Date Description Inspector Results Comments
01/03/2025 COT - LCBU - Masonry Pregrout  Partial Pass Room #116, East interview lobby; CMU wall at 4’8” - 9’4”. Apparatus bay at Room #250, West side - 4 columns at 18’. OK to grout progress areas.
01/08/2025 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'.
1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
01/09/2025 COT - LCBU - Masonry Pregrout  Partial Pass Pre-grout for armory room, CMU walls; North and South at 9’4”. Northeast area of room #102 at 0’ - 4’. Southwest area of apparatus bay - pier at 9’4”. OK to grout progress areas.
01/15/2025 COT - LCBU - Masonry Pregrout  Partial Pass Apparatus room East CMU wall at 23’4”. OK to grout progress areas.
01/17/2025 COT - LCBU - Masonry Pregrout  Partial Pass Evidence room #164, South CMU wall at 14’4”. Apparatus room #251, North CMU wall topped-out at 24’8”. Ok to grout progress areas.
01/22/2025 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'.
1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
1/22/25: reinforcement per plans at apparatus bay south west piers. North wall of rooms (143,142,113,111,102,) per plan at third lift ok to continue, first lift at west and south walls rooms (195,192,196,190).
01/27/2025 COT - LCBU - Masonry Pregrout  Partial Pass Masonry pre-grout at 0” - 56” in electric room, (West and North walls), holding rooms (North and South walls), community room #108, storage room #109, Dorms #213 - 215, Captain’s office. Ok to place grout in progress areas.
01/29/2025 COT - LCBU - Masonry Pregrout  Partial Pass 1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
1/22/25: reinforcement per plans at apparatus bay south west piers. North wall of rooms (143,142,113,111,102,) per plan at third lift ok to continue, first lift at west and south walls rooms (195,192,196,190).
01/29/2025 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'.
01/31/2025 COT - LCBU - Masonry Pregrout  Partial Pass Community room and storage area in Area C, at 0” - 48”. Ok to grout progress areas.
02/03/2025 COT - LCBU - Masonry Pregrout  Partial Pass 1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
1/22/25: reinforcement per plans at apparatus bay south west piers. North wall of rooms (143,142,113,111,102,) per plan at third lift ok to continue, first lift at west and south walls rooms (195,192,196,190).
2/3/25: reinforcement approved by third party inspector at East wall of rooms (102,112,115,116,117) Elevation 9'4" to 14', North Wall of rooms (116 (Lintels)) Elevation 12' to 14', West wall Column at SW Corner of room (205) Elevation 14' to 18'8".
02/04/2025 COT - LCBU - Masonry Pregrout  Partial Pass Area C; Area C, GL: #2, North CMU wall at 18’8”. Community room to locker room, North CMU wall at 15’8” - 16’11”. Apparatus room, Southwest corner 2 each columns at 18’. Ok to grout progress areas.
02/07/2025 COT - LCBU - Masonry Pregrout  Partial Pass Community area East wall at 18’8” in rooms 102 0 112, 115, 117. OK to place grout in progress areas.
02/10/2025 COT - LCBU - Masonry Pregrout  Partial Pass Fitness room, South wall at 23’4”; Administration area and fire riser rooms at 18’8”. OK to grout progress areas
02/12/2025 COT - LCBU - Masonry Pregrout  Partial Pass Administration and Fire Riser room walls (North and South) at 20’; Interview lobby (North and South) at 20’; Restrooms #105 - 107 at 9’4”. Ok to grout progress areas.
02/13/2025 COT - LCBU - Masonry Pregrout  Partial Pass Cross over wall area at bays 1 - 3, at 22’11”; community room, storage area, court yard: North, South, East walls at 9’4’. Ok to grout progress areas.
02/14/2025 COT - LCBU - Masonry Pregrout  Partial Pass Apparatus room cross-over at Bay B at 23’4”; Restrooms in public area at 13’8”. Ok to,grout progress areas.
02/19/2025 COT - LCBU - Masonry Pregrout  Partial Pass CMU walls at 9’4” in dormitory area, Captain’s office area, storage area. OK to grout progress areas.
02/25/2025 COT - LCBU - Masonry Pregrout  Partial Pass GL: #2 at 32’8”, public area at 18’8”, Captain’s office area at 14’. Ok to grout progress areas.
