Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 04/01/2026 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
4-1-26: verified several secondary schedule 40 electrical conduits consisting of 2 1/2", 2", 1"for panel c feeder & panel r1. Okay to backfill approximately 90' of trench. |
| 04/07/2026 |
COT - HCEL - Electrical Progress |
|
Re-inspection required |
4-7-26: 12" clearance is required between DWV & electrical conduits at at crossings-reschedule this portion of the inspection. Okay to backfill progress areas of electrical schedule 40 conduits ranging from 1" to 2" at r1, r2, r3, r4 and data together with Conduits stemming from panel d to 5 floor boxes, r15 & data, panel d & r2. |
| 04/27/2026 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
4-27-26: 10-schedule 40 electrical conduit stub ups for SES ranging from 3" to 2 1/2" at the northwest exterior cmu wall of building approved. Okay to continue with construction at progress areas. |
| 05/05/2026 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
5-5-26: verified #4 copper and grounding rods at 6' min together with 3 grounds for SES. Okay to continue construction at progress areas. |
| 06/08/2026 |
COT - HCEL - Electrical Progress |
|
Canceled |
6-8-26: canceled by contractor. |
| 07/08/2026 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
7/8/26: entry Canopies framing approved, roof nailing approved For both canopies, electrical above ceiling approved at both canopies. |
| 08/05/2026 |
COT - HCEL - Electrical Progress |
|
Not Ready |
8/5/2026 above ceiling inspection not ready. Ensure wires are pulled. Ground pig tails in place, boxes are labeled and ko seals are in place if knockouts occur. |