Inspection Status: Not Ready
Inspection History: COT - HCBU - Building Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 09/02/2026 |
COT - HCBU - Building Above Ceiling |
|
Not Ready |
Not ready: install ceiling grid, hvac diffusers, lights, etc. do not lay tiles in before inspection. Make sure seismic wires are installed where needed. |
| 09/16/2026 |
COT - HCBU - Building Above Ceiling |
|
Partial Pass |
9/16/26: T-Grid areas to include: Break Room=open junction box, insulate round duct. Back of House Corridor= insulate round duct above restrooms, tape tear on flex above restrooms, label all junction boxes above ceiling including low voltage, Deli= open junction boxes. At each location make sure to label Low Voltage junction boxes and you are okay to continue with installation of ceiling tiles. However, please leave several out so that I may verify corrections at the listed above locations. |
| 09/22/2026 |
COT - HCBU - Building Above Ceiling |
|
Passed |
|