Inspection Status: Partial Pass
Inspection History: COT - HCBU - Stem Wall/Retaining Wall
Permit Number - TC-COM-0823-02097
Inspection Description - COT - HCBU - Stem Wall/Retaining Wall
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/20/2024 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. |
|
06/28/2024 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. 6/28/24: North Half of Elevator and Stairwell Core stem walls Gridline B-F/1-5 |
|
07/01/2024 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. 6/28/24: North Half of Elevator and Stairwell Core stem walls Gridline B-F/1-5 7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed. |
|
07/29/2024 | COT - HCBU - Stem Wall/Retaining Wall | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. 6/28/24: North Half of Elevator and Stairwell Core stem walls Gridline B-F/1-5 7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed. 7/29/24: second lift at elevator core wall reinforcement per plan ok to proceed. |