Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - PROGRESS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/02/2021 | ELECTRIC - PROGRESS | Approved | Approved. | |
| 12/11/2020 | ELECTRIC - PROGRESS | Partial Approval | Partial. 16 Room Units with kitchen service island; OK to place outlets at a height that will accommodate island use. | |
| 08/18/2020 | ELECTRIC - PROGRESS | Partial Approval | Partial. Information only. | |
| 08/12/2020 | ELECTRIC - PROGRESS | Partial Approval | partial 1- Sub Panel for Unit 238 is okay, I will release the meter clearance when lock out tag out on dedicated main circuit breaker has been verified. |
|
| 04/08/2020 | ELECTRIC - PROGRESS | Partial Approval | 1- First layer of sheet rock in all drop ceiling areas are okay to tape and mud .This inspection is for rooms 207, 208, 209, 247, 248, 249, 307, 308, 309, 310, 347, 348 only. | |
| 12/18/2019 | ELECTRIC - PROGRESS | Partial Approval | South, East and North breezeway lighting. |