREAS.
04/18/2018 SHEET ROCK NAILING Partial Approval LEVEL #2, ROOMS AND CORRIDORS AT GL: G-M/5-9: OK TO TAPE PROGRESS AREAS. LEVEL #4, DIRTY AND CLEAN ELEVATOR SHAFTS: SHEET ROCKED AND FIRE CAULKED. STAIRWELL #4 NORTH EAST WALLS AT LEVELS 1-2, AND 5-9. OK TO TAPE PROGRESS AREAS.
04/16/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, KITCHEN AREA (SOUTH WALLS - HOOD AREAS). OK TO TAPE PROGRESS AREAS.
04/06/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, OR'S #10 - 17 CEILINGS. OK TO TAPE PROGRESS AREAS.
03/28/2018 SHEET ROCK NAILING Partial Approval LEVEL #3; CORRIDORS #0350540, 0350570, 0350590. OK TO TAPE PROGRESS AREAS.
03/26/2018 SHEET ROCK NAILING Partial Approval LEVEL #2, PRE-POST OP AT GL: H-L/6-10. OK TO TAPE PROGRESS AREAS.
03/13/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, AREA #3, ROOMS AND HALLWAYS: OK TO TAPE PROGRESS AREAS.
03/05/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, AREAS #3 AND #4 (INTERIOR ROOMS) - OK TO TAPE PROGRESS AREAS.
02/22/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, CORRIDOR #0350530 AT GL: H-M/4.2; OR'S #2, 3, 4. EQUIPMENT ROOM #0350530.
02/09/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, PBULIC RESTROOM CEILINGS #034203, 0340204. OK TO TAPE PROGRESS AREAS.
02/08/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, EAST SHSFT WALL - OK TO TAPE. LEVEL #2, AREAS 2, 3: ROOMS #025001, 0250440, GENERAL RADIOLOGY #0250101, 0250102, IDF #0259901, CORRIDOR 0250101.
02/05/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, CORRIDOR AREA #035140A: OK TO TAPE PROGRESS AREAS.
02/02/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, AREA #9 GL: I - M/8 - 4 (EXTERIOR CORRIDOR WALLS) OK TO TAPE PROGRESS AREAS.
01/29/2018 SHEET ROCK NAILING Partial Approval LEVEL #1, SHAFT (BOTTOM), OK TO FIRE CAULK AND TAPE.
01/26/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, ROOMS #721, 722, 724, 729, 727, 728, 730; CORRIDORS #740, 700, 710A-C. OK TO TAPE PROGRESS AREAS.
01/24/2018 SHEET ROCK NAILING Partial Approval LEVEL #2 AT GL: B - C/9 - 11; H/1 - 11 NORTH TO GL: C
01/17/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, OPERATING ROOM #1 CEILING - OK TO TAPE.
01/16/2018 SHEET ROCK NAILING Partial Approval LEVEL #3, GL: B/1 - 9, SOUT OF TRAUMA ELEVATORS; ELEVATOR LOBBY, STAFF WAITING AREA SOUTH; CONFERENCE ROOM.
12/19/2017 SHEET ROCK NAILING Partial Approval TOP-OUT AT 10' BELOW DECK ABOVE IN AREAS 1, 3, 4; BOTTOM OF SHAFT #3 - OK TO TAPE PROGRESS AREAS.
12/12/2017 SHEET ROCK NAILING Partial Approval TRAUMA ELEVATORS (SHAFT LINERS; LEVELS 1 -3) EAST LINERS. VISITOR ELEVATORS (SOUTH LINERS) LEVELS 1 - 9.
12/11/2017 SHEET ROCK NAILING Partial Approval CEILINGS AT GL: B/6 - 10 (DENS-GLAS SYSTEM). OK TO WATERPROOF PROGRESS AREAS.
12/06/2017 SHEET ROCK NAILING Partial Approval LEVEL #4, NORTH CORRIDOR AT GL: F - G/ 4.2 - 10. NORTH WALL AT GL: D/4 - 9. OK TO TAPE PROGRESS AREAS.
