Permit: TC-COM-0423-00942
Permit Details
Apply Date:
04/02/2023
Applicant:
Eduardo Hernandez
Description:
City of Tucson Southside Public Safety Facility - Police and Fire Station
Permit Reviews
Permit Number - TC-COM-0423-00942
Permit Status: Inspections
Permit Description: City of Tucson Southside Public Safety Facility - Police and Fire Station
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/05/2024 | COMMERCIAL REVIEW - FULL v.5 | 09/17/2024 | APPROVED |
| 12/07/2023 | COMMERCIAL REVIEW - FULL v.2 | 12/15/2023 | REQUIRES RESUBMIT |
| 03/21/2024 | COMMERCIAL REVIEW - FULL v.3 | 03/27/2024 | REQUIRES RESUBMIT |
| 05/03/2024 | COMMERCIAL REVIEW - FULL v.4 | 05/14/2024 | REQUIRES RESUBMIT |
| 09/17/2024 | RESTAMP - COMMERCIAL v.1 | 09/20/2024 | APPROVED |
| 04/06/2023 | COMMERCIAL REVIEW - FULL v.1 | 05/04/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0423-00942
Permit Status: Inspections
Permit Description: City of Tucson Southside Public Safety Facility - Police and Fire Station
Total Outstanding Activity Conditions - 13
| Date | Name |
|---|---|
| 03/26/2024 | AIR BALANCING REPORT IS REQUIRED. |
| 03/26/2024 | Special inspections must be performed by an approved third party inspection agency at the owner's expense. Special inspection forms and reports are required to be submitted for review and approved prior to issuance of final approval documents. |
| 03/26/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 03/26/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 03/26/2024 | Masonry Inspection Report submittal review is required. |
| 03/26/2024 | Post-Installed Anchor Inspection Report is required. |
| 03/26/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 03/26/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 03/26/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
| 03/26/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
| 03/26/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
| 09/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Confirmation of payment of sewer connection and or industrial waste fees must be provided prior to issuance of a Temporary Certificate of Occupancy. Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
| 12/18/2023 | Prior to project being finalized applicant must provide easement abandonment and recordation information. |
Conditions
Permit Number - TC-COM-0423-00942
Permit Status: Inspections
Permit Description: City of Tucson Southside Public Safety Facility - Police and Fire Station
| Date | Description | Comments |
|---|---|---|
| 04/06/2023 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. | |
| 09/05/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0423-00942
Permite Description: City of Tucson Southside Public Safety Facility - Police and Fire Station
Total Outstanding Inspections - 35
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/22/2024 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 10/4/24: not ready still laying rebar and j bolt plates. 10/9/24: partial footing inspection at Area D ( picture provided with area that has been inspected under attachments). Ok to proceed in progress area . footing reinforcement for Area C/B. Open court yard area D. Interior Columbs at area C. Total of 5. Total of two columns at area A/B. 10/17/2024 10/22/24: footing reinforcement per plan at area A/B ok to proceed. |
| 10/24/2024 | COT - LCME - Mechanical Underground | N/A | Not Ready | |
| 11/05/2024 | COT - LCBU - Stem Wall/Retaining Wall | N/A | Partial Pass | North portion of structure ; Fire side of structure stem walls at rooms 253, 252, 251, 255, 254, 25^, 250, 221, 222< 220, 219, 218. OK to place grout in progress areas. |
| 12/11/2024 | COT - LCPL - Rough Soil | N/A | Partial Pass | 12/11/24: plumbing underground at schematic #8 waste and vent passed ok to backfill. |
| 04/18/2025 | COT - LCBU - Masonry Pregrout | N/A | Partial Pass | 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed 11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8". 11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253). 12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout. 12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4" 12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4". 12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8" 12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout. 12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'. 4/18/25: reinforcement per plan at Corridor 201 east wall, north east locker room top out, 2nd lift at rooms (254,251,252,253,255) approved. |
