Inspection Status: Partial Pass

Inspection History: COT - HCME - Mechanical Progress 

Permit Number - TC-COM-0823-02097

Inspection Description - COT - HCME - Mechanical Progress 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/08/2025 COT - HCME - Mechanical Progress  Partial Pass 12/16/24: return air hard duct in rooms 1AM008,1AM009,1AM010,1AM011,1AM012,1AM013,1AM014, 1AM003,1RH003,1DI018. Ok to proceed with insulation in progress areas.
1/8/25: 2nd floor 48"x20" hard duct from rooms 2RH003,2RH005,2RH007,2RH009,2RH011,2RH013,2RH015,2RH017,2RH019,2RH021,2RH023,2RH025,2RH027,2RH029, 2RH035, 2RH037,2RH039,2RH041,2RH043,2RH045,2RH047. First floor perimeter return air hard duct passed ok to insulate.
06/20/2025 COT - HCME - Mechanical Progress  Partial Pass Level #3 (East) rooms complete, Section B, Section A, rooms except,for rooms 3RH003, 009, 011, 013. Additional inspections at Level #3: Area A; DWV in rooms 3RH001 - 3RH014
06/30/2025 COT - HCME - Mechanical Progress  Partial Pass 12/16/24: return air hard duct in rooms 1AM008,1AM009,1AM010,1AM011,1AM012,1AM013,1AM014, 1AM003,1RH003,1DI018. Ok to proceed with insulation in progress areas.
1/8/25: 2nd floor 48"x20" hard duct from rooms 2RH003,2RH005,2RH007,2RH009,2RH011,2RH013,2RH015,2RH017,2RH019,2RH021,2RH023,2RH025,2RH027,2RH029, 2RH035, 2RH037,2RH039,2RH041,2RH043,2RH045,2RH047. First floor perimeter return air hard duct passed ok to insulate.
12/16/2024 COT - HCME - Mechanical Progress  Partial Pass 12/16/24: return air hard duct in rooms 1AM008,1AM009,1AM010,1AM011,1AM012,1AM013,1AM014, 1AM003,1RH003,1DI018. Ok to proceed with insulation in progress areas.