Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 02/20/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
2/20/26: EXCAVATION/REBAR PER APPROVED PLANS AT EXTERIOR CMU wall footing GL 1-4/ A-D |
| 02/24/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
2-24-26: excavation/reinforcement verified per plans at exterior CMU wall footings @ GL 1-4/F-D. Okay for concrete placement at progress areas. |
| 02/26/2026 |
COT - HCBU - Preslab |
|
Partial Pass |
2/26/26 partial pass for shade pillars and main support steel footings |
| 05/06/2026 |
COT - HCBU - Preslab |
|
Not Ready |
5-6-26: not ready. |
| 05/07/2026 |
COT - HCBU - Preslab |
|
Passed |
5-7-26: reinforcement @ preslab for slab recess freezer verified per S300/Detail 6-okay to pour footings & over mesh. Schedule inspection to verify #3's @18" o.c. Prior to pouring 4" pad. Reinforcement/Preslab for dock leveler verified per S300 Detail's 9, 13, 14 & Dry pack for steel posts at G/L-A/3.3-3.5 & 2.8-2.7 all approved. Okay for concrete placement at progress areas. |