Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - ABOVE CEILING
Permit Number - T16CM01533
Inspection Description - ELECTRIC - ABOVE CEILING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/11/2020 | ELECTRIC - ABOVE CEILING | Approved | ||
12/09/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial. Retail space #127. | |
11/04/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Room Units. 112; 113; 114; 115; 201; 211; 212; 216. | |
10/23/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial. Room Units 301; 311; 312; 316; 401; 411; 415. Ok to insulate and cover. | |
10/06/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial. Room Units 202; 203; 217; 218; 219; 302; 303; 317; 318; 319. | |
10/01/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial. Level #4; 402; 403; 416; 417; 418. | |
09/29/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial: Stack 5; 7; 8; 9 Room Units 120; 121; 232; 233; 325; 333; 423; 427. Restrooms 159; 160; 161; 162; 167. | |
09/22/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial. All the above Room Units are the same as above. | |
09/21/2020 | ELECTRIC - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled all inspections for this date. | |
09/15/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial. Apartments: 204; 205; 224; 228; 229; 230; 304; 305; 324; 328; 329; 330. | |
09/09/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial. Levels 1-4; Hallways at GL: B-N/3-6. Recommend access panels (3’x3’) be installed at termination of 2” conduits (fire rated panels) at Levels 1-4 with 4 panels at each level. | |
08/25/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Partial. Room Units: 122; 123; 226; 227; 326; 327. | |
08/06/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | partial 1- Electric conductors and boxes are are okay to cover in rooms 132,133,134,341,439 only. |
|
08/05/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | partial | |
07/21/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | partial 1- This inspection is for Stack 5 rooms 236,3,238,435,436 Drop to add an attachment Attachments |
|
07/17/2020 | ELECTRIC - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled. | |
07/10/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | ||
07/09/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | , partial 1- This inspection is for rooms 301,302,303,304,305,311,312,316,317,318,319,324,325,326,327,328,329,330. |
|
07/08/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | partial 1- Electric conductors and boxes are okay to cover in rooms 401,402,403,404,405,411,415,416,417,418,423,424,427,428,430 only. |
|
05/05/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | 1- This inspection is for rooms 121,122,123,225,226,227,325,326,327,424 only. | |
04/24/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | ||
04/22/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | ||
04/21/2020 | ELECTRIC - ABOVE CEILING | Not ready for Inspection | 1- Contractor will reschedule inspection request. | |
04/10/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | ||
03/31/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | This inspection is for rooms 140, 206, 207, 247, 306, 307, 347, 406, 407, 445 only. | |
03/23/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | This inspection is for rooms 141,142,208,248,249,308,348,349,408,446,447 only. | |
03/18/2020 | ELECTRIC - ABOVE CEILING | Not ready for Inspection | 1- Work is incomplete | |
03/02/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | 1- This inspection is for rooms 105,,143,209, 210, 250, 309,310,350,409,410,448 only | |
02/26/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | 1- This inspection are for rooms 146, 148, 254, 255, 354, 355,452, 455 only. | |
02/13/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | Level #2; Electric Rooms #223; 243: OSB Sheathing and 5/8" sheetrock. | |
02/11/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | 1- Electric conductors and light boxes are okay to cover on the second floor North East Balcony only. | |
02/10/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | 1st floor. Units 148, 146, 143, 142, 141, 135, 134. | |
01/24/2020 | ELECTRIC - ABOVE CEILING | Partial Approval | 1- MC cables and metal boxes are okay to cover in units 113 and 114 only. |