Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2026 | COT - HCBU - Framing | Not Ready | Framing for pop out not ready. 5/18/2026 | |
| 05/21/2026 | COT - HCBU - Framing | Partial Pass | Partial pass roof pop out | |
| 05/28/2026 | COT - HCBU - Framing | Partial Pass | 5-28-26: metal framing at Sprouts pop out located at south side of building approved. Okay to continue with construction at progress areas. | |
| 06/26/2026 | COT - HCBU - Framing | Re-inspection required | 6-26-26: see S003/Detail 11 and add 1/2 anchors at 48" o.c. Or Hilti-XU at 12"o.c. Fastener shall have an I.C.B.O report for same, install 2 tek screws at each side of stud, see detail 7 -S004, steel joist reinforcement, bracing at 4', and all other details related to metal framing. | |
| 06/30/2026 | COT - HCBU - Framing | Partial Pass | 6-30-26: submit slip track RFI together with RFI for screws at stud wall connection to floor-See A220/Detail 2. Plans call for 2 #8 screws per stud. Verified Hilti X-U pins at 12" o.c. and bracing at G/L: 3.5/ B-D. | |
| 07/07/2026 | COT - HCBU - Framing | Partial Pass | 7.7.26 Vestibule, mothers rm and break room, bookkeeping, cashier,hallway, scan room. |
|
| 07/13/2026 | COT - HCBU - Framing | Partial Pass | Partial pass hat channel at front of store | |
| COT - HCBU - Framing | Partial Pass | 7-29-26: Framing at hard lid areas at front offices approved. Add screws to east wall metal framing at "mother's room". Okay to continue with construction at front offices. |