Inspection Status: Partial Pass

Inspection History: COT - HCME - Mechanical Intermediate

Permit Number - TC-COM-0823-02097

Inspection Description - COT - HCME - Mechanical Intermediate

Inspection Status - Partial Pass

Date Description Inspector Results Comments
02/19/2025 COT - HCME - Mechanical Intermediate Partial Pass Condensation lines at 1/2” - 1” above ceilings in section “B” (1/2” - 1”).
02/21/2025 COT - HCME - Mechanical Intermediate Partial Pass 2-21-25, primary/secondary storm drains located on 1st floor northeast side together with condensate lines north of stairwell on 1st floor verified under test. Okay to continue with construction.
03/18/2025 COT - HCME - Mechanical Intermediate Partial Pass 3-18-25, 2nd Floor Area A Shaft-1st floor to second floor -okay to start enclosing.
03/24/2025 COT - HCME - Mechanical Intermediate Partial Pass 2-21-25, primary/secondary storm drains located on 1st floor northeast side together with condensate lines north of stairwell on 1st floor verified under test. Okay to continue with construction.
3-18-25, 2nd Floor Area A Shaft-1st floor to second floor -okay to start enclosing.
3/24/25: 3nd floor Area B shaft 2nd floor to third floor ok to proceed.
04/03/2025 COT - HCME - Mechanical Intermediate Partial Pass 4-3-25, 2ND FLOOR SIDE B-SUPPLY HARD DUCT BOTH SIDES OF MAIN CORRIDOR-OKAY TO START WRAPPING. 2RH027, 2RH025-NOT READY, 2RH023, 2RH021, 2RH019, VAV PER PLAN 2ND FLOOR SIDE B-2RH017, 2RH015, 2RH013, 2RH011, 2RH009, 2RH007, 2RH005, 2RH003, 2RH001, 2HR002. OKAY TO CONTINUE WITH CONSTRUCTION AT PROGRESS AREAS.
04/22/2025 COT - HCME - Mechanical Intermediate Canceled
04/24/2025 COT - HCME - Mechanical Intermediate Partial Pass Hood grease duct system; Level 1 - Level 3 (smoke tested), stainless steel duct system for dish washer, Levels 1 - 3. Ok to double wrap grease duct system from level #1 to level #3.
05/06/2025 COT - HCME - Mechanical Intermediate Partial Pass Level #3, Area B return air duct system from air handler #3. Level #2 Area B, return air duct system all insulated.
06/13/2025 COT - HCME - Mechanical Intermediate Partial Pass Level 3 Mechanical areas A & B corridor. VRH3-26 Pookie humidifier Area B tie in. Pookie MAU area B. Re inspect Exhaust fan area A. (3) Approved okay to insulate progress areas. 6/13/2025
07/10/2025 COT - HCME - Mechanical Intermediate Partial Pass Grease duct system smoke tested and wrapped at Levels 1 - 3. Discharge at roof level.
07/24/2025 COT - HCME - Mechanical Intermediate Partial Pass 2-21-25, primary/secondary storm drains located on 1st floor northeast side together with condensate lines north of stairwell on 1st floor verified under test. Okay to continue with construction.
3-18-25, 2nd Floor Area A Shaft-1st floor to second floor -okay to start enclosing.
3/24/25: 3nd floor Area B shaft 2nd floor to third floor ok to proceed.

4-3-25, 2ND FLOOR SIDE B-SUPPLY HARD DUCT BOTH SIDES OF MAIN CORRIDOR-OKAY TO START WRAPPING. 2RH027, 2RH025-NOT READY, 2RH023, 2RH021, 2RH019, VAV PER PLAN 2ND FLOOR SIDE B-2RH017, 2RH015, 2RH013, 2RH011, 2RH009, 2RH007, 2RH005, 2RH003, 2RH001, 2HR002. OKAY TO CONTINUE WITH CONSTRUCTION AT PROGRESS AREAS.

Level 3 Mechanical areas A & B corridor. VRH3-26 Pookie humidifier Area B tie in. Pookie MAU area B. Re inspect Exhaust fan area A. (3) Approved okay to insulate progress areas. 6/13/2025

7/24/25: Level 3 hard duct approved in Area A and Area B