Permit: TC-COM-0925-01634
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
10015 E OLD VAIL RD
Address NEW:
10015 E OLD VAIL RD
Apply Date:
09/05/2025
Applicant:
Adela Buster
Description:
Rev 1 - Update to electrical started 07.07.2026 New Build to Suite of a Sprouts Farmers Market.
Permit Reviews
Permit Number - TC-COM-0925-01634
Permit Status: Issued
Permit Description: Rev 1 - Update to electrical started 07.07.2026
New Build to Suite of a Sprouts Farmers Market.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/24/2025 | COMMERCIAL REVIEW - FULL v.4 | 11/25/2025 | REQUIRES RESUBMIT |
| 03/17/2026 | SPECIAL INSPECTION REVIEW v.1 | 03/18/2026 | REQUIRES RESUBMIT |
| 12/01/2025 | COMMERCIAL REVIEW - FULL v.5 | 12/08/2025 | APPROVED |
| 12/22/2025 | ADMINISTRATIVE v.2 | 12/22/2025 | REQUIRES RESUBMIT |
| 03/24/2026 | SPECIAL INSPECTION REVIEW v.2 | 03/25/2026 | APPROVED |
| 01/13/2026 | ADMINISTRATIVE v.4 | 01/13/2026 | APPROVED |
| 07/07/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | 07/14/2026 | APPROVED |
| 09/25/2026 | SPECIAL INSPECTION REVIEW v.1 | 09/29/2026 | APPROVED |
| 09/05/2025 | COMMERCIAL REVIEW - FULL v.1 | 10/08/2025 | REQUIRES RESUBMIT |
| 07/29/2026 | COMMERCIAL REVIEW - FULL REVISION v.1 | 08/05/2026 | APPROVED |
| 09/24/2026 | SPECIAL INSPECTION REVIEW v.2 | 09/24/2026 | APPROVED |
| 12/09/2025 | ADMINISTRATIVE v.1 | 12/09/2025 | REQUIRES RESUBMIT |
| 08/05/2026 | RESTAMP - COMMERCIAL v.1 | N/A | APPROVED |
| 01/07/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/13/2026 | APPROVED |
| 10/21/2025 | COMMERCIAL REVIEW - FULL v.2 | 11/06/2025 | REQUIRES RESUBMIT |
| 12/16/2025 | RESTAMP - COMMERCIAL v.1 | 12/22/2025 | APPROVED |
| 08/31/2026 | SPECIAL INSPECTION REVIEW v.1 | 08/31/2026 | REQUIRES RESUBMIT |
| 11/14/2025 | COMMERCIAL REVIEW - FULL v.3 | 11/14/2025 | REQUIRES RESUBMIT |
| 01/07/2026 | ADMINISTRATIVE v.3 | 01/07/2026 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - TC-COM-0925-01634
Permit Status: Issued
Permit Description: Rev 1 - Update to electrical started 07.07.2026
New Build to Suite of a Sprouts Farmers Market.
Total Outstanding Activity Conditions - 9
| Date | Name |
|---|---|
| 12/02/2025 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 12/02/2025 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
| 12/02/2025 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 12/02/2025 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 12/02/2025 | Masonry Inspection Report submittal review is required. |
| 12/02/2025 | Post-Installed Anchor Inspection Report is required. |
| 12/02/2025 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
| 12/05/2025 | Masonry Inspection Report submittal review is required. |
| 12/17/2025 | AIR BALANCING REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-0925-01634
Permit Status: Issued
Permit Description: Rev 1 - Update to electrical started 07.07.2026
New Build to Suite of a Sprouts Farmers Market.
| Date | Description | Comments |
|---|---|---|
| 12/09/2025 | Approved Set of Construction Plans was corrupted during download from Studio Session. Address must be assigned to the Permit Application and Plans prior to issuance. Please submit approved plans without City stamps including address. Along with a comment review letter, stating that this is a re-stamp to resolve the addressing issue. | |
| 12/02/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 12/05/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
| 09/05/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 12/02/2025 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 09/05/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 09/05/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 12/05/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. | |
| 12/05/2025 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 12/17/2025 | WATER STERILIZATION REPORT IS REQUIRED. | |
| 12/02/2025 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. | |
| 12/05/2025 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0925-01634
Permite Description: Rev 1 - Update to electrical started 07.07.2026
New Build to Suite of a Sprouts Farmers Market.
