Permit: T16CM02176

Parcel: 12310001H


Addresses:

1625 N CAMPBELL AV

Inspection Status: Approved

Inspection History: PLUMBING - MEDICAL GAS/TEST

Date Description Inspector Results Comments
04/05/2019 PLUMBING - MEDICAL GAS/TEST Approved
02/26/2019 PLUMBING - MEDICAL GAS/TEST Partial Approval Medical Gas Final certification to be completed when subject equipment is operational.
02/07/2019 PLUMBING - MEDICAL GAS/TEST Approved
10/29/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval Level #2. CT Scan #2: Oxygen, Nitrous oxide, Med Air, Med vacuum. WAGD.
10/10/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval CATH Rooms #2 & #3; all lines tested at 150 psi: Oxygen Nitrous Oxide. Medical vacuum, Medical aid. WAGD
09/06/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #2, MRI ROOM #1: NITROUS OXIDE, OXYGEN, WAGD, MED AIR, MED VACUUM, ALL TESTED AT 150 PSI. EP-1 AND EP-2, LEVEL #2, NITROUS OXIDE, OXYGEN, WAGD, MEDICAL AIR, MEDICAL VACUUM, CARBON DIOXIDE: ALL LINES YESTED AT 150 PSI
08/14/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #2, EP#1 AND EP #2: MED GAS, MED VACUUM, NITROUS OXIDE; MED AIR; WAGD, OXYGEN; CARBON DIOXIDE: ALL LINES TESTED AT 150 PSI.
08/03/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OR #18, CARBON DIOXIDE, OXYGEN, NITROUS OXIDE, MED AIR; MED VACUUM, WAGD - TESTED AT 150 PSI NITROGEN TESTED AT 275 PSI. LEVEL #2, CATH LAB #3, OXYGEN, NITROUS OXIDE, MED AIR, MED VACUUM, WAGD - TESTED AT 150 PSI.
07/13/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #2, CATH LABS #1 AND #2: LINES: OXYGEN, NITROUS OXIDE, MED AIR, WAGD, MED VACUUM.
07/09/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #2, CATH LAB #4; LINES: OXYGEN, MEDICAL AIR, NITROUS OXIDE, MEDICAL VACUUM, WAGD.
06/26/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, PROCEDURE ROOM "A": MED AIR, NITROGEN, NITROUS OXIDE, CARBON DIOXIDE, OXYGEN; MED VACUUM, WAGD. LINES TESTED AT 150 PSI; NITROGEN TESTED AT 275: ZONE VALVE BOX #325. LEVEL #2, IR #2, ZONE VALVE BOX #214, IR #2, ZONE VALVE BOX #215; LINES: WAGD, OXYGEN, NITROGEN, CARBON DIOXIDE, VACUUM, MED AIR: TESTED AT Q50 PSI, NITROGEN TESTED AT 275 PSI.
05/10/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OPERATING ROOM #22, GAS LINES 3/4" - 1 1/4": OXYGEN, NITROGEN, NITROGEN OXIDE, CARBON DIOXIDE, MED VACUUM, MED AIR, WAGD.
04/24/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #1, BOTTLE ROOM: 3/4" - 2" LINES: NITROUS OXIDE; CARBON DIOXIDE - TESTED AT 150 PSI; NITROGEN TESTED AT 275 PSI.
04/06/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval CSPD ROOMS NORTH AND SOUTH; LOW PRESSURE LINES AT 1/2" - 1" (NON MEDICAL AIR) - 10 OUTLETS
04/04/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OR'S #22 AND #23: LINES AT 3/4"- 1 1/2" IN WALLS: MED AIR, WAGD, OXYGEN, NITROUS OXIDE, CARBON DIXIDE, MED VACUUM (TESTED AT 150 PSI). NITROGEN TESTED AT 275 PSI. LEVEL #2, NITROGEN LINES AT 3/4" AT SHAFT #7 - ZONE VALVE BOX #275, MRI AREA ZONE VALVE BOX AT EQUIPMENT ALCOVE AREA, TESTED AT 275 PSI.
03/28/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, SATELLITE BIO ROOM (LINES AT 1: - 1/2"), MED AIR, MED VACUUM, OXYGEN: ALL TESTED AT 150 PSI. LEVEL #2, ZONE VALVE BOX #214; LINES AT 1/2" - 1 1/2", TESTED AT 150 PSI: OXYGEN, NITROUS OXIDE, WAGD, MED VACUUM, MED AIR. MRI 32, ZONE VALVE BOX #224, OXYGEN, MED AIR, NITROUS OXIDE, WAGD, MED VACUUM: ALL TESTED AT 150 PSI. PARTIALLY COMPLETED ROOMS: PT3, MRI 1, MRI 3 (TO BE COMPLETED AT A LATER DATE).
