Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCPL - Plumbing Progress
Permit Number - TC-COM-0423-00942
Inspection Description - COT - LCPL - Plumbing Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required 12/3/24: Partial plumbing pressure test on System 1 in area B. Ok to backfill shading required 12/5/24: domestic water from back flow preventer to building tie in attic south west corner under 100psi ok to backfill progress area. 12-24-24, partial pressure test for system 1 waste & vent.Okay to backfill inspected area. 1/8/25: plumbing underground at Area A rooms 251,252,253,254,255,256. Ok to backfill. |
|
| 01/15/2025 | COT - LCPL - Plumbing Progress | Partial Pass | Plumbing underground in kitchen area; concrete has been placed in subject area. | |
| 01/17/2025 | COT - LCPL - Plumbing Progress | Canceled | Contractor cancelled. | |
| 01/22/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required 12/3/24: Partial plumbing pressure test on System 1 in area B. Ok to backfill shading required 12/5/24: domestic water from back flow preventer to building tie in attic south west corner under 100psi ok to backfill progress area. 12-24-24, partial pressure test for system 1 waste & vent.Okay to backfill inspected area. 1/8/25: plumbing underground at Area A rooms 251,252,253,254,255,256. Ok to backfill. 1/22/25: Sand/oil interceptor at south west corner under pressure ok to backfill. |
|
| 01/31/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 4” waste line in apparatus room,,approximately 50’. Ok to cover progress area. | |
| 02/11/2025 | COT - LCPL - Plumbing Progress | Partial Pass | Apparatus room Southeast area, 6” sewer line approximately 30’ for system #2. Ok to cover progress area. | |
| 02/13/2025 | COT - LCPL - Plumbing Progress | Partial Pass | Apparatus room, Bay #6 area, 6” line with 5 lateral lines (approximately 85’). Ok to cover progress areas. | |
| 02/20/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required 12/3/24: Partial plumbing pressure test on System 1 in area B. Ok to backfill shading required 12/5/24: domestic water from back flow preventer to building tie in attic south west corner under 100psi ok to backfill progress area. 12-24-24, partial pressure test for system 1 waste & vent.Okay to backfill inspected area. 1/8/25: plumbing underground at Area A rooms 251,252,253,254,255,256. Ok to backfill. 1/22/25: Sand/oil interceptor at south west corner under pressure ok to backfill. 2/20/25: Sewer underground at SW corner of Apparatus Bay under pressure and per plans. |
|
| 05/08/2025 | COT - LCPL - Plumbing Progress | Not Ready | 5-8-25, not ready. | |
| 05/12/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 5-12-25, partial pass for 4-4" Schedule 40 roof drains under test located in room 229. Okay to proceed with build at progress areas. | |
| 05/23/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 5-23-25, storm drain's at corridor-201, community room and area A and B approved. Kitchen in wall DWV, domestic together with gas line verified under test and per plans. Okay to continue construction at progress areas. | |
| 06/05/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 6/5/2025 Restroom 209 & 217 domestic water approved. | |
| 06/09/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 211,209,224 area A plumbing in walls approved. Area B. 237,238,239,240. In wall and OH. Approved. |
|
| 06/13/2025 | COT - LCPL - Plumbing Progress | Not Ready | ||
| 06/17/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 6-17-25: (In wall domestic/roof drains/gas line inspections)in wall domestic on restroom room 140, 4" Charlotte roof drains at corridor 136, open courtyard gas line, police courtyard hose bib and gas line-under test, room 148 domestic and DWV, room 151-domestic and 4-4" Charlotte roof drains, Area C & D (spray foam areas only)-room 132 domestic & 2-4" Charlotte roof drains, rm 129-4" Charlotte roof drains, fire riser rm 115-hose bib, Area-A kitchen in wall domestic and 3 Condensate lines at rm 222. Areas mentioned were verified under test and per approved plans-okay to continue construction at progress areas. | |
| 07/07/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 7/7/25: plumbing intermediate in-wall at break room 123 per approved plans and under pressure. | |
| 07/23/2025 | COT - LCPL - Plumbing Progress | Partial Pass | Area A, rooms and restrooms 105, 107, 168, 172 in wall plumbing. | |
| 08/01/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 8-1-25: in wall domestic Area D, room 147 verified per plans. Okay to continue construction at progress area. | |
| 08/07/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 8-7-25: sewer connection verified per plans. Okay to backfill approximately 80' of 6" SDR35 PVC. | |
| 10/09/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 10/9/25: 252-255 in wall domestic and DWV above ceiling | |
| 10/17/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 10-17-25: all MEP's building above ceiling and in wall for rooms 254,255 and lockers 152&153 173,173,174,175,178,179, and 194 verified per plans. Okay to continue construction at progress areas. | |
| 10/28/2024 | COT - LCPL - Plumbing Progress | Not Ready | ||
| 10/29/2024 | COT - LCPL - Plumbing Progress | Not Ready | ||
| 10/29/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 10-29-25: overhead domestic pressure test verified at 100psi at apparatus bay. Okay to continue with construction at progress areas. | |
| 11/10/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 11/10/2025 partial pass tie in from Underground inspection for sand/oil interceptor to 4 trench drains north of apparatus bay. Okay to backfill progress areas. | |
| 11/13/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 11-13-25: mechanical, electrical and plumbing above ceiling at Debriefing and interview lobby LMS approved. Okay to continue with construction at progress areas. | |
| 11/18/2024 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required | |
| 11/22/2024 | COT - LCPL - Plumbing Progress | Partial Pass | Underground plumbing in area C. Ok to cover progress areas. | |
| 12/03/2024 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required 12/3/24: Partial plumbing pressure test on System 1 in area B. Ok to backfill shading required |
|
| 12/06/2024 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required 12/3/24: Partial plumbing pressure test on System 1 in area B. Ok to backfill shading required 12/5/24: domestic water from back flow preventer to building tie in attic south west corner under 100psi ok to backfill progress area. |
|
| 12/17/2024 | COT - LCPL - Plumbing Progress | Not Ready | Contractor cancelled. | |
| 12/24/2024 | COT - LCPL - Plumbing Progress | Partial Pass | 12-24-24, partial pressure test for system 1 waste & vent.Okay to backfill inspected area. |