Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Firewall/Fire Barrier/Firestop
Permit Number - TC-COM-0823-02097
Inspection Description - COT - HCBU - Firewall/Fire Barrier/Firestop
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/07/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Call in when all of 1st Floor Above Ceiling @ Priority Walls caulking is in place. 12/27/2024 2/7/25:Fire Caulk Inspection @ 1st floor for Area's (A&B) at top out. |
|
| 03/11/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Levels 1 - 3 mono coated beams and columns. Level #3 upper deck coated completely. | |
| 04/23/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Call in when all of 1st Floor Above Ceiling @ Priority Walls caulking is in place. 12/27/2024 2/7/25:Fire Caulk Inspection @ 1st floor for Area's (A&B) at top out. 3/23/25: partial pass for Edge of slab fire safing 2nd floor. Pending south corner of building. |
|
| 05/07/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | 5-7-25, fire caulking for through slab penetration on Side A-2nd floor verified. South Bay on ground level was fire caulked via 2nd floor Side B along room 2HR033. Okay to proceed with construction at progress areas. | |
| 05/16/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Re-inspection required | 5-16-25, through slab penetrations on 2nd Floor Side B, seal penetration at room 2RH036, 2RH048, 2RH046, 2RH044, 2RH042, 2RH040, 2RH038, 2RH030, 2RH038, 2RH026, 2RH024, 2RH022, | |
| 05/28/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Call in when all of 1st Floor Above Ceiling @ Priority Walls caulking is in place. 12/27/2024 2/7/25:Fire Caulk Inspection @ 1st floor for Area's (A&B) at top out. 3/23/25: partial pass for Edge of slab fire safing 2nd floor. Pending south corner of building. 5-7-25, fire caulking for through slab penetration on Side A-2nd floor verified. South Bay on ground level was fire caulked via 2nd floor Side B along room 2HR033. Okay to proceed with construction at progress areas. 5-16-25, through slab penetrations on 2nd Floor Side B, seal penetration at room 2RH036, 2RH048, 2RH046, 2RH044, 2RH042, 2RH040, 2RH038, 2RH030, 2RH038, 2RH026, 2RH024, 2RH022, 5/28/25: 3rd floor edge of slab fire protection per approved plans. |
|
| 07/24/2025 | COT - HCBU - Firewall/Fire Barrier/Firestop | Partial Pass | Call in when all of 1st Floor Above Ceiling @ Priority Walls caulking is in place. 12/27/2024 2/7/25:Fire Caulk Inspection @ 1st floor for Area's (A&B) at top out. 3/23/25: partial pass for Edge of slab fire safing 2nd floor. Pending south corner of building. 5-7-25, fire caulking for through slab penetration on Side A-2nd floor verified. South Bay on ground level was fire caulked via 2nd floor Side B along room 2HR033. Okay to proceed with construction at progress areas. 5-16-25, through slab penetrations on 2nd Floor Side B, seal penetration at room 2RH036, 2RH048, 2RH046, 2RH044, 2RH042, 2RH040, 2RH038, 2RH030, 2RH038, 2RH026, 2RH024, 2RH022, 5/28/25: 3rd floor edge of slab fire protection per approved plans. 7/24/25:2nd floor shaft walls |
|
| 12/27/2024 | COT - HCBU - Firewall/Fire Barrier/Firestop | Re-inspection required | Call in when all of 1st Floor Above Ceiling @ Priority Walls caulking is in place. 12/27/2024 |