Permit: T16CM01533

Parcel: 116206300

Inspection Status: Approved

Inspection History: PLUMBING - ABOVE CEILING

Date Description Inspector Results Comments
12/11/2020 PLUMBING - ABOVE CEILING Approved
11/12/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Waste and vent lines at South portion of garage.
11/10/2020 PLUMBING - ABOVE CEILING Not ready for Inspection Not ready. Contractor cancelled, will reschedule for 12 November.
11/06/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Garage level (South); waste and vent lines at 2 1/2”-8” lines at GL:C-H/3-7.
11/04/2020 PLUMBING - ABOVE CEILING Partial Approval Room Units. 112; 113; 114; 115; 201; 211; 212; 216.
10/23/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Room Units. 301; 311; 312; 316; 401; 411; 415. Ok to insulate and cover.
10/06/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Room Units 202; 203; 217; 218; 219; 302; 303; 317; 318; 319
10/01/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Level #4; Room Units 402; 403; 416; 417; 418.
09/29/2020 PLUMBING - ABOVE CEILING Partial Approval Partial: Stack 5; 7; 8; 9 Room Units 120; 121; 232; 233; 325; 333; 423; 427. Restrooms 159; 160; 161; 162; 167.
09/22/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. All the above Room Units are the same as above.
09/21/2020 PLUMBING - ABOVE CEILING Not ready for Inspection Not ready. Contractor cancelled all inspections for this date.
09/15/2020 PLUMBING - ABOVE CEILING Partial Approval 204. 205; 224; 228; 229; 230; 304, 305; 324; 328,; 329; 330
09/09/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Levels 1-4; Hallways at GL: B-N/3-6
09/04/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Apartments 232; 233; 333; 460
09/03/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Stack #13; Apartments 112; 211; 212; 216; 311; 312; 316; 411; 415.
09/02/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Stack #11; Apartments 114; 115; 203; 218; 219; 303; 318; 319; 403; 417; 418; Retail space 101. Stack #12; Apartments 113; 201; 202; 217; 301; 302; 317; 401; 402; 416; Retail space #101-A.
09/01/2020 PLUMBING - ABOVE CEILING Denied Denied. Stack #11; system leaking. Stack #12; system leaking.
08/31/2020 PLUMBING - ABOVE CEILING Not ready for Inspection Not ready. Contractor cancelled will reschedule for 1 September
08/25/2020 PLUMBING - ABOVE CEILING Partial Approval Partial. Room Units: 122; 123; 226; 227; 326; 327.
08/19/2020 PLUMBING - ABOVE CEILING Cancelled CA
1- Contractor cancelled the inspection request
08/13/2020 PLUMBING - ABOVE CEILING Partial Approval partial
1- This inspection is for the Commercial unit 127 and Residential rooms 120,224,22,229,324,327,328,423,427,428 only.
2- DWV water head test provided.
3- Overhead and in wall domestic water distribution is okay to cover.
08/12/2020 PLUMBING - ABOVE CEILING Not ready for Inspection NR
1- Work is incomplete.
08/06/2020 PLUMBING - ABOVE CEILING Partial Approval partial
1- DWV system and overhead and in wall domestic water distribution is okay to cover in rooms 132,133,134,239,240,241,339,340,341,439 only.
08/05/2020 PLUMBING - ABOVE CEILING Not ready for Inspection NR
1- Work is incomplete
08/04/2020 PLUMBING - ABOVE CEILING Cancelled CA
1- Contractor cancelled the inspection request.
08/03/2020 PLUMBING - ABOVE CEILING Partial Approval partial
1- DWV water test provided
2- Domestic overhead and in wall water distribution hydrostatic pressure test provided.
Note; This inspection is for Stack 8 all floors.
07/30/2020 PLUMBING - ABOVE CEILING Cancelled CA
1- Contractor cancelled the inspection request
07/29/2020 PLUMBING - ABOVE CEILING Cancelled CA
1- Contractor cancelled the inspection request.
07/21/2020 PLUMBING - ABOVE CEILING Partial Approval partial
1- This inspection is for Stack 5 rooms 236,3,238,435,436

Drop to add an attachment
Attachments
07/20/2020 PLUMBING - ABOVE CEILING Partial Approval partial
1- Electric and plumbing under sub floor is okay to cover in residential rooms 112,113,114,115,120,121 only and in sub floor Commercial rooms 101,125,127,153,154 only.
07/17/2020 PLUMBING - ABOVE CEILING Not ready for Inspection Not ready. Contractor cancelled.
07/10/2020 PLUMBING - ABOVE CEILING Partial Approval partial 2- Laundry Room MC cables and metal boxes okay.
05/08/2020 PLUMBING - ABOVE CEILING Not ready for Inspection 1- Work is incomplete
05/06/2020 PLUMBING - ABOVE CEILING Not ready for Inspection 1- Work is incomplete.
05/05/2020 PLUMBING - ABOVE CEILING Partial Approval 1- This inspection is for rooms 121,122,123,225,226,227,325,326,327,424 only.
04/24/2020 PLUMBING - ABOVE CEILING Partial Approval
04/22/2020 PLUMBING - ABOVE CEILING Partial Approval
04/21/2020 PLUMBING - ABOVE CEILING Not ready for Inspection 1- Contractor will reschedule inspection request.
04/10/2020 PLUMBING - ABOVE CEILING Partial Approval
03/31/2020 PLUMBING - ABOVE CEILING Partial Approval This inspection is for rooms 140, 206, 207, 247, 306, 307, 347, 406, 407, 445 only.
03/16/2020 PLUMBING - ABOVE CEILING Not ready for Inspection Work is incomplete
03/02/2020 PLUMBING - ABOVE CEILING Partial Approval 1- This inspection is for rooms 105,,143,209, 210, 250, 309,310,350,409,410,448 only
02/26/2020 PLUMBING - ABOVE CEILING Partial Approval 1- This inspection are for rooms 146, 148, 254, 255, 354, 355,452, 455 only.
02/24/2020 PLUMBING - ABOVE CEILING Partial Approval
02/21/2020 PLUMBING - ABOVE CEILING Partial Approval DVW ONLY. Units 146, 254, 354, 452.