Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
|
COT - HCPL - Plumbing Progress |
|
Partial Pass |
2/19/26L Partial pass for 4" sewer line and 4" gray water line at GL F.5/4-3.5. Ok to backfill progress area. Sleeve in place and plumbing under pressure. |
| 03/06/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
3-6-26: verified trench depth & tracer wire on a 1 1/2" domestic water line from northeast section of site that runs approximately 400' east. Okay to backfill progress areas using shading materials. |
| 03/12/2026 |
COT - HCPL - Plumbing Progress |
|
Canceled |
3-12-26: canceled-not ready. |
| 03/19/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
3/19/26: rough-soil for produce prep room. Ok to backfill. Shading required |
| 03/25/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
3-25-26: underground plumbing on entire interior building verified under test & per plans. Okay to backfill progress areas using shading materials. |
| 04/22/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
4-22-26: grease interceptor verified under test and per civil plans- P.400 Detail 5. Okay to backfill progress areas using shading materials. |
| 05/14/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
5-14-26: main water line stub up at north west side of building verified under test at 3.5psi. |
| 06/04/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
6/4/26: plumbing intermediate for PVC (DWV) and Copper (Domestic) at produce prep Area located behind coolers and freezers approved. Hangers and supports above ceiling will be looked at during above ceiling inspection. |
| 06/24/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
6-24-26: partial pass for domestic copper lines. Lines verified under test at 100 psi. In wall DWV at back of house from G/L: 2.1-4/F-D verified under test. Okay to continue with construction at progress areas. |
| 07/22/2026 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Partial pass. Main line under test. Pending remaining gas lines to all equipments. Ensure gas is bonded. 7/22/2026 |