| 04/18/2025 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 3-25-25, reinforcement per plans on separation wall between the dorms at 18' 8". Public lobby east lintel 23' 4" & Fire court yard north wall @ 26' 8". Okay to grout. 3/28/25: reinforcement per plan at Locker Rooms East Wall (Elev 4'8"-9'4"), (rooms (178,177,179,183) East wall (Elev 4'8"-9'4")). 4-2-25, reinforcement per plans on corridor lintel #201-(south lintel) at 18' 8". Okay to grout. 4/11/25: reinforcement per plan at Locker rooms (NORTH,SOUTH, AND WEST) top out., East wall corridor 201 lintel. 4/14/25: Reinforcement per plan at Locker room east wall top out, public lobby east 101, evidence drop off room 175 west wall, 4/15/25 west wall of 163. (14'-18'). West wall of 175,176. (14'-16'8"). West wall room 201. (13'4"-17'4"). East wall room 201 (16'-20'). North and east wall of rooms 251-257. (0-4'8"). West wall of room 257 (0-4'8"). Approved for grout per third party report. 4/18/25: reinforcement per plan at Corridor 201 east wall, north east locker room top out, 2nd lift at rooms (254,251,252,253,255) approved. |
| 06/17/2025 | COT - LCBU - Roof Nailing | N/A | Partial Pass | 6-17-25: fitness parapet nailing inspection approved. Okay to proceed with construction. |
| 07/10/2025 | COT - LCEL - Outdoor Lighting | N/A | Partial Pass | Lighting in exterior soffits at fitness area and West soffit of apparatus area. Ok to cover progress areas. |
| 12/10/2024 | COT - LCEL - Electrical Underground | N/A | Partial Pass | Partial pass. Electrical. Stubbed up vertically. D area. Out door receptacles. Controls for garage door. 10/18/2024 10/23/24: electrical underground at MDF room 114 passed, (8)4” conduit 50’ run from building at SES to transformer, electrical underground for ATS per plans, electrical underground at room 196 per plans ok to proceed. 11/14/24: electrical underground passed from room 226 (COMM) to room 114 (MDF), storage room to ATS complete ok to backfill. 11/15/24: reinforcement/ grounding per plan at 3 light pole base SG at north west trash enclosure. 12/2/24: reinforcement/ grounding per plan at 2 light pole base one on north and one south of south entry on FAIR ST. 12/10/24:12/3/24: partial pass for pre-slab at Area C south end and area d south end 12/10/24: reinforcement per plan at slab in rooms 141,137,171,172,177,179,179,183,182,184,180,181,185,186,187,194,193,189,190,191,192. |
| 11/06/2024 | BULD - Electrical Clearance | N/A | Partial Pass | Request meter and service for temporary construction power; power for construction trailers. Code is TMPP - sent 11/22 - JConrad |
| 09/17/2025 | COT - LCPL - Gas Pressure Test | N/A | Partial Pass | Overhead 2” gas line from Area A through apparatus room to SW gas meter location. |
| 09/22/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Partial Pass | 9-22-25: firewall caulking, framing, plumbing, mechanical, electrical above ceiling, electrical intermediates verified per plans at room's 193, 177, 194, 181, 182, 183, 184, 185. 186, 187, 188, 189, 190, 191. Okay to continue with construction at progress areas. |
| 09/22/2025 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | 9-22-25: firewall caulking, framing, plumbing, mechanical, electrical above ceiling, electrical intermediates verified per plans at room's 193, 177, 194, 181, 182, 183, 184, 185. 186, 187, 188, 189, 190, 191. Okay to continue with construction at progress areas. |
| 08/28/2025 | COT - LCBU - Framing | N/A | Partial Pass | Fitness room soffits, Ok to set mechanical and lighting |
| 05/23/2025 | COT - LCEL - Electrical Progress | N/A | Partial Pass | 5-23-25, in wall electrical at kitchen, office-room 223, and Area A verified per plans. Okay to spray foam at progress areas. |
| 10/17/2025 | COT - LCME - Mechanical Above Ceiling | N/A | Partial Pass | 10-17-25: all MEP's building above ceiling and in wall for rooms 254,255 and lockers 152&153 173,173,174,175,178,179, and 194 verified per plans. Okay to continue construction at progress areas. |
| 09/10/2025 | COT - LCPL - Plumbing Above Ceiling | N/A | Partial Pass | Areas C and D all joints above ceilings; Ok to insulate joint areas. |