12/05/2017 SHEET ROCK NAILING Partial Approval LEVEL #1: KITCHEN AND OFFICE AREAS: TOP-OUT AT 10' BELOW DECK ABOVE, GL: G - M/10; C - E/4.2 - 10.
11/30/2017 SHEET ROCK NAILING Partial Approval LEVEL #3, GLl H - C.2/4 - 11. OK TO TAPE PROGRESS AREAS.
11/29/2017 SHEET ROCK NAILING Partial Approval SHELL SPACE AT GL: D/4 - 9. OK TO TAPE PROGRESS AREAS.
11/22/2017 SHEET ROCK NAILING Partial Approval VISITOR ELEVATORS #9, 10, 11: (SHAFT LINER WALLS). OK TO INSULATE AND COVER WALLS.
11/15/2017 SHEET ROCK NAILING Partial Approval LEVELS #5 AND #6, SHAFT #1, FIRST LAYER; LEVEL #9, SHAFT #10. OK TO INSULATE AND APPLY SECOND LAYER OF SHEETROCK.
11/08/2017 SHEET ROCK NAILING Partial Approval SHAFT #1 AT LEVELS $5 - 7; SHEETROCK AND FIRE CAULKING. OK TO TAPE PROGRESS AREAS.
10/26/2017 SHEET ROCK NAILING Partial Approval LEVEL #7, TOWER #5, ALL ROOMS (NORTH, SOUTH AND MIDDLE SECTIONS). OK TO TAPE PROGRESS AREAS. LEVEL #4, SHAFT #9, FIRE CAULKED, FIRST LAYER OF SHEETROCK, WEST STAIRWAY #4, SHEETROCK TOP-OUT AT 12' BELOW DECK ABOVE; IDF ROOM - PLYWOOD SHEATHING; ACCESSIBLE SHAFT (WEST).
10/19/2017 SHEET ROCK NAILING Partial Approval ELEVATOR #3, LEVEL #3, FIRST LAYER OF SHEET ROCK.
10/18/2017 SHEET ROCK NAILING Partial Approval LEVEL #7, TOWER #5, NORTH SIDE (PATIENT ROOMS #1 - 12 AND HALLWAY). OK TO TAPE PROGRESS AREAS.
10/12/2017 SHEET ROCK NAILING Partial Approval TOP-OUT AT 10' FROM DECK ABOVE: GL:4.25 - 6.5/I.5 - J; 6.5 -8/I - J; CORRIDOR I.5 -K/8; 7/I.5; 4.2 - 5.5/I.5 -M.
10/10/2017 SHEET ROCK NAILING Partial Approval MAIN DISTRIBUTION FRAME; LEVEL #4; PLYWOOD SHEATHING (2' - 10' LEVEL THROUGHOUT)
10/04/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING AT GL: 12 - 13/M -N, LEVELS 1 - 10. OK TO WATERPROOF PROGRESS AREAS.
09/27/2017 SHEET ROCK NAILING Partial Approval LEVEL #1, GL: 10/G: ELECTRIC ROOM - OK TO TAPE
09/26/2017 SHEET ROCK NAILING Partial Approval LEVEL #4, SHAFT #3, FIRST LAYER. SHAFT #13 IS COMPLETE.
09/22/2017 SHEET ROCK NAILING Partial Approval LEVEL #4, TOWER #4, SHAFT #13, FIRST LAYER ONLY.
09/21/2017 SHEET ROCK NAILING Partial Approval LEVEL #1, ELECTRIC ROOMS AT GL: F/9; G/11, I/11. OK TO TAPE ROOMS.
09/20/2017 SHEET ROCK NAILING Partial Approval LEVEL #4, SHAFT #13, FIRST LAYER; HHW SHAFT, FIRST LAYER. LEVEL #8, SHAFT #12, TOWER #4. LEVEL #7, SHAFT #1: NOT READY FOR INSPECTION; NEED TO COMPLETE 2 LAYERS ON EAST WALL.
09/19/2017 SHEET ROCK NAILING Partial Approval ELECTRIC ROOMS AT GL: 10.5/H; H.25/10: LEVEL #1. LEVEL #6, TOWER #4, SHAFT #14 FIRST LAYER.
