Inspection Status: Re-inspection required
Inspection History: COT - LCEL - Electrical Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/15/2026 | COT - LCEL - Electrical Final | Re-inspection required | 4-15-26: label junction box above ceiling throughout apparatus bay, label disconnect at decon room/ no power at receptacle, open knockout at junction box southwest area of apparatus bay, label receptacle at north wall of dayroom, label junction box electrical room 229, complete installation of card reader dorm corridor, label receptacles at mdf room, label floor receptacles at community room. Note: still pending- rooftop & exterior. |
|
| 04/21/2026 | COT - LCEL - Electrical Final | Partial Pass | Roof inspection completed. Other items have been completed. Pending exterior. 4/21/2026 | |
| 04/21/2026 | COT - LCEL - Electrical Final | Partial Pass | Roof inspection completed. Other items have been completed. Pending exterior. 4/21/2026 | |
| 12/03/2025 | COT - LCEL - Electrical Final | Partial Pass | 12-3-25: electrical final on electrical room-provide permanent schedules for all panels, open knockout at junction box at east wall of electrical room, weather resistant receptacles are required on all exterior receptacles [ same applies for rooftop, receptacles].Electrical final for room's, 143, 119, 120, 121, 145, 125, 126, 127, 160, 159, 158, 131, 123, 124, 130, 117, 131, 132, 134, 165, 133, 164, corridor 166, 168, 170, 169, 162, 171, 148, 151-add cover plates to receptacles at locker together with a shackle at breakers or disconnect electrical wires from breakers, 155-add cover plates & a shackle at breakers, 163, 162, 179, 187, 194, 175, 174, 173, 195. Reschedule inspection when listed above items have been corrected. Submit an RFI to the city for review/approval for the roof drains & SES, and a 3rd party inspection report for the outdoor lighting is required. |
|
| 12/05/2025 | COT - LCEL - Electrical Final | Partial Pass | 12-5-25: partial pass- on electrical final for room's 137, 13, 139, 105, 107, public lobby. Label all receptacles throughout-will verify at upcoming inspections. |
|
| 12/10/2025 | COT - LCEL - Electrical Final | Re-inspection required | 12/10/25: PD half of property: properly support EMT at RTU south east,WR receptacles required at RTU south east corner, seal conduits at roof(2), bathroom door push 5 pounds opening force, knee guards required at lavatories throughout, | |
| 12/11/2025 | COT - LCEL - Electrical Final | Partial Pass | 12-11-25: partial pass-electrical corrections made on PD half of property. |