02/26/2025 COT - LCBU - Masonry Pregrout  Partial Pass Area B, Dorm area CMU walls North and South at 14’. Ok to grout progress areas.
02/27/2025 COT - LCBU - Masonry Pregrout  Partial Pass Dorms in area B, West wall at 14’; East storage area walls at 14’. Ok to grout progress areas.
02/28/2025 COT - LCBU - Masonry Pregrout  Partial Pass Dorms in Area B at 18’8”; Open courtyard South wall at 18’8”, Restrooms 105, 106, 107,108 at 18’8”. Ok to grout progress areas.
03/04/2025 COT - LCBU - Masonry Pregrout  Partial Pass 3-4-25, partial pass-pre grout for captain's office (room 218) captain's dorms (213 &215), top out at community room 108). Okay to grout 5 lift at 23' 4"
03/07/2025 COT - LCBU - Masonry Pregrout  Partial Pass 1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
1/22/25: reinforcement per plans at apparatus bay south west piers. North wall of rooms (143,142,113,111,102,) per plan at third lift ok to continue, first lift at west and south walls rooms (195,192,196,190).
2/3/25: reinforcement approved by third party inspector at East wall of rooms (102,112,115,116,117) Elevation 9'4" to 14', North Wall of rooms (116 (Lintels)) Elevation 12' to 14', West wall Column at SW Corner of room (205) Elevation 14' to 18'8".
3-4-25, partial pass-pre grout for captain's office (room 218) captain's dorms (213 &215), top out at community room 108). Okay to grout 5 lift at 23' 4"
3/7/25: canceled per Contractor
03/11/2025 COT - LCBU - Masonry Pregrout  Partial Pass Dormitory areas: CMU walls (N, S, W) at 18’9”. Police interior courtyard East walls at 9’4”. OK to grout progress areas.
03/13/2025 COT - LCBU - Masonry Pregrout  Partial Pass 3-13-25, reinforcement for Area C-police courtyard verified per plan-okay for grout at 2nd lift. Reinforcement verified for Area B-Dorms Top out on South and West wall-okay to grout at 20ft. Reinforcement verified at Area B separation (laundry room) okay to grout 1st lift at 4' 8". Kitchen South wall at 18' 8"-okay for grout 4th lift.
03/17/2025 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'.
3-13-25, reinforcement for Area C-police courtyard verified per plan-okay for grout at 2nd lift. Reinforcement for Area B-Dorms Top out on South and West wall-okay to grout at 20ft. Reinforcement for Area B separation (laundry room) okay to grout 1st lift at 4' 8". Kitchen South wall at 18' 8"-okay for grout 4th lift.
3/17/25: reinforcement per plan at east wall of rooms (227,228,244) elev 4'8"-8'8", north wall of of room 213 elev 22'-26'8", East walls of room (213,214,215,218) elev 22'-26'8", south wall of rooms (208,209) elev 14'-18'8",
03/20/2025 COT - LCBU - Masonry Pregrout  Partial Pass 1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
1/22/25: reinforcement per plans at apparatus bay south west piers. North wall of rooms (143,142,113,111,102,) per plan at third lift ok to continue, first lift at west and south walls rooms (195,192,196,190).
2/3/25: reinforcement approved by third party inspector at East wall of rooms (102,112,115,116,117) Elevation 9'4" to 14', North Wall of rooms (116 (Lintels)) Elevation 12' to 14', West wall Column at SW Corner of room (205) Elevation 14' to 18'8".
3-4-25, partial pass-pre grout for captain's office (room 218) captain's dorms (213 &215), top out at community room 108). Okay to grout 5 lift at 23' 4"
3/7/25: canceled per Contractor
3/20/25: First lift from 0’-4’8” at west wall of rooms (163,149,176,172,171,164), first lift from 0’-4’8” East walls of rooms (176,172,171), first lift from 0’-4’8” south walls in rooms (176,172,171,170), south wall of room 223 at 26’ approved, west walls of rooms ( 226,225,224,223) at 14’.
03/21/2025 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'.
3-13-25, reinforcement for Area C-police courtyard verified per plan-okay for grout at 2nd lift. Reinforcement for Area B-Dorms Top out on South and West wall-okay to grout at 20ft. Reinforcement for Area B separation (laundry room) okay to grout 1st lift at 4' 8". Kitchen South wall at 18' 8"-okay for grout 4th lift.
