Inspection Status: Partial Pass

Inspection History: COT - HCBU - Stem Wall/Retaining Wall 

Permit Number - TC-COM-0823-02097

Inspection Description - COT - HCBU - Stem Wall/Retaining Wall 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
06/20/2024 COT - HCBU - Stem Wall/Retaining Wall  Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
06/28/2024 COT - HCBU - Stem Wall/Retaining Wall  Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
6/28/24: North Half of Elevator and Stairwell Core stem walls Gridline B-F/1-5
07/01/2024 COT - HCBU - Stem Wall/Retaining Wall  Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
6/28/24: North Half of Elevator and Stairwell Core stem walls Gridline B-F/1-5
7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed.
07/29/2024 COT - HCBU - Stem Wall/Retaining Wall  Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
6/28/24: North Half of Elevator and Stairwell Core stem walls Gridline B-F/1-5
7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed.
7/29/24: second lift at elevator core wall reinforcement per plan ok to proceed.