Inspection Status: Partial Pass
Inspection History: COT - LCBU - Roof Nailing
| Date |
Description |
Inspector |
Results |
Comments |
| 05/12/2025 |
COT - LCBU - Roof Nailing |
|
Partial Pass |
5-12-25, Inspected wall framing on south wall of MDF room #114. Submit an engineer RFI fix for wall framing/ cmu wall box cut out. Not allowed to cut header on metal framing. Sheathing/nailing on each side of apparatus parapet located on west side verified per plans. Okay to continue construction at progress areas. |
| 05/16/2025 |
COT - LCBU - Roof Nailing |
|
Partial Pass |
5-16-25, screws on plywood on east side "apparatus " parapet framing verified per plans . Okay to continue with construction progress areas. |
| 06/13/2025 |
COT - LCBU - Roof Nailing |
|
Partial Pass |
6/13/2025 Plywood nailing inspection for parapet at Public Entrance, Fitness Area, South and Southeast parapet. Okay to proceed with progress areas. |
| 06/17/2025 |
COT - LCBU - Roof Nailing |
|
Partial Pass |
6-17-25: fitness parapet nailing inspection approved. Okay to proceed with construction. |