Permit: T16CM01533
Permit Details
Apply Date:
02/29/2016
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW 4 STORY MULTI-FAMILY APARTMENT BUILDING
Contractors:
- LLOYD CONSTRUCTION COMPANY INC *** APA ***
Permit Reviews
Permit Number - T16CM01533
Permit Status: C of o
Permit Description: NEW 4 STORY MULTI-FAMILY APARTMENT BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/01/2016 | COMMERCIAL - NEW | 06/13/2016 | COMPLETED |
03/08/2022 | REVISION - - 4TH | 03/25/2022 | COMPLETED |
03/25/2022 | REVISION - - 4TH | 03/29/2022 | COMPLETED |
05/08/2020 | REVISION - - 2ND | 08/13/2020 | COMPLETED |
05/09/2017 | RESUBMITTAL | 06/28/2017 | COMPLETED |
06/13/2016 | RESUBMITTAL - TI ALL | 10/07/2016 | COMPLETED |
06/28/2017 | RESUBMITTAL | 09/07/2017 | COMPLETED |
08/10/2020 | REVISION - - 3RD | 09/11/2020 | COMPLETED |
08/27/2019 | REVISION - - 1ST | 05/08/2020 | COMPLETED |
09/07/2017 | RESUBMITTAL | 09/07/2017 | COMPLETED |
09/07/2017 | RESUBMITTAL | 08/27/2019 | COMPLETED |
09/09/2016 | PLANS OK TO SUBMIT - COMM | 09/11/2020 | COMPLETED |
09/14/2020 | REVISION - - 3RD | 02/25/2021 | COMPLETED |
09/21/2021 | REVISION - - 4TH | 10/25/2021 | COMPLETED |
10/07/2016 | RESUBMITTAL | 05/09/2017 | COMPLETED |
12/08/2021 | REVISION - - 4TH | 01/04/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T16CM01533
Permit Status: C of o
Permit Description: NEW 4 STORY MULTI-FAMILY APARTMENT BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/29/2016 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T16CM01533
Permit Description: NEW 4 STORY MULTI-FAMILY APARTMENT BUILDING
Total Completed Inspections - 55
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/29/2018 | ENGINEERING - FINAL | BBENEDON | Approved | This was a pre pre-con with Dennis from Lloyd the 471-8421 and Rodney and Cody with day Excavating. Temporary stormwater controls are in place. Swip notifications are posted. Call for inspections under your development package permit as soon as your plans and permits are approved. |
07/19/2019 | ELECTRIC - UFER | TVALENCIA | Approved | 1- Ufer ground conductor provided for the South S.E.S. only. |
09/11/2019 | ELECTRIC - UNDERGROUND | TVALENCIA | Approved | 1- Underground electric conduits are okay to cover for the Transformer pad and conduits just East of Transformer pad at grid line D. |
10/01/2019 | PLUMBING - SEWER HCS CONNECT | JCLAXTON | Approved | Building sewer tap in new main man hole part of city main. |
10/16/2019 | PLUMBING - ROUGH, SOIL | DQUINN | Approved | Storm and sanitary pvc rough , for south half of complex, ok to backfill at sw quadrant of buildings. |
11/05/2019 | ELECTRIC - TEMPORARY SERVICE | ESTEVENS | Approved | The TEP clearance code is TMPP. |
11/18/2019 | STUCCO MESH | ESTEVENS | Approved | Northside SES location. |
12/18/2019 | ELECTRIC - PROGRESS | ESTEVENS | Approved | South, East and North breezeway lighting. |
12/18/2019 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | Exhaust fans shaft #7. |
12/20/2019 | FIREWALL/FIREBARRIER/FIRESTOP | TVALENCIA | Approved | 1- The first layer of 5/8 sheet rock on beams in rooms 205 and 206 is okay for the second layer. |
12/23/2019 | ROOF NAILING | ESTEVENS | Approved | North side roof. |
02/06/2020 | ENGINEERING PRE-CONSTRUCTION | BBENEDON | Approved | Dennis with Loydd construction. Please call for stormwater follow up inspections. All inspections are on the combination permit. Stormwater piping and landscaping is within the right of way and is being inspected by transportation. |
06/17/2020 | U VALUE FOR WINDOW | TVALENCIA | Approved | |
08/19/2020 | ELECTRIC - SERVICE UPGRADE | TVALENCIA | Approved | Clear electric eco Unit 238 only. |