03/21/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #4, KNUCKLE AREA, RT ROOMS - ZONE BOX 4.1; 1/2" - 3/4" LINES (MED AIR, OXYGEN).
03/14/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #2, ZONE VALVE BOXES #214 - 215; LINES AT 3/4" - 2": OXYGEN, NITROUS OXIDE, MEDICAL AIR, MEDICAL VACUUM, WAGD. ALL LINES TESTED AT 150 PSI.
03/07/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, PROCEDURE ROOM "B" - LINES: MED VACUUM, OXYGEN, NITROUS OXIDE, CARBON DIOXIDE, WAGD (TESTED AT 150 PSI), NITROGEN LINE (TESTED AT 275 PSI). LEVEL #2, XONE BOXES #220226 - AREA #4, 220227 - AREA #7 - STANDARD MEDICAL GAS LINES.
03/01/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval MED GAS LINES (3/4" - 2") AT GL: K-M/5-8: MED AIR, OXYGEN, NITROUS OXIDE, VACUUM, WAGD; AT SHAFT #7
02/28/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OR'S #11, 12, 19, 20, 21; ANESTHEIA ROOMS, WORK EQUIPMENT ROOMS. LEVEL #1, OVERHEAD SYSTEM AND UNDERGROUND SYSTEM.
02/20/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #1, AREA #3, 1/2" - 3". SOUTH EAST BUILDING AREA - UNDERGROUND AT 4" - 6" TO HOOK-UP TO LIQAIRE TANK AREA.
02/06/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #2; 1/2" - 2" LINES TESTED AT 150 PSI IN AREAS #5, 7, 8, 9. OXYGEN, MED AIR, MED VACUUM LINES.
01/30/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OR'S #16 - 17, 3/4" - 1" LINES: OXYGEN, CARBON DIOXIDE, NITROUS OXIDE, MEDICAL AIR, MEDICAL VACUUM, MAGD - TESTED AT 150 PSI: NITROGEN TESTED AT 275 PSI.
01/25/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval EVEL #3, OR'S #11 AND #12: CARBON DIOXIDE, NITROUS OXIDE, OXYGEN, WAGD, MED AIR , MED VACUUM TESTED AT 150 psi. NITROGEN TESTED AT 275 PSI.
01/18/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OR'S #7, 8, 9, 14, AND 15 - MED GAS LINES AT 3/4" - 1 1/2": CARBON DIOXIDE, NITRUS OCXIDE, OXYGEN, MED AIR, WAGD, MED VACUUM - TESTED AT 150 PSI; NITROGEN TESTED AT 275 PSI. OVER HEAD LINES IN CORRIDOR SOUTH OF "H" LINE TO SHAFT #7.
01/16/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVELS #3 - 4, LINES AT 2" (OXYGEN) TO 4" (MEDICAL VACUUM) FROM SKIDS TO SHAFT #12, TOWER #5 FEEDER. LEVEL #3, OR #10; LINES AT 3/4" - 2" TESTED AT 150 PSI, NITROGEN TESTED AT 250 PSI.
01/08/2018 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #8, TOWER #4, LINES AT 3/4" - 3". OPERATIN G PRESSURE AT 60 - 65 PSI; OXYGEN, MED VACUUM, MED AIR.
12/28/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #8, TOWER #4 (3/4" - 2" LINES); MEDICAL GAS, MEDICAL VACUUM, OXYGEN (PATIENT BURN ROOMS). LEVEL #2, TOWER #4, 6 PATIENT ROOMS (3/4" - 2" LINES), OXYGEN, MEDICAL VACUUM, MEDICAL AIR.
12/21/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OR #5, 1/2" - 2" LINES - CARBON DIOXIDE, NITRUS OXIDE, OXYGEN, MED AIR, MED VACUUM, WAGD TESTED AT 150 PSI; NITROGEN LINES TESTED AT 275 PSI.
12/14/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OR #4, LINES AT 3/4" - 2"; NITROUS OXIDE, OXYGEN, CARBON DIOXIDE, MED AIR, MED VACUUM, WAGD - ALL LINES TESTED AT 150 psi.
12/13/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #5, TOWER #4, C-SECTION AREAS #1 - 2M BABY RESUSCITATION AREA - LINES AT 3/4" - 2": NITROUS OXIDE, OXYGEN, MED AIR, WAGD, MED VACUUM; TESTED AT 150 psi, NITROGEN LINES TESTED AT 275 psi.
