Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
08/29/2023
Applicant:
Bobby Hammond
Description:
The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.

Permit Reviews

Permit Number - TC-COM-0823-02097
Permit Status: Issued
Permit Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Start Date Submittal Complete Date Status  
04/19/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 04/23/2024 APPROVED Review Details
08/30/2023 COMMERCIAL REVIEW - FULL v.1 10/09/2023 REQUIRES RESUBMIT Review Details
09/18/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 09/19/2024 APPROVED Review Details
02/15/2024 RESTAMP - COMMERCIAL v.1 02/16/2024 APPROVED Review Details
04/10/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/15/2024 REQUIRES RESUBMIT Review Details
01/31/2024 COMMERCIAL REVIEW - FULL v.2 02/15/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0823-02097
Permit Status: Issued
Permit Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Total Outstanding Activity Conditions - 18
Date Name
04/23/2024 AIR BALANCING REPORT IS REQUIRED.
04/23/2024 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
04/23/2024 COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
04/23/2024 Elevator Designs must be submitted and approved prior to ...
04/23/2024 ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
04/23/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/23/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
04/23/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
04/23/2024 Masonry Inspection Report submittal review is required.
04/23/2024 Post-Installed Anchor Inspection Report is required.
04/23/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
04/23/2024 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
04/23/2024 STATE FIRE MARSHAL INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION
04/23/2024 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
04/23/2024 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
04/23/2024 SPECIAL INSPECTION FOR WELD REINF STEEL IS REQUIRED.
04/23/2024 SPECIAL INSPECTION FOR WELDING IS REQUIRED.
09/18/2024 Dust Control/Air Quality Permit

Conditions

Permit Number - TC-COM-0823-02097
Permit Status: Issued
Permit Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Date Description Comments
04/23/2024 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
04/23/2024 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
04/23/2024 SPECIAL INSPECTION FOR SMOKE CONTROL SYSTEM IS REQUIRED.
04/23/2024 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Issued
Permit Number: TC-COM-0823-02097
Permite Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Total Outstanding Inspections - 8
Last Inspection Date Description Inspector Results Comments
06/20/2024 COT - HCEL - Grounding/Bonding N/A Partial Pass 6/20/24: partial for UFER at southeast corner of building.
06/27/2024 COT - HCPL - Sewer N/A Partial Pass 6/18/24: partial for sewer from manhole on north west corner of project to 1st clean out. Ok to proceed. Air pressure test will be completed once run is complete.
6/26/24: partial for sewer from 1st clean out to future tie in at grease interceptor.
6/27/24: Air test at 5PSI for sewer pipe from manhole on northwest corner of project to future tie in at grease interceptor. Ok to backfill progress areas. Shading required
06/28/2024 BULD - Electrical Clearance N/A Partial Pass 6/28/24: TEMP Construction POWER TMPP TEP CLEARANCE. PARTIAL PASS
07/29/2024 COT - HCBU - Stem Wall/Retaining Wall N/A Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
6/28/24: North Half of Elevator and Stairwell Core stem walls Gridline B-F/1-5
7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed.
7/29/24: second lift at elevator core wall reinforcement per plan ok to proceed.
08/07/2024 COT - HCEL - Electrical Underground N/A Partial Pass 7/10/24: partial electrical underground for (4) 4" conduit for low voltage from midpoint of building to northwest elevator shaft , branch circuits conduits per plan mid span of building GL I-F.2/3. Ok to backfill progress areas.
7/22/24: electrical underground at emergency elec room and main elec room on south east corner partial pass. Stub-outs,
7/23/24: ok to backfill and compact electrical underground at emergency elec room per plans, pending UFER (will leave exposed).
8/6/24: Canceled by Mike
8/7/24: (8)4" conduit from building to future transformer for secondaries.
08/20/2024 COT - HCBU - Interior Shear Bracing N/A Partial Pass 7/1/24: not ready
7/15/24: Rebar Inspection for 2nd lift South Stairwell Core and 1st lift Elevator Core Walls. Reinforcement per plan ok to proceed.
7/26/24: rebar inspection for 3rd lift south Stairwell core per plans ok to proceed.
7/29/24: second lift at elevator core wall reinforcement per plan ok to proceed.
8/6/24: canceled by Mike
8/7/24: third lift at elevator core wall reinforcement per plan ok to proceed.
8/9/24: reinforcement inspection at first lift north stairwell core per plans ok to proceed.
8/14/24: Reinforcement inspection at 2nd lift at north stairwell core per plans ok to proceed,
8/20/24: reinforcement inspection at 3rd lift at north stairwell core per plans ok to proceed.
08/27/2024 COT - HCPL - Plumbing Roof Drains N/A Partial Pass 7/24/24: plumbing underground Area A per plans ok to backfill. partial pass on underground plumbing at Area B north of elevator shaft.
8/9/24: plumbing underground Area B (grease) per plans ok to proceed.

Elevator sump pump on test. Area B sanitary waste per plan and under pressure. X2 4” vents for grease interceptor on test. Okay to backfill progress areas. Shading required. 8/23/2024
8/27/24: (2) 3" for domestic water under pressure at 100psi, 8" storm drain under pressure ok to proceed
10/17/2024 COT - HCBU - Preslab N/A Partial Pass 10/17/2024 reinforcement for 2nd floor approved. Okay for concrete placement.

Completed Inspections

Permit Status: Issued
Permit Number: TC-COM-0823-02097
Permit Description: The Project proposes a New 3-Story stand alone & independently licensed 48 bed, inpatient physical rehabilitation hospital, Level 1 is a administrative and support spaces. Level 2 & 3 are the patient floors. Each floor contains a therapy suite and 24 bed nursing units.
Total Completed Inspections - 1
Date Description Inspector Results Comments
08/29/2024 COT - HCPL - Plumbing Progress Passed 7/24/24: plumbing underground Area A per plans ok to backfill. partial pass on underground plumbing at Area B north of elevator shaft.
8/9/24: plumbing underground Area B (grease) per plans ok to proceed.

Elevator sump pump on test. Area B sanitary waste per plan and under pressure. X2 4” vents for grease interceptor on test. Okay to backfill progress areas. Shading required. 8/23/2024
8/27/24: (2) 3" for domestic water under pressure at 100psi, 8" storm drain under pressure ok to proceed
8/29/24: tie in at sewer passed ok to proceed.

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
TUCSON REHAB SPECIAL INSPECTIONS CERTIFICATE-2024-04-19_V1.PDF DOCUMENTS VIEW
WILLDAN_APPROVED_COMCHECK_V1.PDF DOCUMENTS VIEW
WILLDAN_APPROVED_IFC PROJMANVOL1OF2_V1.PDF DOCUMENTS VIEW
WILLDAN_APPROVED_IFC PROJMANVOL2OF2_V1.PDF DOCUMENTS VIEW
WILLDAN_APPROVED_PROJECT MANUAL_V1.PDF DOCUMENTS VIEW
WILLDAN_APPROVED_STRUCT CALCS_V1.PDF DOCUMENTS VIEW
CONS-2024-01-18_TUCSON_ADDENDUM 4_COMPOSITE SET_V2.PDF DOCUMENTS VIEW
CONS-2024-01-18_TUCSON_ADDENDUM 4_COMPOSITE SET_V2.PDF DOCUMENTS VIEW
CONS-2024-01-18_TUCSON_ADDENDUM 4_COMPOSITE SET_V2.PDF DOCUMENTS VIEW