10/30/2020 | BUILDING - PROGRESS | JBURGE | Approved | Partial. Information: Plywood sheathing (3/4”) fire rated as per Pyro Guard. Ok to use in communication areas. |
11/02/2020 | PLUMBING - PROGRESS | JBURGE | Approved | Partial. Garage level waste and vent lines at GL: H-O/3-8 (2 1/2”-8” lines). Ok to drop test lines into Manhole (Mercado System) |
11/20/2020 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | |
11/20/2020 | PLUMBING - ROOF DRAINS | JBURGE | Approved | |
11/23/2020 | TEP CLEARANCE - AM | JBURGE | Approved | CODE ECO/ Level #4 402; 403; 404; 405; 406; 407; 408; 409; 410; 411; 412; 413; 414; 416. |
11/30/2020 | ELECTRIC - RECONNECT | ESTEVENS | Approved | Both are approved. The TEP clearance code is RECN. |
11/30/2020 | ELECTRIC - FINAL | ESTEVENS | Approved | Both are approved. The TEP clearance code is RECN. |
12/09/2020 | TEP CLEARANCE - PM | JBURGE | Approved | CODE ECO, Units 201; 202; 203; 204; 205; 206; 207; 208; 209; 210; 211; 212; 213; 214; 215; 216; 217; 218; 219 |
12/11/2020 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | |
12/11/2020 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | |
12/11/2020 | PLUMBING - ABOVE CEILING | JBURGE | Approved | |
12/11/2020 | PLUMBING - INTERMEDIATE | JBURGE | Approved | |
12/11/2020 | ELECTRIC - TEMP POWER FOR TEST | JBURGE | Approved | |
12/11/2020 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | |
12/11/2020 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | |
12/11/2020 | SHEET ROCK NAILING | JBURGE | Approved | |
12/11/2020 | BUILDING ABOVE CEILING | JBURGE | Approved | |
12/11/2020 | FRAMING | JBURGE | Approved | |
12/11/2020 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | |
12/11/2020 | BUILDING PRE-SLAB | JBURGE | Approved | |
12/11/2020 | STEM WALL/RETAINING WALL | JBURGE | Approved | |
12/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | |
12/14/2020 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | Approved. Level #1 Room Units 103; 105; 107; 109; 114; 116; 117; 118. Sub panels at #332 (pool room); 430 (Yoga Room); 433 (Gym room). Ok to energize panels and place meters. |
12/16/2020 | STORMWATER FOLLOW-UP INSP | BBENEDON | Approved | Continued. |
12/22/2020 | PLUMBING - BACK WATER VALVE | JBURGE | Approved | Approved. Tested and certified. |
04/02/2021 | PLUMBING - FINAL | JBURGE | Approved | Approved. Bacteria test results forwarded to Robert Sherry. |
04/02/2021 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | Approved. |
04/02/2021 | OUTDOOR LIGHTING FINAL | JBURGE | Approved | Approved. |
04/02/2021 | MECHANICAL - FINAL | JBURGE | Approved | Approved. |
05/04/2021 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | Approved. Ok to set commercial gas meter. Called in to SW Gas at 1420 hours. |
05/07/2021 | GAS CLEARANCE | JBURGE | Approved | CODE |
05/07/2021 | PLUMBING - GAS PRESS TEST FNL | JBURGE | Approved | Approved. Ok to set commercial gas meter. CLEARANCE. OK to set new meter. |
08/03/2021 | FIRE INTERMEDIATE | MRoss | Approved | |
08/19/2021 | FIRE SPKLR - FINAL | MRoss | Approved | |
08/19/2021 | FIRE - ALARM FINAL | MRoss | Approved | ERRC is under permit # T21FC00570 |
08/20/2021 | STORMWATER FINAL INSPECTION | DROBERTS | Approved | APPROVED |
08/20/2021 | STORMWATER INSTALL OF CONTROLS | DROBERTS | Approved | APPROVED |
08/24/2021 | BUILDING - FINAL | JBURGE | Approved | . Partial. Information for TCO application. |
08/25/2021 | RIGHT OF WAY - FINAL | DR | Approved | OK FOR TEMP CO PER PIA INSPECTOR JACK KOKOT. |
09/22/2021 | FIRE - FINAL | MRoss | Approved | Items needed for C of O -ERRC system installed and tested -Add access keys to commercial suites as TIs are completed. |
07/25/2022 | ZONING - FINAL | DROBERTS | Approved | THE COMBINATIONS HAS BEEN APPROVED. |