Permit: T16CM01533

Parcel: 116206300

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
07/26/2022 BUILDING - PROGRESS Approved Approved
08/17/2021 BUILDING - PROGRESS Partial Approval Partial. Fire caulking in fire walls of commercial suites on East and North sides of building.
08/16/2021 BUILDING - PROGRESS Cancelled ca
Per Dennis.
08/11/2021 BUILDING - PROGRESS Partial Approval 01075. Partial. Clarification of required hand rails on East and North side of building. Meeting with Superintendent and owners representative.
08/04/2021 BUILDING - PROGRESS Partial Approval Partial. Walk through for future sheet rock nailing and fire caulking in commercial suites. Ok to tape progress areas.
07/26/2021 BUILDING - PROGRESS Partial Approval Partial. Information only concerning changes made to original plans.
07/14/2021 BUILDING - PROGRESS Partial Approval Partial. Information only: ADA restrooms and fire wall rating in commercial suites.
04/02/2021 BUILDING - PROGRESS Partial Approval Partial. Apartments and retail spaces are complete.
03/10/2021 BUILDING - PROGRESS Partial Approval Partial. Information for application of security doors on Level #1. Installed doors are per code.
03/08/2021 BUILDING - PROGRESS Partial Approval Partial. Information for relocation of back flow device in to garage as per RFI #325; dated 2.18.21
03/03/2021 BUILDING - PROGRESS Partial Approval Partial. Information for relocation of back flow device to garage area (fountain in courtyard area); RFI #325; dated 2/18/2021.
02/03/2021 BUILDING - PROGRESS Partial Approval Partial. Level #1; Retail spaces 150; 156; 160; 164; 166; 168; 170; 172; 176; 180; 184; 188; 190; 192; 194; 198 (shell spaces) have been completed. Ok to begin TI construction when permits have been pulled for each space.
02/02/2021 BUILDING - PROGRESS Partial Approval PARTIAL INFORMATION ONLY FOR TEMPORARY CERTIFICATE OF OCCUPANCY
10/30/2020 BUILDING - PROGRESS Partial Approval Partial. Information: Plywood sheathing (3/4”) fire rated as per Pyro Guard. Ok to use in communication areas.
10/20/2020 BUILDING - PROGRESS Partial Approval Partial. (01040); Interior courtyard at GL: K-M/4-5; North Section at GL: O-H/2-7 Levels 1 - 8 below top of parapet wall East and West walls and balcony walls. South Building wall from ground to 8’ below top of parapet wall at GL: 3-7. Ok to scratch coat progress areas.
10/09/2020 BUILDING - PROGRESS Partial Approval Partial. Information only: inspection scheduling for 12-16 October.
09/30/2020 BUILDING - PROGRESS Partial Approval Partial. Stucco mesh at exterior walls and interior courtyard walls at parapet to top of windows (6’-8’). Ok to scratch coat progress areas.
06/26/2020 BUILDING - PROGRESS Partial Approval partial
1- Fire caulking around annular space of can lights okay.
06/23/2020 BUILDING - PROGRESS Partial Approval partial
1- Okay to enclose the inaccessible space at first floor stairwell #03
10/18/2019 BUILDING - PROGRESS Not ready for Inspection Consult meeting