Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Above Ceiling

Permit Number - TC-COM-0823-02097

Inspection Description - COT - HCPL - Plumbing Above Ceiling

Inspection Status - Partial Pass

Date Description Inspector Results Comments
03/03/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass Level #1, Area B, Domestic Waste and Vent lines at 2” - 3”.
03/05/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass 3-5-25, in wall fist floor DWV verified under test for room's that include, janitor closet, patient bariatrics restroom, office/staff bathroom, vac pump room.
03/11/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass Level 1 Area A; waste and vent lines at 2” - 4”; lines under hydro tests.
05/30/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass 3-5-25, in wall fist floor DWV verified under test for room's that include, janitor closet, patient bariatrics restroom, office/staff bathroom, vac pump room.
5/30/25: Overhead DWV 2nd floor in rooms (Rooms: 2RH057,2RH019,2TH005,2RH055,2RH062,2TH004,2TH002,2TH008,2TH009-1), & 1st floor dining waste over head, 3" sup pump discharge from room 1EG003-1DI56.
07/10/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass Level #3: domestic waste and vents at 1 1/2” - 4” on East side of Level.
07/29/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass 7-29-25: 3rd floor Area B above ceiling DWV along west end verified per plans and under test. Okay to continue with construction at progress areas.
08/07/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass 8/7/25: 3rd floor East patient rooms above ceiling in hard lid areas approved ok to proceed.
08/12/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass 8/12/25: 3rd floor west patient restrooms hard ceilings
08/19/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass 8-19-25: domestic mains on 3rd floor Area A&B verified under test.
Note: insulation, labelling of copper lines and sealing penetrations will be verified at a later inspection.
09/19/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass Above ceiling in dining room area, serving room, kitchen, and vending area.
09/29/2025 COT - HCPL - Plumbing Above Ceiling Partial Pass 9/29/2025 Gauge in room 3RH059 for non potable water.