09/14/2017 SHEET ROCK NAILING Partial Approval LEVEL #5, TOWER #5, SHAFT #1; LEVEL #5, TOWER #4, SHAFT #13; LEVEL #7, TOWER #4, SHAFT #12: NOT READY FOR INSPECTION.
09/13/2017 SHEET ROCK NAILING Partial Approval LEVEL #5, SHAFT #14; ONE LAYER APPLIED
09/12/2017 SHEET ROCK NAILING Partial Approval TOP-OUT AT 8' BELOW DECK ABOVE; GL: H/7 - 15. OK TO TAPE SECOND LAYER AREAS.
09/11/2017 SHEET ROCK NAILING Partial Approval EVEL #4, SHAFT #14; TWO LAYERS OF SHEETROCK APPLIED AND FIRE CAULKING.
09/06/2017 SHEET ROCK NAILING Partial Approval LEVEL #5, TOWER #5: PATIENT ROOMS; SUPPORT ROOMS, CORRIDORS. OK TO TAPE PROGRESS AREAS.
08/30/2017 SHEET ROCK NAILING Partial Approval LEVEL #5, TOWER #5, PATIENT ROOMS #2 - 9, 12 AND TOWER HALLWAY. LEVEL #4 FIRST LAYER: WALL AT GL: 8/G - L. SECOND LAYER: LEVEL #4, STAIRWELL #1, NORTH AND SOUTH WALLS; ELEVATORS 6, 7, 8, (NORTH AND SOUTH WALLS). SECOND LAYER COMPLETE AT ELEVATORS #3, 4, 5,. OK TO TAPE PROGRESS AREAS.
08/28/2017 SHEET ROCK NAILING Partial Approval HALLWAY AT GL: H.8 - I.8/11, TOP OUT AT 12' BELOW DECK ABOVE. WALL AT GL: 8/G - H.5. OK TO TAPE PROGRESS AREAS ( FIRST LAYER)
08/23/2017 SHEET ROCK NAILING Partial Approval LEVEL #5: LDR -2; LEVE #6, SHAFT #12, SHAFT #1 - FIRE CAULKED: FIRST LAYER OF SHEETROCK.
08/22/2017 SHEET ROCK NAILING Partial Approval CHUTE #0440503, FIRE CAULKED, FIRST LAYER COMPLETE: CORRIDOR # 0440600A BOTH SIDED TOPPED-OUT AT 12' FROM DECK ABOVE.
08/17/2017 SHEET ROCK NAILING Partial Approval LEVEL #2; GL: B - H/5 - 10; TOP OUT AT 4' - 10' BELOW DECK ABOVE. LEVEL #4: VISITOR ELEVATORS - WALLS NORTH, SOUTH, EAST 2 LAYERS. OK TO TAPE. VISITOR AREA WALL AT GL: I/12 - 13, BOTH SIDES.
08/09/2017 SHEET ROCK NAILING Partial Approval LEVEL #4, HALLWAY AT GL: 11/G - N: TOP-OUT AT 12' FROM DECK ABOVE. SHAFT #8 (SECOND LAYER) IS NOT READY - SOUTH WALL ONLY SINGLE LAYER.
08/08/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING, LEVEL #1, DENS-GLASS SHEATHING: GL: C/12 - 14; 14/C - B; B/14 - 16. OK TO WATERPROOF AND COVER.
08/07/2017 SHEET ROCK NAILING Partial Approval LEVEL #5, SHAFT #12, 2ND LAYER OF SHEET ROCK. LEVEL #4; ELECTRIC ROOM # 0459801A. OK TO TAPE PROGRESS AREAS.
08/04/2017 SHEET ROCK NAILING Not ready for Inspection LEVEL #4 ELEVATORS NEED TO BE FIRE CAULKED/SHEET ROCKED.
08/03/2017 SHEET ROCK NAILING Partial Approval EXTERIOR DENZ-GLAS SHEATHING AT STAIRWELL #2; LEVELS #2 - 10. OK TO WATERPROOF AND COVER. INTERIOR: SHAFT #8; LEVEL #4. OK TO PLACE SECOND LAYER OF SHEETROCK AND TAPE.
