Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: TC-COM-0925-01634

Parcel: 14118602A


Addresses:

10015 E OLD VAIL RD

Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Progress 

Date Description Inspector Results Comments
COT - HCPL - Plumbing Progress  Partial Pass 2/19/26L Partial pass for 4" sewer line and 4" gray water line at GL F.5/4-3.5. Ok to backfill progress area. Sleeve in place and plumbing under pressure.
03/06/2026 COT - HCPL - Plumbing Progress  Partial Pass 3-6-26: verified trench depth & tracer wire on a 1 1/2" domestic water line from northeast section of site that runs approximately 400' east. Okay to backfill progress areas using shading materials.
03/12/2026 COT - HCPL - Plumbing Progress  Canceled 3-12-26: canceled-not ready.
03/19/2026 COT - HCPL - Plumbing Progress  Partial Pass 3/19/26: rough-soil for produce prep room. Ok to backfill. Shading required
03/25/2026 COT - HCPL - Plumbing Progress  Partial Pass 3-25-26: underground plumbing on entire interior building verified under test & per plans. Okay to backfill progress areas using shading materials.
04/22/2026 COT - HCPL - Plumbing Progress  Partial Pass 4-22-26: grease interceptor verified under test and per civil plans- P.400 Detail 5. Okay to backfill progress areas using shading materials.
05/14/2026 COT - HCPL - Plumbing Progress  Partial Pass 5-14-26: main water line stub up at north west side of building verified under test at 3.5psi.
06/04/2026 COT - HCPL - Plumbing Progress  Partial Pass 6/4/26: plumbing intermediate for PVC (DWV) and Copper (Domestic) at produce prep Area located behind coolers and freezers approved. Hangers and supports above ceiling will be looked at during above ceiling inspection.
06/24/2026 COT - HCPL - Plumbing Progress  Partial Pass 6-24-26: partial pass for domestic copper lines. Lines verified under test at 100 psi. In wall DWV at back of house from G/L: 2.1-4/F-D verified under test. Okay to continue with construction at progress areas.
07/22/2026 COT - HCPL - Plumbing Progress  Partial Pass Partial pass. Main line under test. Pending remaining gas lines to all equipments. Ensure gas is bonded. 7/22/2026