Parcel: 13216600A


Addresses:

4410 S PARK AV


Inspection Status: Partial Pass

Inspection History: COT - LCBU - Stem Wall/Retaining Wall 

Permit Number - TC-COM-0423-00942

Inspection Description - COT - LCBU - Stem Wall/Retaining Wall 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
10/17/2024 COT - LCBU - Stem Wall/Retaining Wall  Partial Pass Stem wall/ area perimeter of locker rooms pending east wall.
Perimeter of processing building including west wing wall of sally port area. Okay to grout progress areas. 10/17/2024
10/18/2024 COT - LCBU - Stem Wall/Retaining Wall  Partial Pass east wall from evidence drop off 175 to CRU 132. Wall along the Men’s room 170, supply 171, armory 172. Okay to grout progress areas. 10/18/2024
10/24/2024 COT - LCBU - Stem Wall/Retaining Wall  Partial Pass Corridor wall west end of 149 and 176 all the way to south end of sally port. Break room 148. Open courtyard area. Corridor 142 and 113. Admin 111. North wall of those rooms. East wall of room 102,112, and 115. 10/24/2024
10/28/2024 COT - LCBU - Stem Wall/Retaining Wall  Partial Pass Vertical and horizontal reinforcements along with c hooks approved. Double width wall at CRU #132 - Detective #129 towards front lobby #116-#117 heading north. Public entrance (northeast). 1st lift. Okay to grout progress areas. 10/28/2024
10/29/2024 COT - LCBU - Stem Wall/Retaining Wall  Partial Pass Área D. West side. 181 north side. 4 adult pods. 189-192. 195,193,194,180,177,178,179. Okay to grout progress areas. 10/29/2024
10/30/2024 COT - LCBU - Stem Wall/Retaining Wall  Partial Pass Stem wall/ area perimeter of locker rooms pending east wall.
Perimeter of processing building including west wing wall of sally port area. Okay to grout progress areas. 10/17/2024

east wall from evidence drop off 175 to CRU 132. Wall along the Men’s room 170, supply 171, armory 172. Okay to grout progress areas. 10/18/2024

Corridor wall west end of 149 and 176 all the way to south end of sally port. Break room 148. Open courtyard area. Corridor 142 and 113. Admin 111. North wall of those rooms. East wall of room 102,112, and 115. 10/24/2024

Vertical and horizontal reinforcements along with c hooks approved. Double width wall at CRU #132 - Detective #129 towards front lobby #116-#117 heading north. Public entrance (northeast). 1st lift. Okay to grout progress areas. 10/28/2024

Área D. West side. 181 north side. 4 adult pods. 189-192. 195,193,194,180,177,178,179. Okay to grout progress areas. 10/29/2024
10/30/24: reinforcement per plan at stem wall in rooms. 104,105,106,107,108,109,110 ok to fully grout progress areas.
11/04/2024 COT - LCBU - Stem Wall/Retaining Wall  Not Ready Contractor cancelled due to inclement weather.
11/05/2024 COT - LCBU - Stem Wall/Retaining Wall  Partial Pass North portion of structure ; Fire side of structure stem walls at rooms 253, 252, 251, 255, 254, 25^, 250, 221, 222< 220, 219, 218. OK to place grout in progress areas.
11/06/2024 COT - LCBU - Stem Wall/Retaining Wall  Partial Pass Stem walls at Fire portion of building; turn-out, 253, 252, 251, 255, 254, 256, 250, 221, 222, 220, 219, 218. OK to place grout in progress areas.