Inspection History Details
Inspection Status: Approved
Inspection History: FRAMING
Permit Number - T16CM01533
Inspection Description - FRAMING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/11/2020 | FRAMING | Approved | ||
09/09/2020 | FRAMING | Partial Approval | Partial. Levels 1-4; Hallways at GL: B-N/3-6. | |
09/04/2020 | FRAMING | Partial Approval | Partial. Apartments 232; 233; 333; 460 | |
09/03/2020 | FRAMING | Partial Approval | Partial. Stack #13; Apartments 112; 211; 212; 216; 311; 312; 316; 411; 415. | |
09/01/2020 | FRAMING | Partial Approval | Partial. Stack #11; Apartments #114; 115; 203; 218; 219; 303; 318; 319; 403; 417; 418; Retail space #101. Stack #12; Apartments #113; 201; 202; 217; 301; 302; 317; 401; 402; 416;. Retail space #101-A. | |
08/31/2020 | FRAMING | Not ready for Inspection | Not ready. Contractor cancelled will reschedule for 1 September | |
07/15/2020 | FRAMING | Partial Approval | partial | |
05/11/2020 | FRAMING | Partial Approval | 1- Framing okay in rooms 120,121,122,123,132,133,134,135,140,141,142 only. | |
05/07/2020 | FRAMING | Partial Approval | 1- Framing inspection was for rooms 406,407,435,436,439,440 & 445 only. | |
05/04/2020 | FRAMING | Partial Approval | 1- Framing okay to cover in rooms 241,242,236,237,238,336,337,338,341,342 only. | |
04/29/2020 | FRAMING | Partial Approval | 1- This inspection was for rooms 207,208,247,248,306,307,308,347,348 only. Okay to cover. | |
04/28/2020 | FRAMING | Partial Approval | 1- This inspection is for rooms 143,209, 210,249,250,309,310,349,350 only. Okay for sheet rock. |
|
04/23/2020 | FRAMING | Partial Approval | 1- This inspection was for rooms 146,148,254,255,354,355,452,453 only. Okay to cover. | |
04/22/2020 | FRAMING | Partial Approval | ||
04/21/2020 | FRAMING | Not ready for Inspection | 1- Contractor will reschedule inspection request. | |
04/08/2020 | FRAMING | Partial Approval | 1- North Stairwell sheathing and electric is okay for the first layer of Sheetrock. | |
01/28/2020 | FRAMING | Partial Approval | Electrical rooms are ok to drywall. | |
10/21/2019 | FRAMING | Partial Approval | 4th floor south side. | |
10/14/2019 | FRAMING | Not ready for Inspection | Need Mep intermediates in place for frame inspection. | |
10/07/2019 | FRAMING | Partial Approval | 3rd floor strapping and ties complete. | |
09/27/2019 | FRAMING | Partial Approval | Level 3, flooring complete. | |
09/24/2019 | FRAMING | Not ready for Inspection | rained out. | |
09/23/2019 | FRAMING | Not ready for Inspection | Framers have left site. Please reschedule for 24 September. Arrived at site at 1615 hours. | |
09/12/2019 | FRAMING | Partial Approval | From center of elevators to north side. | |
08/27/2019 | FRAMING | Partial Approval | 1- Floor nailing is okay on the second floor between grid lines 5.8 to 5 and between grid line 5.8 to 3.75 and between grid line E to G and 3.75 to 5 only. | |
08/15/2019 | FRAMING | Partial Approval | 1- Second floor floor nailing is okay for bldg. A and B North and west of elevator shaft. | |
08/07/2019 | FRAMING | Partial Approval | 1- Second level floor nailing is okay for bldg. A and B North and South. |