12/12/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, ER #3, CARBON DIOXIDE, NITROUS OXIDE, OXYGEN, MED VACUUM, MED AIR - ALL LINES TESTED AT 150 psi. NITROGEN LINES TESTED AT 170 psi.
12/05/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #9 - TOWER #4; RISERS AT SOUTH END OF TOWER. ALL LINES TESTED AT 150 psi; OXYGEN, MED AIR, MED VACUUM (3/4" - 4" LINES).
11/28/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval NORTH AREAS TO SHAFT #7, LINES AT 1/2" - 2": OXYGEN, MED AIR, NITRUS OXIDE, MED VACUUM, MAGD. ALL LINES TESTED AT 150 PSI.
11/28/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OR #2, LINES AT 3/4" - 2", FROM Z BOX 3.2 TO OR #2. MED VACUUM, CARBON DIOXIDE, OXYGEN, MED AIR, WAGD, NITROUS OXIDE - ALL TESTED AT 150psi. NITROGEN TESTED AT 225psi.
11/20/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, OPERATING ROOM $1; LINES AT 1/2" - 2" AT STATION #ZVB 3 - 2 (CARBON DIOXIDE, NITROGREN, NITRUS OXIDE, OXYGEN, MEDICAL AIR, WAGD, MEDICAL VACUUM.
11/09/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #8, TOWER #4, EAST AND WEST WINGS; MED AIR, OXYGEN, MED GAS - LINES 3/4" - 2". ALL LINES TESTED AT 150 PSI.
11/06/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, GL: 4.2 - 10/C -H; MEDICAL AIR, OXYGEN, MEDICAL VACUUM. (3/4" - 2" LINES.)
10/31/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #3, TOWER #5, MED AIR, OXYGEN, MED VACUUM: (1/2" - 2" LINES). ALL LINES TESTED AT 150 psi.
10/26/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #7, TOWER #4, MED VACUUM, MED AIR, OXYGEN LINES - TESTED AT 150psi. LEVEL #3, SHAFT #7 TO ZONE VALVES #3-27, 3-28, 3-29; ALL LINES TESTED AT 150psi.
10/19/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #6, TOWER #4, MED GAS, OXYGEN, MED VACUUM LINES (1/2" - 2"). ALL LINES TESTED AT 150 psi
10/18/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #4, TOWER #4, NON-MEDICAL AIR LINES (3/4"), MEDICAL AIR, OXYGEN, VACUUM LINES (3/4" - 6")
09/26/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #9, TOWER #5, (3/4" - 3" LINES) Z BOXES 9.1, 9.2; ALL TESTED AT 60 psi. LEVEL #5, TOWER #4, LINES TESTED AT 60 psi. Z BOXES 5 - 8, 5-9.
09/20/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #1, AREA #10; 2" COPPER LINE TESTED AT 150 psi - GL; 13/N - M. OK TO COVER PROGRESS AREA.
09/19/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval LEVEL #5, TOWER #4, PATIENT ROOMS #1 - 12; 4 TRIAGE ROOMS.
09/15/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval OXYGEN, MED AIR, VACUUM LINES TESTED AT 150 psi. GL: G/12.
09/06/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval 3/4" - 2" GAS LIES ON LEVELS #7 - 8; TOWER #5. ALL LINES TESTED AT 150 psi
07/14/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval WELL BABY AREA AT LEVEL #5; LEAK REPAIRED - LINES TESTED AT 150 psi.
06/06/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval THREE MED GAS LINES IN SHAFT #7; LEVELS #4 - 5; GL 9/K: TESTED AT 150 psi.
05/10/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval GAS LINES IN SHAFT #7, UNDER TEST AT 150 psi; WATER LINES WERE NOT READY FOR INSPECTION (NOT UNDER TEST)
02/21/2017 PLUMBING - MEDICAL GAS/TEST Partial Approval SHAFT #11, LEVELS 4 - 9; ALL GAUGES READ 150 PSI AT THE TIME OF THE TESTING: RESULTS OF TESTING ARE LOCATED WITH KEVIN MOORE.
02/16/2017 PLUMBING - MEDICAL GAS/TEST Not ready for Inspection WILL RESCHEDULE FOR 17 FEBRUARY.