Parcel: 13216600A


Addresses:

4410 S PARK AV


Inspection Status: Partial Pass

Inspection History: COT - LCEL - Electrical Progress  

Permit Number - TC-COM-0423-00942

Inspection Description - COT - LCEL - Electrical Progress  

Inspection Status - Partial Pass

Date Description Inspector Results Comments
05/06/2025 COT - LCEL - Electrical Progress   Partial Pass 5-6-25, electrical in wall exterior side only on dorm rooms verified per plan. Okay to spray foam exterior walls at progress areas.
05/15/2025 COT - LCEL - Electrical Progress   Partial Pass Dorm rooms in area B, single rooms and corridors. Ok to insulate and cover walls.
05/23/2025 COT - LCEL - Electrical Progress   Partial Pass 5-23-25, in wall electrical at kitchen, office-room 223, and Area A verified per plans. Okay to spray foam at progress areas.
06/03/2025 COT - LCEL - Electrical Progress   Partial Pass Area A. Electrical interior walls. 201-223. Okay to one side progress areas.
Spray foam Insulation at all exterior walls area A. 201-223. 6/3/2025
06/09/2025 COT - LCEL - Electrical Progress   Partial Pass 6/9/2025 108, 109, 110. Electrical in walls at exterior only. Okay to proceed progress areas.
06/11/2025 COT - LCEL - Electrical Progress   Partial Pass Electrical in walls. Exterior walls Area C and D Areas to receive spray foam insulation approved. Okay to proceed progress areas. 6/11/2025
07/07/2025 COT - LCEL - Electrical Progress   Not Ready
07/09/2025 COT - LCEL - Electrical Progress   Partial Pass 7-9-25: in wall rough electrical on rooms east of corridor 135. Okay to continue with construction at progress areas.
07/23/2025 COT - LCEL - Electrical Progress   Partial Pass Area A, in wall electric.
COT - LCEL - Electrical Progress   Partial Pass 8-1-25: electrical progress & framing for room's 147,148, 162, 163, 147, 148, Corridor 166, 161 verified per plans. Okay to continue with construction at progress areas.
COT - LCEL - Electrical Progress   Partial Pass 8-13-25: In wall electrical & framing Area D-men's/woman's locker rooms approved. Okay to continue with construction at progress areas.
COT - LCEL - Electrical Progress   Partial Pass 8-20-25: room 147 & 148 (soffits & ceiling lights). In wall electrical/framing at 193 & 194, 173, 174, 175, 187 (fur out framing ). Okay to continue with construction at progress areas.
10/17/2025 COT - LCEL - Electrical Progress   Partial Pass 10-17-25: all MEP's building above ceiling and in wall for rooms 254,255 and lockers 152&153 173,173,174,175,178,179, and 194 verified per plans. Okay to continue construction at progress areas.