Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCPL - Plumbing Above Ceiling
Permit Number - TC-COM-0423-00942
Inspection Description - COT - LCPL - Plumbing Above Ceiling
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/02/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 7/1/25: Overhead plumbing Area A and Connecting to Area B | |
| 07/11/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 7/11/25: above ceiling (Framing, mechanical, plumbing, electrical) approved in rooms 237,238,239,240,209 | |
| 07/18/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 7-18-25: plumbing supports approved for room 209. Okay to continue with construction at progress areas. | |
| 08/13/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 8-13-25: above ceiling mechanical & electrical, plumbing at hard lids and soffits in Area's C & D, corridor 135, 168, 170, 167. Verified flex, supports, electrical conduits, fire alarm conduits , and lighting. Okay to continue with construction at progress areas. | |
| 08/21/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 8-21-25: above ceiling plumbing at room's 105, 107, and locker room approved. Okay to continue with construction at progress areas. | |
| 09/03/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 9-3-25: verified framing, in wall domestic & MEP's above ceiling at Area D men's/woman's locker rooms. Okay to continue with construction at progress areas. | |
| 09/09/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 9-9-25: electrical/mechanical/ and plumbing above ceiling throughout Corridor 136 verified per approved plans. Okay to continue construction at progress areas. | |
| 09/10/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | Areas C and D all joints above ceilings; Ok to insulate joint areas. | |
| 09/22/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 9-22-25: firewall caulking, framing, plumbing, mechanical, electrical above ceiling, electrical intermediates verified per plans at room's 193, 177, 194, 181, 182, 183, 184, 185. 186, 187, 188, 189, 190, 191. Okay to continue with construction at progress areas. | |
| 09/24/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 9/24/25: Building above ceiling approved in Fitness room 141 | |
| 10/08/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 10/8/25: Corridor 149,corridor 146,161, corridor 135 corridor 128,corridor 166,corridor 176,171,164,132,133,134,165,129,130, 131,124, 123,145,119,120,121,125,126,127,158,159,160,162,112,143, |
|
| 10/17/2025 | COT - LCPL - Plumbing Above Ceiling | Partial Pass | 10-17-25: all MEP's building above ceiling and in wall for rooms 254,255 and lockers 152&153 173,173,174,175,178,179, and 194 verified per plans. Okay to continue construction at progress areas. |