Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Roof Drains
Permit Number - TC-COM-0823-02097
Inspection Description - COT - HCPL - Plumbing Roof Drains
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/26/2025 | COT - HCPL - Plumbing Roof Drains | Partial Pass | 3” primary drain in North stairwell, air tested | |
| 04/02/2025 | COT - HCPL - Plumbing Roof Drains | Partial Pass | 4-2-25, verified per plans and under test on DOMESTIC FOR SECTION B-2RH14, DWV ROOM 2RH16, DWV2RH18, DOMESTIC WATER 2RH20, DOMESTIC2RH22, DOMESTIC-2HR24. Okay to continue with construction at progress areas. | |
| 04/04/2025 | COT - HCPL - Plumbing Roof Drains | Canceled | 4/4/2025 canceled per contractor. | |
| 07/24/2024 | COT - HCPL - Plumbing Roof Drains | Partial Pass | 7/24/24: plumbing underground Area A per plans ok to backfill. partial pass on underground plumbing at Area B north of elevator shaft. 6" PVC for plumbing roof drains underground partial pass, | |
| 08/27/2024 | COT - HCPL - Plumbing Roof Drains | Partial Pass | 7/24/24: plumbing underground Area A per plans ok to backfill. partial pass on underground plumbing at Area B north of elevator shaft. 8/9/24: plumbing underground Area B (grease) per plans ok to proceed. Elevator sump pump on test. Area B sanitary waste per plan and under pressure. X2 4” vents for grease interceptor on test. Okay to backfill progress areas. Shading required. 8/23/2024 8/27/24: (2) 3" for domestic water under pressure at 100psi, 8" storm drain under pressure ok to proceed |