Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel: 13216600A


Addresses:

4410 S PARK AV


Inspection Status: Partial Pass

Inspection History: COT - LCBU - Building Progress

Permit Number - TC-COM-0423-00942

Inspection Description - COT - LCBU - Building Progress

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/16/2025 COT - LCBU - Building Progress Partial Pass Information only for<future pre-slab inspection,scheduling,
02/20/2025 COT - LCBU - Building Progress Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).
2/20/25: Plumbing Sewer underground @ SW corner of Apparatus Bay passed
06/03/2025 COT - LCBU - Building Progress Partial Pass Spray foam Insulation at all exterior walls area A. 201-223. 6/3/2025
06/20/2025 COT - LCBU - Building Progress Partial Pass Spray insulation on exterior walls at Room 108, 109.
06/24/2025 COT - LCBU - Building Progress Partial Pass 6/23/25: Area B dorm room restrooms 236-240, Area A north,
164-102 exterior rooms,Insulation Area A Dayroom Kitchen Area, And spray foam insulation exterior walls Area C
06/25/2025 COT - LCBU - Building Progress Partial Pass 6/25/25: drywall nailing approved in rooms 114,244,245,246,247,248,249,229,230,231,232,233,234,235,242, corridor 243, corridor 228, corridor 241, 226.
COT - LCBU - Building Progress Partial Pass 7/1/25: drywall nailing approved in rooms 204,205,206,210,212,213,214,215,216,217,208,207,201,203
07/10/2025 COT - LCBU - Building Progress Partial Pass New soffits for fitness area, apparatus area, lighting for dormitory areas.
07/15/2025 COT - LCBU - Building Progress Partial Pass 7-15-25: insulation inspection Area C, east of corridor 135 approved-okay to continue with construction at progress areas. Drywall nailing inspection for community room #108 verified per plans-okay for tape & texture.
07/17/2025 COT - LCBU - Building Progress Partial Pass 7-17-25: drywall/durock nailing on room's 237-240 verified per plans. Okay for tape & texture.
COT - LCBU - Building Progress Partial Pass 7-21-25: Area A framing at soffits and hard lids located at dayroom and kitchen area approved-okay to continue with construction at progress areas. Exterior drywall nailing at Area C-room's 164, 165, 132, 129, 118.116, 115, 102 also inspected and approved. Okay to tape & texture.
07/24/2025 COT - LCBU - Building Progress Partial Pass 7-24-25: drywall nailing inspection for Area on Hard lids for room's 209, 211, dayroom & kitchen. Area C-East of corridor interior walls minus room 129-due to door frame possibly moving to north wall. Okay to tape & texture progress areas.
07/25/2025 COT - LCBU - Building Progress Partial Pass 7/25/25: drywall nailing inspection for Area D locker rooms exterior wall. Ok to proceed
COT - LCBU - Building Progress Re-inspection required 7-30-25: insulation not ready-reschedule inspection at your convenience.
07/31/2025 COT - LCBU - Building Progress Partial Pass 7-31-25: verified insulation for Area C, room's 114, 143, 145, 158, 159, 160, corridor 166, 168, 170-okay to continue with construction at progress areas.
08/07/2025 COT - LCBU - Building Progress Partial Pass 8-7-25: insulation at room's 148,147,163,162,161. Corridor 166 drywall nailing, 167(minus restrooms), 160, 158, 159, corridor 146, 143, 142, 144, 145 verified per plans-okay to continue with construction at progress areas.
Framing Area C &D-Soffits at southeast corner, room 164, 128, 166, 167, 168, 170, 117, 123, 147, corridor 135-okay to continue with construction at progress areas.
Electrical-Southeast parapet & apparatus bay lights verified per plans-okay to continue with construction at progress areas.
08/13/2025 COT - LCBU - Building Progress Partial Pass 8-13-25: insulation in 105, 107, 137, 138, 139, 140 and tactic room area. Okay to continue with construction at progress areas.
08/21/2025 COT - LCBU - Building Progress Partial Pass 8-21-25: in wall insulation at room's 105, 107, and locker room approved. Okay to continue with construction at progress areas.
08/25/2025 COT - LCBU - Building Progress Partial Pass Sheet rock nailing in rooms 107 - 107, restrooms 168, 170 - 172, corridor 198. OK to tape progress areas.
08/27/2025 COT - LCBU - Building Progress Partial Pass Area D; locker rooms and break area: insulation and sheet rock nailing. Ok to tape progress areas.
08/28/2025 COT - LCBU - Building Progress Partial Pass Sheet rock nailing in fitness room and corridors #136, 176. Ok to tape progress areas.
09/10/2025 COT - LCBU - Building Progress Partial Pass Hard lid ceilings in shower areas. Moisture resistant sheet rock applied in subject ceiling areas.
09/11/2025 COT - LCBU - Building Progress Partial Pass 9-11-25: drywall nailing for corridor 136 approved. Okay for tape & texture.
09/24/2025 COT - LCBU - Building Progress Partial Pass 9/24/25: Drywall nailing on ceilings approved at processing area rooms 177,180,181,182,183,184,185,186,188,189,190,191,192
09/29/2025 COT - LCBU - Building Progress Partial Pass 9/29/25: Drywall nailing on ceilings approved at fitness room 141.
10/22/2025 COT - LCBU - Building Progress Partial Pass 10-22-25: drywall nailing at room 254& 255 approved. Okay to tape & texture progress areas.
11/20/2024 COT - LCBU - Building Progress Partial Pass 11/14/24: reinforcement per plan at Columns first lift @4'8" at East and West side of room 250, reinforcement per plan at open courtyard stem wall ok to proceed
11/15/24: reinforcement per plan at Apparatus bay at south wall @4'8".
11/20/24: reinforcement per plan at first lift at Freestanding 24" masonry wall, reinforcement per plan at second lift at south west wall of apparatus bay, first lift at south wall @ 5'4" at south walls of (rooms 251, 252, 253).