07/27/2017 SHEET ROCK NAILING Partial Approval SHAFT #8; LEVEL #4 DIRTY ELEVATOR - LEVEL #4 AT GL: 10/I - J. OK TO TAP PROGRESS AREAS.
07/21/2017 SHEET ROCK NAILING Partial Approval LEVEL #4; GL: D/7 - 10, TOP OUT AT 12' BELOW DECK ABOVE. OK TO TAPE PROGRESS AREAS. LDR - 2, OK TO INSULATE AND TAPE.
07/20/2017 SHEET ROCK NAILING Partial Approval ELEVATORS #13 & 14, LEVELS 7 & 8; 2ND LAYER. OK TO FIRE CAULK AND TAPE PROGRESS AREAS.
07/17/2017 SHEET ROCK NAILING Partial Approval LEVEL #4, NORTH WALL AT GL: B/4.2 - 8, TOP OUT AT 12' BELOW DECK ABOVE. HALLWAY (WEST WALL) GL: 11/M -N. OK TO TAPE PROGRESS AREAS.
07/11/2017 SHEET ROCK NAILING Partial Approval LEVEL #5, GL: 11/K - L, 1 HOUR RATED WALL. LEVEL #3, HALLWAY AT GL: G -H/10 - 11, 2 HOUR RATED WALLS AT ELECTRIC ROOM #0349902 - TOP-OUT AT 4' BELOW DECK ABOVE.
07/10/2017 SHEET ROCK NAILING Partial Approval LEVELS #5, 6, 7 SECOND LAYER OF SHEET ROCK AT GL: 4.2/B - C. OK TO TAPE PROGRESS AREAS.
07/06/2017 SHEET ROCK NAILING Partial Approval STAIRWELL #3, LEVEL #4, WOUTH WALL, FIRST LAYER.
06/30/2017 SHEET ROCK NAILING Partial Approval SHAFT #11, LEVEL #4 - SHEET ROCK AND FIRE CAULKED. SHAFT #7, LEVEL #4 - FIRST LAYER OF SHEET ROCK; OK T APPLY SECOND LAYER OF SHEET ROCK.
06/28/2017 SHEET ROCK NAILING Partial Approval CLEAN ELEVATOR FIRST LAYER AT LEVEL #4; UTILITY RISER ROOM AT STAIRWELL #3.
06/26/2017 SHEET ROCK NAILING Partial Approval AIR HANDLER #7, CORRIDOR WALL AT GL: 10.5/L. OK TO TAPE PROGRESS AREA.
06/22/2017 SHEET ROCK NAILING Partial Approval SHAFTS 6a - 6b, EAST WALLS: SECOND LAYER - HUNG AND TAPED.
06/20/2017 SHEET ROCK NAILING Partial Approval SHAFT #6B - WEST WALL (FIRE CAULKED), FIRST LAYER - OK TO COVER. SHAFT #12: NORTH AND EAST WALLS - FIRST LAYER. OK TO SECOND LAYER.
06/19/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING AT GL: H/13 - 15; LEVELS 2 - 4.5. OK TO WATERPOOOF PROGRESS AREAS.
06/15/2017 SHEET ROCK NAILING Partial Approval CLEAN ELEVATOR LEVEL 4 FIRE CAULK AND FRAMING OK.
SHAFT 12 INTERIOR FIRE CAULK NORTH SIDE OK.
COLUMN FRAMING LEVEL 4 OK / READY FOR PLB. ELECT.
SHAFT 5 LEVEL 4 OK TO TAPE. SHAFT 2 LEVEL 4 OK TO TAPE.
06/13/2017 SHEET ROCK NAILING Partial Approval SECOND LAYER TOP-OUT ON WALL AT GL: 8/G - I, SHAFTS #6A, 6B EAST WALLS HAVE BEEN FIRE CAULKED. EAST WALL SCREWING - NEED TO BE FIRE CAULKED AT GL: 13/G - N.
