Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: TC-COM-0823-02097
Permit Details
Apply Date:
08/29/2023
Applicant:
Bobby Hammond
Description:
The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Permit Reviews
Permit Number - TC-COM-0823-02097
Permit Status: Issued
Permit Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
04/19/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/23/2024 | APPROVED |
08/30/2023 | COMMERCIAL REVIEW - FULL v.1 | 10/09/2023 | REQUIRES RESUBMIT |
09/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 09/19/2024 | APPROVED |
02/15/2024 | RESTAMP - COMMERCIAL v.1 | 02/16/2024 | APPROVED |
04/10/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/15/2024 | REQUIRES RESUBMIT |
01/31/2024 | COMMERCIAL REVIEW - FULL v.2 | 02/15/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0823-02097
Permit Status: Issued
Permit Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Total Outstanding Activity Conditions - 18
Date | Name |
---|---|
04/23/2024 | AIR BALANCING REPORT IS REQUIRED. |
04/23/2024 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
04/23/2024 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
04/23/2024 | Elevator Designs must be submitted and approved prior to ... |
04/23/2024 | ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
04/23/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
04/23/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
04/23/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
04/23/2024 | Masonry Inspection Report submittal review is required. |
04/23/2024 | Post-Installed Anchor Inspection Report is required. |
04/23/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
04/23/2024 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
04/23/2024 | STATE FIRE MARSHAL INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION |
04/23/2024 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
04/23/2024 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
04/23/2024 | SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED. |
04/23/2024 | SPECIAL INSPECTION FOR WELDING IS REQUIRED. |
09/18/2024 | Dust Control/Air Quality Permit |
Conditions
Permit Number - TC-COM-0823-02097
Permit Status: Issued
Permit Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Date | Description | Comments |
---|---|---|
04/23/2024 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
04/23/2024 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
04/23/2024 | SPECIAL INSPECTION FOR SMOKE CONTROL SYSTEM IS REQUIRED. | |
04/23/2024 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Issued
Permit Number: TC-COM-0823-02097
Permite Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Total Outstanding Inspections - 8
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/20/2024 | COT - HCEL - Grounding/Bonding | N/A | Partial Pass | 6/20/24: partial for UFER at southeast corner of building. |
06/27/2024 | COT - HCPL - Sewer | N/A | Partial Pass | 6/18/24: partial for sewer from manhole on north west corner of project to 1st clean out. Ok to proceed. Air pressure test will be completed once run is complete. 6/26/24: partial for sewer from 1st clean out to future tie in at grease interceptor. 6/27/24: Air test at 5PSI for sewer pipe from manhole on northwest corner of project to future tie in at grease interceptor. Ok to backfill progress areas. Shading required |
06/28/2024 | BULD - Electrical Clearance | N/A | Partial Pass | 6/28/24: TEMP Construction POWER TMPP TEP CLEARANCE. PARTIAL PASS |
07/29/2024 | COT - HCBU - Stem Wall/Retaining Wall | N/A | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. 6/28/24: North Half of Elevator and Stairwell Core stem walls Gridline B-F/1-5 7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed. 7/29/24: second lift at elevator core wall reinforcement per plan ok to proceed. |
08/07/2024 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 7/10/24: partial electrical underground for (4) 4" conduit for low voltage from midpoint of building to northwest elevator shaft , branch circuits conduits per plan mid span of building GL I-F.2/3. Ok to backfill progress areas. 7/22/24: electrical underground at emergency elec room and main elec room on south east corner partial pass. Stub-outs, 7/23/24: ok to backfill and compact electrical underground at emergency elec room per plans, pending UFER (will leave exposed). 8/6/24: Canceled by Mike 8/7/24: (8)4" conduit from building to future transformer for secondaries. |
08/20/2024 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 7/1/24: not ready 7/15/24: Rebar Inspection for 2nd lift South Stairwell Core and 1st lift Elevator Core Walls. Reinforcement per plan ok to proceed. 7/26/24: rebar inspection for 3rd lift south Stairwell core per plans ok to proceed. 7/29/24: second lift at elevator core wall reinforcement per plan ok to proceed. 8/6/24: canceled by Mike 8/7/24: third lift at elevator core wall reinforcement per plan ok to proceed. 8/9/24: reinforcement inspection at first lift north stairwell core per plans ok to proceed. 8/14/24: Reinforcement inspection at 2nd lift at north stairwell core per plans ok to proceed, 8/20/24: reinforcement inspection at 3rd lift at north stairwell core per plans ok to proceed. |
08/27/2024 | COT - HCPL - Plumbing Roof Drains | N/A | Partial Pass | 7/24/24: plumbing underground Area A per plans ok to backfill. partial pass on underground plumbing at Area B north of elevator shaft. 8/9/24: plumbing underground Area B (grease) per plans ok to proceed. Elevator sump pump on test. Area B sanitary waste per plan and under pressure. X2 4” vents for grease interceptor on test. Okay to backfill progress areas. Shading required. 8/23/2024 8/27/24: (2) 3" for domestic water under pressure at 100psi, 8" storm drain under pressure ok to proceed |
10/17/2024 | COT - HCBU - Preslab | N/A | Partial Pass | 10/17/2024 reinforcement for 2nd floor approved. Okay for concrete placement. |
Completed Inspections
Permit Status: Issued
Permit Number: TC-COM-0823-02097
Permit Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/29/2024 | COT - HCPL - Plumbing Progress | Passed | 7/24/24: plumbing underground Area A per plans ok to backfill. partial pass on underground plumbing at Area B north of elevator shaft. 8/9/24: plumbing underground Area B (grease) per plans ok to proceed. Elevator sump pump on test. Area B sanitary waste per plan and under pressure. X2 4” vents for grease interceptor on test. Okay to backfill progress areas. Shading required. 8/23/2024 8/27/24: (2) 3" for domestic water under pressure at 100psi, 8" storm drain under pressure ok to proceed 8/29/24: tie in at sewer passed ok to proceed. |