Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Preslab  

Permit Number - TC-COM-0823-02097

Inspection Description - COT - HCBU - Preslab  

Inspection Status - Partial Pass

Date Description Inspector Results Comments
06/11/2024 COT - HCBU - Preslab   Partial Pass 6/11/24: footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
06/12/2024 COT - HCBU - Preslab   Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
06/20/2024 COT - HCBU - Preslab   Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
06/28/2024 COT - HCBU - Preslab   Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
6/28/24: North half of Exterior Grade Beams. Gridline B-F/1-5
07/01/2024 COT - HCBU - Preslab   Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
6/28/24: North half of Exterior Grade Beams. Gridline B-F/1-5
7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed.
09/06/2024 COT - HCBU - Preslab   Partial Pass 6/11/24: spread footings at Area B from GL L-H/1-5 passed ok to proceed. Stairway at Area B GL L-K/5-4 passed ok to proceed, elevator pit footing per plan ok to proceed
6/12/24: Spread footings for Area A complete ok to proceed.
6/20/24: Rebar inspection for East Side Exterior perimeter grade beam from Gridline E.2-L/5, J.1/1-5, J.1-E/1.1, stem wall at south east stairwell ok to pour, stem wall for elevator passed ok to proceed.
6/28/24: North half of Exterior Grade Beams. Gridline B-F/1-5
7/1/24: concrete wall reinforcement per plan at first level south east corner stairwell ok to proceed.
9/6/24: Reinforcement for slab on grade per plans for Area A and Area B ok to proceed.
10/17/2024 COT - HCBU - Preslab   Partial Pass 10/17/2024 reinforcement for 2nd floor approved. Okay for concrete placement.