06/12/2017 SHEET ROCK NAILING Partial Approval CONTROL ROOM TOP-OUT (BOTH SIDES), 9' DOWN FROM DECK ABOVE, GL: 10.5/L - OK TO TAPE PROGRESS AREA.
06/08/2017 SHEET ROCK NAILING Partial Approval ELEVATORS #13 AND 14, NORTH WALL HAS BEEN FIRE CAULKED, OK TO HANG SECOND LAYER. AREAS NOT READY: LEVELS #3, SHAFTS #2, 4, 5 - NEED TO BE FIRE CAULKED. EAST SERVICE ELEVATORS AT LEVELS #3, 4, 5 - GAPS IN SHEET ROCK NEED TO BE CLOSED.
06/06/2017 SHEET ROCK NAILING Partial Approval LEVEL #4 STORAGE AREA; GL: 10/L, SOUTH WALL AT 10' TOP-OUT. OK TO TAPE PROGRESS AREA. SHAFT #7, SOUTH WALL (FIRE CAULKED); OK TO APPLY SECOND LAYER. *LEVEL #4, SHAFT #5 IS NOT READY FOR INSPECTION - NEED TO COMPETE FORE CAULKING AT DECK ABOVE. **LEVEL #3 SHAFT: SHAFT TO BE INSPECTED WAS NOT IDENTIFIED. RESCHEDULE FOR 7 JUNE.
06/05/2017 SHEET ROCK NAILING Partial Approval PASS THROUGH HALLWAY (TEMPORARY PASSAGE) AT GL: H/14 - 15, WITH A TWO HOUR FIRE RATING.
06/02/2017 SHEET ROCK NAILING Partial Approval LEVEL #4: FIRE PUMP ROOM (SOUTH WALL). EXTERIOR WALL AT GL: 4.2/G - K; SHAFT #2 ONE LAYER OF SHEET ROCK, GL: 10 AT 24" DOWN FROM DECK ABOVE. OK TO TAPE PROGRESS AREAS.
05/31/2017 SHEET ROCK NAILING Partial Approval SHAFT #4, (2 LAYERS), OK TO TAPE AND FIRE CAULK. SHAFT #5 - ONE LAYER; WEST WALL AT GGL: 4.2/I - L. OK TO TAPE PROGRESS AREA. SHAFT #2, NOT READY FOR INSPECTION.
05/30/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING AT LEVEL #4; GL: 13/G - N. OK TO WATER PROOF PROGRESS AREAS.
05/29/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING AT GL: 4.2/G - L; LEVEL 4 - 6: OK TO WATERPROOF PROGRESS AREAS.
05/25/2017 SHEET ROCK NAILING Partial Approval LEVEL #7, SHAFTS #10 AND 11; ENSURE INSULATION IS COMPLETE - OK TO COVER PROGRESS AREAS. LEVEL #2, ELECTRIC ROOM AND RISER ROOM; #0259810, 0259903. LEVEL #3, ELECTRIC ROOM AND RISER ROOMS #0359810 AND 0359903; OK TO TAPE PROGRESS AREAS.
05/23/2017 SHEET ROCK NAILING Partial Approval LEVEL #4 SHAFTS #4 AND #5 (1ST LAYER) PUMP ROOM - SOUTH WALL; OK TO COVER PROGRESS AREAS.
05/22/2017 SHEET ROCK NAILING Partial Approval LEVEL #5, SHAFTS #10 - 11, SECOND LAYER OF SHEET ROCK APPLIED. OK TO TAPE PROGRESS AREAS.
05/19/2017 SHEET ROCK NAILING Partial Approval EXTERIOR WALLS AT GL: 12/H - N, LEVELS 2 - 3; OK TO WATERPROOF PROGRESS AREAS. INTERIOR: LEVEL #4, IDF ROOM #0459810, PUMP ROOM #0459903 - OK TO TAPE PROGRESS AREAS.