3/17/25: reinforcement per plan at east wall of rooms (227,228,244) elev 4'8"-8'8", north wall of of room 213 elev 22'-26'8", East walls of room (213,214,215,218) elev 22'-26'8", south wall of rooms (208,209) elev 14'-18'8",
3/21/25: reinforcement per plan at south wall of room 208 and 205 18'8"-23'4"
03/24/2025 COT - LCBU - Masonry Pregrout  Partial Pass 1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
1/22/25: reinforcement per plans at apparatus bay south west piers. North wall of rooms (143,142,113,111,102,) per plan at third lift ok to continue, first lift at west and south walls rooms (195,192,196,190).
2/3/25: reinforcement approved by third party inspector at East wall of rooms (102,112,115,116,117) Elevation 9'4" to 14', North Wall of rooms (116 (Lintels)) Elevation 12' to 14', West wall Column at SW Corner of room (205) Elevation 14' to 18'8".
3-4-25, partial pass-pre grout for captain's office (room 218) captain's dorms (213 &215), top out at community room 108). Okay to grout 5 lift at 23' 4"
3/7/25: canceled per Contractor
3/20/25: First lift from 0’-4’8” at west wall of rooms (163,149,176,172,171,164), first lift from 0’-4’8” East walls of rooms (176,172,171), first lift from 0’-4’8” south walls in rooms (176,172,171,170), south wall of room 223 at 26’ approved, west walls of rooms ( 226,225,224,223) at 14’.
3/21/25: reinforcement per plan at south wall of room 208 and 205 18'8"-23'4"
3/24/25: reinforcement per plans at east wall courtyard (police) 16'8-20', south wall courtyard (police) 16'8"-20',west wall of courtyard (police) 16'8"-20',
03/24/2025 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'
03/28/2025 COT - LCBU - Masonry Pregrout  Partial Pass
03/28/2025 COT - LCBU - Masonry Pregrout  Partial Pass 1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
1/22/25: reinforcement per plans at apparatus bay south west piers. North wall of rooms (143,142,113,111,102,) per plan at third lift ok to continue, first lift at west and south walls rooms (195,192,196,190).
2/3/25: reinforcement approved by third party inspector at East wall of rooms (102,112,115,116,117) Elevation 9'4" to 14', North Wall of rooms (116 (Lintels)) Elevation 12' to 14', West wall Column at SW Corner of room (205) Elevation 14' to 18'8".
3-4-25, partial pass-pre grout for captain's office (room 218) captain's dorms (213 &215), top out at community room 108). Okay to grout 5 lift at 23' 4"
3/7/25: canceled per Contractor
3/20/25: First lift from 0’-4’8” at west wall of rooms (163,149,176,172,171,164), first lift from 0’-4’8” East walls of rooms (176,172,171), first lift from 0’-4’8” south walls in rooms (176,172,171,170), south wall of room 223 at 26’ approved, west walls of rooms ( 226,225,224,223) at 14’.
3/21/25: reinforcement per plan at south wall of room 208 and 205 18'8"-23'4"
3/24/25: reinforcement per plans at east wall courtyard (police) 16'8-20', south wall courtyard (police) 16'8"-20',west wall of courtyard (police) 16'8"-20',
3/28/25: reinforcement per plan at Locker Rooms East Wall (Elev 4'8"-9'4"), (rooms (178,177,179,183) East wall (Elev 4'8"-9'4")).
04/01/2025 COT - LCBU - Masonry Pregrout  Partial Pass 4-1-25, reinforcement per plans on east wall of community room at 23' 4"-okay to grout.
04/07/2025 COT - LCBU - Masonry Pregrout  Partial Pass Lintel at corridor 201 at 23’ 4”. Ok to grout progress areas. Armory areas; 170 - 175, corridor 176 topped out. Ok to grout progress areas.
04/18/2025 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'.
4/18/25: reinforcement per plan at Corridor 201 east wall, north east locker room top out, 2nd lift at rooms (254,251,252,253,255) approved.
05/07/2025 COT - LCBU - Masonry Pregrout  Not Ready 5-7-25, not ready-will reschedule.
