Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCPL - Plumbing Progress
Permit Number - TC-COM-0423-00942
Inspection Description - COT - LCPL - Plumbing Progress
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/08/2025 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required 12/3/24: Partial plumbing pressure test on System 1 in area B. Ok to backfill shading required 12/5/24: domestic water from back flow preventer to building tie in attic south west corner under 100psi ok to backfill progress area. 12-24-24, partial pressure test for system 1 waste & vent.Okay to backfill inspected area. 1/8/25: plumbing underground at Area A rooms 251,252,253,254,255,256. Ok to backfill. |
|
10/28/2024 | COT - LCPL - Plumbing Progress | Not Ready | ||
10/29/2024 | COT - LCPL - Plumbing Progress | Not Ready | ||
11/18/2024 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required | |
11/22/2024 | COT - LCPL - Plumbing Progress | Partial Pass | Underground plumbing in area C. Ok to cover progress areas. | |
12/03/2024 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required 12/3/24: Partial plumbing pressure test on System 1 in area B. Ok to backfill shading required |
|
12/06/2024 | COT - LCPL - Plumbing Progress | Partial Pass | 11/18/24: Plumbing underground for System 2 passed ok to proceed with backfill. Shading required 12/3/24: Partial plumbing pressure test on System 1 in area B. Ok to backfill shading required 12/5/24: domestic water from back flow preventer to building tie in attic south west corner under 100psi ok to backfill progress area. |
|
12/17/2024 | COT - LCPL - Plumbing Progress | Not Ready | Contractor cancelled. | |
12/24/2024 | COT - LCPL - Plumbing Progress | Partial Pass | 12-24-24, partial pressure test for system 1 waste & vent.Okay to backfill inspected area. |