05/17/2017 SHEET ROCK NAILING Partial Approval LEVEL #4, ELECTRIC ROOM #0459810 - SOUTH AND WEST WALLS; ROOM #0459610 (2 LAYERS) OF INTERIOR AT GL: 5/M - N, ESTERIOR WALLS (EAST AND NORTH); STAIRWELL #1: LEVELS #2 - 5. OK TO TAPE. VISITORS ELEVATORS (#13 AND 14), EXTERIOR WALLS AT LEVELS 8 - 2; OK TO TAPE PROGRESS AREAS.
05/16/2017 SHEET ROCK NAILING Partial Approval LEVEL #5, SHAFTS #10 AND #11; FIRST LAYER OF SHEET ROCK APPLIED; OK TO FIRE CAULK TOP AREA OF SHAFT. LEVEL #6, SHAFTS #10 AND #11: SHAFT #10, FIRST LAYER ONLY; SHAFT #11, SECOND LAYER APPLIED - OK TO TAPE AND FIRE CAULK.
05/11/2017 SHEET ROCK NAILING Partial Approval INTERIOR WALLS OF ELECTRIC ROMS AT LEVELS 8 & 9. OK TO TAPE PROGRESS AREAS.
05/09/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING AT GL: 4.2/G - H. OK TO WATER PROOF PROGRESS AREAS. INTERIOR SHEET ROCK: RESTROOM BACK WALLS AT LEVELS 5, 6, 7. OK TO TAPE PROGRESS AREAS.
04/26/2017 SHEET ROCK NAILING Partial Approval EXTERIOR (DENZ-GLAS WALLS) AT G: 10/G - N. OK TO WATERPROOF.
04/25/2017 SHEET ROCK NAILING Partial Approval STAIRWELL #1, LEVELS #1 - #4, LEVEL #2: ELECTRIC ROOMS #0259812, 02598009, 024808, 024807, IDF ROOM #0249902. OK TO TAPE PROGRESS AREAS.
04/21/2017 SHEET ROCK NAILING Partial Approval NTERIOR, SOUTH WALL OF PATIENT/STAFF ELEVATOR. HALLWAY (SINGLE LAYER - 12" DOWN FROM DECK ABOVE) GL: 11/G - N; (DOUBLE LAYER 12" DOWN FROM DECK ABOVE); GL: 11/I - J, 11.5/J - K, 11.5/N - G EAST. OK TO TAPE PROGRESS AREA.
04/20/2017 SHEET ROCK NAILING Partial Approval EXTERIOR DENZ-GLAS SYSTEM AT GL: 4.2/G - L. OK TO WATERPROOF.
04/17/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING: GL: 10/G - N (LEVEL #10); 13.5/C - I, (LEVELS 8 - 10); INSULATION: LEVEL #5: GL: 10/G - N. OK TO COVER WALLS.
04/14/2017 SHEET ROCK NAILING Partial Approval EAST WALL OF RESTROOMS #06045, 06046, 07045, 07046. OK TO TAPE PROGRESS AREAS.
04/12/2017 SHEET ROCK NAILING Partial Approval GL: 11/G - M. 12 FEET DOWN FROM CEILING. OK TO TAPE PROGRESS AREAS.
04/04/2017 SHEET ROCK NAILING Partial Approval IDF ROOMS AT LEVEL 3; #0349902; LEVEL 2; ROOMS: 0249803, 0249804. LEVEL 6 - 7: GL 9/J - N. OK TO TAPE PROGRESS AREAS.
03/29/2017 SHEET ROCK NAILING Partial Approval EXTERIOR LEVELS 6 AND 7 AT GL: 10/J - N. GL: B/12, LEVELS 4 - 10. OK TO WATER PROOF PROGRESS AREAS.
03/28/2017 SHEET ROCK NAILING Partial Approval LEVEL #4 ELECTRIC ROOM - NAILED AND TAPED.
03/21/2017 SHEET ROCK NAILING Partial Approval LEVEL #3 ELECTRIC ROOMS. CORRECTIONS EFFECTED AT ENTRY AREAS. OK TO TAPE PROGRESS AREAS.
03/15/2017 SHEET ROCK NAILING Partial Approval PENTHOUSE UPPER LEVEL - NORTH, WEST, AND SOUT WALLS. OK TO TAPE PROGRESS AREAS.
