Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
Permit Number - TC-COM-0823-02097
Inspection Description - COT - HCBU - Preslab
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/11/2024 | COT - HCBU - Preslab | Partial Pass | 6/11/24: footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed | |
06/12/2024 | COT - HCBU - Preslab | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. |
|
06/20/2024 | COT - HCBU - Preslab | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. |
|
06/28/2024 | COT - HCBU - Preslab | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. 6/28/24: North half of Exterior Grade Beams. Gridline B-F/1-5 |
|
07/01/2024 | COT - HCBU - Preslab | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. 6/28/24: North half of Exterior Grade Beams. Gridline B-F/1-5 7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed. |
|
09/06/2024 | COT - HCBU - Preslab | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. 6/28/24: North half of Exterior Grade Beams. Gridline B-F/1-5 7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed. 9/6/24: Reinforcement for slab on grade per plans for Area A and Area B ok to proceed. |
|
10/17/2024 | COT - HCBU - Preslab | Partial Pass | 10/17/2024 reinforcement for 2nd floor approved. Okay for concrete placement. | |
11/13/2024 | COT - HCBU - Preslab | Partial Pass | 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed 6/12/24: Spread footings for Area A complete ok to proceed. 6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed. 6/28/24: North half of Exterior Grade Beams. Gridline B-F/1-5 7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed. 9/6/24: Reinforcement for slab on grade per plans for Area A and Area B ok to proceed. 10/17/2024 reinforcement for 2nd floor approved. Okay for concrete placement. 11/13/24: reinforcement for 3rd floor deck approved ok for concrete placement |