Total Outstanding Inspections - 14
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2026 | COT - HCBU - Preslab | N/A | Partial Pass | 2/20/26: EXCAVATION/REBAR PER APPROVED PLANS AT EXTERIOR CMU wall footing GL 1-4/ A-D |
| 09/14/2026 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 9/14/2026 kitchen hood. clean outs have been added. smoke test approved. Second layer in place. |
| 07/31/2026 | BULD - Electrical Clearance | N/A | Partial Pass | 7-31-26: partial pass pending address RFI approval by the city- okay to energize SES at 10015 E. Old Vail Rd. ECO clearance issued to TEP. |
| 06/05/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Not Ready | 6-5-26: scheduled for 6-8-26. |
| 07/08/2026 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 7/8/26: one-side drywall screw inspection at GL E-F/1-2 okay to tape and texture |
| 06/05/2026 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | 6-5-26: sheathing screw inspection at canal-yard decking, at Sprouts metal framing pop out at south side of building together with sheathing at rooftop tower approved. Okay to continue with construction at progress areas. |
| 03/19/2026 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 3/19/26: 3rd lift approved at east and west walls, 2nd lift approved at north and south walls |
| 07/08/2026 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 7/8/26: entry Canopies framing approved, roof nailing approved For both canopies, electrical above ceiling approved at both canopies. |
| 03/19/2026 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | 3/19/26: rough-soil for produce prep room. Ok to backfill. Shading required |
| 09/29/2026 | COT - FCON - Fire - Final | N/A | Partial Pass | ok for tco levev 4 still need the hood to pass before any cooking. |
| COT - FCON - Hood System - Final | N/A | Not Ready | ||
| 09/29/2026 | ENGR Engineering Final | N/A | Partial Pass | Site and DP are almost complete. Okay to apply for TCO level 2. Outstanding conditions need to be satisfied. |
| 09/29/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 9/29/2026 partial pass. Okay to poly for level 2 TCO. |
| 09/29/2026 | COT - HCBU - TCO | N/A | Partial Pass | 9/29/2026 partial pass. Okay to poly for level 2 TCO. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0925-01634
Permit Description: Rev 1 - Update to electrical started 07.07.2026
New Build to Suite of a Sprouts Farmers Market.
Total Completed Inspections - 30
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/07/2026 | COT - HCBU - Preslab | Passed | 5-7-26: reinforcement @ preslab for slab recess freezer verified per S300/Detail 6-okay to pour footings & over mesh. Schedule inspection to verify #3's @18" o.c. Prior to pouring 4" pad. Reinforcement/Preslab for dock leveler verified per S300 Detail's 9, 13, 14 & Dry pack for steel posts at G/L-A/3.3-3.5 & 2.8-2.7 all approved. Okay for concrete placement at progress areas. | |
| 07/31/2026 | COT - HCPL - Gas Pressure Test | Passed | 7-31-26: gas pressure test approved-verified system at 15 PSI. | |
| 09/18/2026 | COT - HCPL - Plumbing Intermediate | Passed | 9/18/26: plumbing intermediates approved. | |
| 09/21/2026 | COT - HCME - Mechanical Intermediate | Passed | 9/21/26: mechanical & electrical intermediates approved. | |
| 09/21/2026 | COT - HCEL - Electrical Intermediate | Passed | 9/21/26: mechanical & electrical intermediates approved. | |
| 09/22/2026 | COT - BULD - SWG Clearance | Passed | ||
| 09/22/2026 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
| 09/22/2026 | TRSP - ROW - Notice of Completion | Passed | shell building on private property has completed development package connection to right of way, approved | |
| 09/22/2026 | COT - FCON - Sprinkler - Final | Passed | ||
| 09/22/2026 | COT - HCBU - Building Above Ceiling | Passed | ||
| 09/22/2026 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 09/22/2026 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
| 09/22/2026 | COT - HCBU - Framing | Passed | ||
| 09/22/2026 | COT - HCBU - Masonry Pregrout | Passed | ||
| 09/22/2026 | COT - HCBU - Roof Nailing | Passed | ||
| 09/22/2026 | COT - HCEL - Electrical Above Ceiling | Passed | ||
| 09/22/2026 | COT - HCEL - Electrical Progress | Passed | ||
| 09/22/2026 | COT - HCEL - Electrical Underground | Passed | ||
| 09/22/2026 | COT - HCME - Mechanical Above Ceiling | Passed | ||
| 09/22/2026 | COT - HCME - Mechanical Progress | Passed | ||
| 09/22/2026 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
| 09/22/2026 | COT - HCPL - Plumbing Progress | Passed | ||
| 09/22/2026 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 09/22/2026 | COT - HCPL - Rough Soil | Passed | ||
| 09/22/2026 | COT - HCPL - Sewer | Passed | ||
| 09/28/2026 | COT - HCEL - Electrical Final | Passed | ||
| 09/28/2026 | COT - HCME - Mechanical Final | Passed | ||
| 09/28/2026 | COT - HCPL - Plumbing Final | Passed | ||
| 09/28/2026 | COT - HCEL - Outdoor Lighting | Passed | ||
| 09/29/2026 | COT - FCON - Alarm - Final | Passed |