Inspection Status: Partial Pass

Inspection History: COT - HCBU - Building Progress

Permit Number - TC-COM-0823-02097

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Partial Pass

Date Description Inspector Results Comments
04/04/2025 COT - HCBU - Building Progress Partial Pass Partial pass. South wall 1st floor elevation exterior nailing complete from finished floor to roof. (Soffit not included). 4/4/2025
04/08/2025 COT - HCBU - Building Progress Partial Pass 4-8-25, framing for soffits located northeast/south and entry on east side (minus canopy) approved. Okay to continue with construction at progress areas.
04/21/2025 COT - HCBU - Building Progress Re-inspection required 4/21/2025 nailing at exterior sheathing not per schedule. 1st floor.
04/23/2025 COT - HCBU - Building Progress Partial Pass Partial pass. South wall 1st floor elevation exterior nailing complete from finished floor to roof. (Soffit not included). 4/4/2025
4-8-25, framing for soffits located northeast/south and entry on east side (minus canopy) approved. Okay to continue with construction at progress areas.

4/21/2025 nailing at exterior sheathing not per schedule. 1st floor.
4/23/25: first floor exterior sheathing approved ok to proceed.
04/24/2025 COT - HCBU - Building Progress Partial Pass Level #2 exterior sheathing. Ok to water proof and water surface areas.
04/28/2025 COT - HCBU - Building Progress Re-inspection required 4-28-25, 3rd floor exterior sheathing- Rooms 3RH019, 3RH009, 3RH001B add screws to loose panels and check spacing at joints and along edges. 3RH045-repair section of torn wall. Okay to continue construction at progress areas but a reinspection is required on listed above rooms.
04/29/2025 COT - HCBU - Building Progress Partial Pass 4-29-25, screws for exterior sheathing on 3rd floor approved. Okay to continue with construction at progress areas.