03/12/2017 SHEET ROCK NAILING Partial Approval ELEVATOR SHAFTS LEVEL 8 - ALL ELEVATORS (SHAFT ELEVATOR - WEST WALL NEEDS TO BE FIRE CAULKED); LEVEL #7 - ALL ELEVATORS EXCEPT FOR STAFF ELEVATOR; LEVEL 6; ALL ELEVATORS ARE OK. LEVEL #3 ELECTRIC ROOMS: 0349802, 03, 04, 05, 06 - INTERIOR WALLS.
03/08/2017 SHEET ROCK NAILING Partial Approval ELEVATOR #4 INTERIOR/EXTERIOR SHAFT SHEET ROCK. LEVELS 5 - 6.
03/01/2017 SHEET ROCK NAILING Partial Approval EXERIOR SHEATHING AT GL: B/10.5, LEVELS 1 - 2; B/11 - 13 LEVELS 4 - 7; 13/B - G LEVELS 4 - 7. OK TO WATERPROOF.
02/24/2017 SHEET ROCK NAILING Partial Approval NORTH WALL' GL: A.5/9 - 10. LEVELS 1 - 7. EAST WALL AT GL: C - D.5/ 15.5; LEVELS 2 - 4.
02/22/2017 SHEET ROCK NAILING Partial Approval 2 HOUR RATED WALL (SECOND LAYER) AT GL: 9/G - K.5: 1 HOUR RATED WALLS (HALLWAY) AT GL: G/9 - 11 (12' DOWN FROM DECK ABOVE.
02/21/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING, NORTH AREA AT GL: B/10.5; LEVELS 4 - 10; B/11 - 12, LEVELS 4 - 8. OK TO WATERPROOF PROGRESS AREAS.
02/14/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING AT LEVELS #6 - 10; GL: G/8 - 10; LEELS #4 - 7 AT GL: 10.5 /B - C.
01/31/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING AT GL: A.9 - C.8/10.5 AT LEVELS 4 - 6. OK TO WATER PROOF PROGRRESS AREAS.
01/27/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING: LEVELS #8 & 9 AT GL: H/5 - 9.5. PENTHOUSE EXTERIOR SHEATHING AT 28'. OK TO WATER PROOF PROGRESS AREAS.
01/24/2017 SHEET ROCK NAILING Partial Approval ELEVATOR SHAFTS AT LEVELS 2 - 5.
01/12/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING AT STAIRWELL #4. LEVEL #10; GL: 5 - 9/D.4: ROCK WOOL AND FIRE CAULKING IN PLACE AT FLOOR LEVEL.
01/08/2017 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING: GL: B/4.2 - 6; B/8.5 -9, 4.2/B -C.5 (LEVEL 1, AREA 1)
12/28/2016 SHEET ROCK NAILING Partial Approval LEVEL #4 MAIN CORRIDOR - SOUTH WALL TWO HOUR RATED AT 12' DOWN FROM DECK ABOVE - GL: F.5/4.5 - 9.5; LEVEL #3 SHAFT ELECTRIC ROOM #035980; LEVEL #2 ELECTRIC ROOMS #0259801 AND 0259802, INTERIOR/EXTERIOR - OK TO TAPE.
12/27/2016 SHEET ROCK NAILING Partial Approval LEVEL #4, MAIN HALLWAY GL: F.5/6 - 9.5 AT 12' FROM DECK DOWN. OK TO TAPE PROGRESS AREAS.
12/26/2016 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING (DENS-GLAS SYSTEM) ON NORTH WALL AT LEVELS 8 - 9. OK TO COVER.
12/21/2016 SHEET ROCK NAILING Partial Approval EXTERIOR SHEATHING (DENS-GLAS) AT LEVELS 7 & 8: GL: B/4.2 - 9.5.
12/14/2016 SHEET ROCK NAILING Partial Approval NORTH EXTERIOR WALL (DENS-GLAS SHEATHING) AT G: D/4.2 - 9; LEVELS 4 - 6.