| COT - FCON - Hood System - Final | N/A | Not Ready | We dont do smoke test. | |
| 07/17/2025 | COT - LCBU - Building Progress | N/A | Partial Pass | 7-17-25: drywall/durock nailing on room's 237-240 verified per plans. Okay for tape & texture. |
| 10/29/2025 | COT - LCME - Kitchen Hood | N/A | Partial Pass | 10-29-25: verified 1st layer of hood wrap-okay for second layer at room's 204& 148. |
| 10/29/2025 | COT - LCPL - Plumbing Roof Drains | N/A | Partial Pass | 10-29-25: roof drains at apparatus bay verified under test. |
| 08/11/2025 | COT - LCPL - Sewer | N/A | Partial Pass | Roughly 60’ transition from 6” to 4”. Tracer wire in place along with bedding heading toward the apperatus bay from man hole at park. Okay to backfill progress areas at own risk. Shading material is required. 8/11/2025 |
| 11/13/2025 | COT - LCBU - Building Above Ceiling | N/A | Partial Pass | 11-13-25: mechanical, electrical and plumbing above ceiling at Debriefing and interview lobby LMS approved. Okay to continue with construction at progress areas. |
| 08/26/2025 | COT - LCME - Mechanical Progress | N/A | Partial Pass | Metal duct systems in processing area; ensure pooky covering is complete on all ducts. |
| 12/24/2024 | COT - LCPL - Plumbing Progress | N/A | Partial Pass | 12-24-24, partial pressure test for system 1 waste & vent.Okay to backfill inspected area. |
| 12/10/2024 | COT - LCBU - Preslab | N/A | Partial Pass | 12/3/24: partial pass for pre-slab at Area C south end and area d south end 12/10/24: reinforcement per plan at slab in rooms 141,137,171,172,177,179,179,183,182,184,180,181,185,186,187,194,193,189,190,191,192. |
| 12/02/2025 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Partial Pass for Police Station side of Sprinkler System. |
| 12/03/2025 | COT - LCPL - Gas Final | N/A | Partial Pass | 12-3-25: partial pass. |
| 07/10/2025 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | Dormitory areas A and B unit rooms and restrooms above hard ceilings. Ok to cover progress areas. |
| 11/15/2024 | COT - LCEL - Grounding/Bonding | N/A | Partial Pass | 10/9/24: partial for UFER Partial pass. Electrical. Stubbed up vertically. D area. Out door receptacles. Controls for garage door. 10/18/2024 10/23/24: electrical underground at MDF room 114 passed, (8)4” conduit 50’ run from building at SES to transformer, electrical underground for ATS per plans, electrical underground at room 196 per plans ok to proceed. 11/14/24: electrical underground passed from room 226 (COMM) to room 114 (MDF), storage room to ATS complete ok to backfill. 11/15/24: reinforcement/ grounding per plan at 3 light pole base SG at north west trash enclosure. |
| COT - FCON - Fire - Final | N/A | Scheduled | ||
| 12/04/2025 | COT - FCON - Alarm - Final | N/A | Partial Pass | Tested All Smoke Detectors, Heat Detectors, Duct Detectors, Horn/Strobes, Tampers and Water Flows on Police Station Side. All passed. Will test Fire Station at a later date. |
| COT - LCBU - Building Final | N/A | Requested | ||
| 12/05/2025 | COT - LCEL - Electrical Final | N/A | Partial Pass | 12-5-25: partial pass- on electrical final for room's 137, 13, 139, 105, 107, public lobby. Label all receptacles throughout-will verify at upcoming inspections. |
| COT - LCME - Mechanical Final | N/A | Requested |
Completed Inspections
Permit Status: Inspections
Permit Number: TC-COM-0423-00942
Permit Description: City of Tucson Southside Public Safety Facility - Police and Fire Station
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/16/2025 | BULD - Electrical Clearance | Passed | Ok to set meter; cannot energize system until 2nd Party Final Inspection (1 August). Code: ECO | |
| 12/03/2025 | COT - LCEL - Electrical Above Ceiling | Passed | 12-3-25: electrical above ceiling approved. | |
| 12/03/2025 | COT - LCEL - Grounding/Bonding | Passed | 12-3-25: grounding/bonding approved. | |
| 12/03/2025 | COT - BULD - SWG Clearance | Passed | 12-3-25: okay to install meter. Clearance issued to SWG. |
Scheduled Inspections
Scheduled Inspections - TC-COM-0423-00942
Status: Inspections
Description: City of Tucson Southside Public Safety Facility - Police and Fire Station
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 12/02/2025 | COT - FCON - Fire - Final | Scheduled |