Parcel: 13216600A


Addresses:

4410 S PARK AV


Inspection Status: Partial Pass

Inspection History: COT - LCBU - Framing

Permit Number - TC-COM-0423-00942

Inspection Description - COT - LCBU - Framing

Inspection Status - Partial Pass

Date Description Inspector Results Comments
05/06/2025 COT - LCBU - Framing Partial Pass 5-6-25, framing for exterior walls at dorm rooms verified per plan. Okay to spray foam progress areas.
05/06/2025 COT - LCBU - Framing Partial Pass 5-6-25, exterior parapet framing at Apparatus Bay verified per RFI. West side of bay is approximately 90% complete. The East side at approximately 60%-okay to continue with construction at progress areas.
05/08/2025 COT - LCBU - Framing Partial Pass 5-8-25, framing on apparatus parapets on east and west side verified per plans-Okay to continue with construction at progress areas. Interior framing for dorm rooms and corridors verified. Also, Interior wall framing on Rooms 201-226 (dayroom & kitchen area) also verified per plans -okay to continue with construction at progress areas.
05/12/2025 COT - LCBU - Framing Partial Pass 5-12-25, Inspected wall framing on south wall of MDF room #114. Submit an engineer RFI fix for wall framing/ cmu wall box cut out. Not allowed to cut header on metal framing. Sheathing/nailing on each side of apparatus parapet located on west side verified per plans. Okay to continue construction at progress areas.
05/13/2025 COT - LCBU - Framing Partial Pass 5-13-25, metal framing for MDF-Room #114 approved (disregard RFI). Metal framing along the Eastside Apparatus parapet inspected and approved. Okay to continue with construction at progress areas.
05/16/2025 COT - LCBU - Framing Partial Pass 5-16-25, metal framing at public entrance parapet verified per plans. Okay to continue with installation of plywood over progress areas.
05/29/2025 COT - LCBU - Framing Partial Pass South and Southeast parapet wall framing of Processing area. Ok to cover progress areas.
06/09/2025 COT - LCBU - Framing Partial Pass 6/9/2025 Community room 108, 109, 110 exterior framing walls per plan. Okay to proceed progress areas.
06/11/2025 COT - LCBU - Framing Partial Pass Exterior walls Area C and D Areas to receive spray foam insulation approved. Okay to proceed progress areas. 6/11/2025
07/01/2025 COT - LCBU - Framing Partial Pass 7/1/25: framing per plan at Area C rooms 102,111,112,113,115,116,117,118,119,120,121,122,123,124,125,126,127,128,129,130,131,131,133, 134,165,168,169, 164,170.
07/10/2025 COT - LCBU - Framing Partial Pass Inspection performed on 9 July.
07/11/2025 COT - LCBU - Framing Partial Pass 7/11/25: above ceiling (Framing, mechanical, plumbing, electrical) approved in rooms 237,238,239,240,209
07/18/2025 COT - LCBU - Framing Partial Pass 7-18-25: above ceiling framing in room 209 approved. Okay to continue with construction at progress areas.
07/21/2025 COT - LCBU - Framing Partial Pass 7-21-25: Area A framing at soffits and hard lids located at dayroom and kitchen area approved-okay to continue with construction at progress areas. Exterior drywall nailing at Area C-room's 164, 165, 132, 129, 118.116, 115, 102 also inspected and approved. Okay to tape & texture.
07/23/2025 COT - LCBU - Framing Partial Pass Areas C & D office areas and common rooms. Except for rooms 148, 162, 163.
07/30/2025 COT - LCBU - Framing Partial Pass 7-30-25: metal framing at soffit on east side apparatus bay verified per plans. Okay to continue with construction at progress areas.
08/01/2025 COT - LCBU - Framing Partial Pass 8-1-25: electrical progress & framing for room's 147,148, 162, 163, 147, 148, Corridor 166, 161 verified per plans. Okay to continue with construction at progress areas.
08/07/2025 COT - LCBU - Framing Partial Pass 8-7-25: insulation at room's 148,147,163,162,161. Corridor 166 drywall nailing, 167(minus restrooms), 160, 158, 159, corridor 146, 143, 142, 144, 145 verified per plans-okay to continue with construction at progress areas.
Framing Area C &D-Soffits at southeast corner, room 164, 128, 166, 167, 168, 170, 117, 123, 147, corridor 135-okay to continue with construction at progress areas.
Electrical-Southeast parapet & apparatus bay lights verified per plans-okay to continue with construction at progress areas.
08/13/2025 COT - LCBU - Framing Partial Pass 8-13-25: framing inspection at hard lids and soffits in Area's C & D, corridor 135, 168, 170, 167, verified per plans. In wall framing Area D-men's/woman's locker rooms. Okay to continue with construction at progress areas.
08/20/2025 COT - LCBU - Framing Partial Pass 8-20-25: drywall nailing Area C-Corridor 136-okay to fire tape. Fur out framing for lockers & roof drains at room 175 & framing at room's 173, 174, 193,194, 187 room 147 & 148 (framing/electrical for soffits & above ceiling lights). Okay to continue with construction at progress areas.
08/21/2025 COT - LCBU - Framing Partial Pass 8-21-25: Grid framing/framing approved at room's 105 & 107
08/28/2025 COT - LCBU - Framing Partial Pass Fitness room soffits, Ok to set mechanical and lighting
09/22/2025 COT - LCBU - Framing Partial Pass 9-22-25: Area D-firewall caulking, framing, plumbing, mechanical, electrical above ceiling, electrical intermediates verified per plans at room's 193, 177, 194, 181, 182, 183, 184, 185. 186, 187, 188, 189, 190, 191. Okay to continue with construction at progress areas.
09/24/2025 COT - LCBU - Framing Partial Pass 9/24/25: Building above ceiling approved in Fitness room 141
10/17/2025 COT - LCBU - Framing Partial Pass 10-17-25: framing for rooms 254,255 and lockers 152&153 173,173,174,175,178,179, and 194 verified per plans. Okay to continue construction at progress areas.