05/09/2025 COT - LCBU - Masonry Pregrout  Partial Pass 5-9-25, reinforcement on interior walls -Section D, rooms 177-184 verified per plans. Okay to grout 2nd lift at 9' 4".
06/02/2025 COT - LCBU - Masonry Pregrout  Partial Pass 1/8/25: reinforcement per plan at apparatus bay east wall and piers from 14'-18', apparatus bay west wall and piers top out per plan ok to proceed with grout. Reinforcement per plan at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 4'8"-8'. Ok to proceed with grout at progress areas.
1/22/25: reinforcement per plans at apparatus bay south west piers. North wall of rooms (143,142,113,111,102,) per plan at third lift ok to continue, first lift at west and south walls rooms (195,192,196,190).
2/3/25: reinforcement approved by third party inspector at East wall of rooms (102,112,115,116,117) Elevation 9'4" to 14', North Wall of rooms (116 (Lintels)) Elevation 12' to 14', West wall Column at SW Corner of room (205) Elevation 14' to 18'8".
3-4-25, partial pass-pre grout for captain's office (room 218) captain's dorms (213 &215), top out at community room 108). Okay to grout 5 lift at 23' 4"
3/7/25: canceled per Contractor
3/20/25: First lift from 0’-4’8” at west wall of rooms (163,149,176,172,171,164), first lift from 0’-4’8” East walls of rooms (176,172,171), first lift from 0’-4’8” south walls in rooms (176,172,171,170), south wall of room 223 at 26’ approved, west walls of rooms ( 226,225,224,223) at 14’.
3/21/25: reinforcement per plan at south wall of room 208 and 205 18'8"-23'4"
3/24/25: reinforcement per plans at east wall courtyard (police) 16'8-20', south wall courtyard (police) 16'8"-20',west wall of courtyard (police) 16'8"-20',
3/28/25: reinforcement per plan at Locker Rooms East Wall (Elev 4'8"-9'4"), (rooms (178,177,179,183) East wall (Elev 4'8"-9'4")).
4-1-25, reinforcement per plans on east wall of community room at 23' 4"-okay to grout.
5-9-25, reinforcement on interior walls -Section D, rooms 177-184 verified per plans. Okay to grout 2nd lift at 9' 4".
06/02/2025 COT - LCBU - Masonry Pregrout  Partial Pass 6/2/25: reinforcement per plan at Sally port west and east fully grouted CMU wall. West wall top out. East wall from 0'-4'8". Partial pass for first lift at CMU water closet chase wall from 0'-4'8" in rooms 184 and 192.
11/07/2024 COT - LCBU - Masonry Pregrout  Partial Pass Southeast corner of structure; double CMU wall at 0’ - 4’, at areas : CRU #132, room #129, room #117 (North wall). OK to grout progress areas.
11/13/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
11/25/2024 COT - LCBU - Masonry Pregrout  Partial Pass Apparatus bay #250; North and South wall at 9’4” “D” wall; North half of West wall; 4 each columns at 9’4” at bay openings. Stand alone wall (screen wall) at 9’4” in Area B. OK to place grout in progress areas.
12/03/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/04/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/06/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/09/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/11/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/16/2024 COT - LCBU - Masonry Pregrout  Partial Pass CMU walls; North wall at 26’8” along rooms 207 and 21 (low side wall at 12’), South wall at 26’8”. Z Wall at 18’8”, free standing wall at 28’. OK to grout progress areas.
12/23/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/2024 COT - LCBU - Masonry Pregrout  Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
12/3/24: first lift at Southwest corner of apparatus Bay MC2 and MC1 per plans at 5'4". Ok to grout progress area. Freestanding 24" masonry wall third lift approved ok to proceed with grout.
12/9/24: reinforcement per plan 5th lift at south end of apparatus bay from 18'8"- 23'4"
12/11/24: reinforcement per plan at 5th lift north end of apparatus bay from 18'8-23'4", reinforcement per plan at free standing masonry wall from 18'8"-23'4".
12/12/24: reinforcement per plan at south west corner of room 250 elev 14'8"-18'8"
12/23/24: top out at free standing masonry wall passed. Double wall at south east corner first lift passed ok to proceed with grout.
12/31/24: reinforcement at south walls in the public lobby, mdf, tactics, exam/atpt off, fitness ok to grout first lift from 0"-4'8", apparatus bay east wall and piers from 9'4"-14'