Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Canceled
Inspection History: COT - HCEL - Electrical Above Ceiling
Permit Number - TC-COM-0823-02097
Inspection Description - COT - HCEL - Electrical Above Ceiling
Inspection Status - Canceled
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/06/2025 | COT - HCEL - Electrical Above Ceiling | Canceled | Canceled per contractor. 6/6/2025 | |
| 06/09/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | MEP at Level #2; Rooms: 2RH006, 2RH008, 2RH010, 2RH012, 2RH014, 2RH016: Electric in above rooms needs to have wore pulled and “J” Boxes covered. Level #3 Domestic water lines at 3/4” - 1 1/2” and condensation lines in rooms : 3RH004, 3RH006, 3RH008, 3RH0010, 3RH0012, 3RH0014. | |
| 07/17/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Level #2, East side patient rooms in areas A & B hard lid ceilings | |
| 08/06/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Level #3, East side of floor; room units and restrooms, mechanical, plumbing, electric and framing. Ok to cover walls in progress areas. | |
| 08/08/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 8/7/25: 3rd floor East patient rooms above ceiling in hard lid areas approved ok to proceed. | |
| 08/12/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 8/12/25: 3rd floor west patient restrooms hard ceilings | |
| 08/18/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Level #1; areas A and B, corridors and rooms; except for kitchen area and lobby area. Ensure all penetrations are properly Fire caulked and junction boxes are covered. | |
| 08/22/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 8/21/25: 3rd floor ISO patient room by north stair (above hard ceiling) | |
| 09/04/2025 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 9-4-25: 2nd floor above ceiling electrical in room's 2RH001, 2RH003, 2HR005, 2HR009, 2RH007, 2RH011, 2RH013, 2RH015, 2RH019, 2RH017, 2RH021, 2RH023, 2RH025, 2RH027, 2RH029, 2RH031. Provide supports for conduits throughout, missing nurse calls in each room, finish framing and install can lights for all rooms. | |
| 09/19/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Dining area, serving room, vending area. Level #2, Section B, East side rooms lighting above sink (10) rooms. | |
| 09/29/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 2nd floor corridor south end of smoke wall approved. Okay to proceed progress areas. 9/29/2025 | |
| 10/01/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 10-1-25: install can light at room 2RH037. Okay to continue with construction at patient rooms together with vestibule. We will inspect labelling of junction boxes, supports, etc at upcoming inspections. | |
| 10/03/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 10-3-25: room's 2EG004, Office corridor, 2RH058 Fire foam 2, penetration on south walls above ceiling, 2LB001-add covers to 2 junction boxes/label, mop sink, 2RH066, 2TH005. | |
| 10/17/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 10-17-27: 2TH001, 2TH003, 2TH005, 2TH004-label junction box, 2RH064. Okay to continue with construction at progress areas. | |
| 10/22/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 10-22-25: electrical above ceiling at 2nd floor approved, however, there several patient rooms at the 3rd floor that are missing labeling at the disconnects together with several junction boxes that are covered with tape. Remove and label everything above ceiling and reschedule. | |
| 10/24/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 10-24-25: electrical above ceiling on 3rd floor patient rooms approved. Okay to continue with construction at progress areas | |
| 10/30/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | First floor elevator area, waiting area and vestibule area. OK to set ceiling tiles in progress areas. | |
| 11/03/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Level #3. overhead electric in<center corridor from won door to South end of floor. Ok to set ceiling tiles | |
| 11/21/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 11-21-25: electrical above ceiling for room's 3TH001B, 3TH002, 3TH003, gym corridor approved. 3TH005 Not ready-reschedule. Okay to continue with construction at progress areas. |