Permit: T16CM01533

Parcel: 116206300

Inspection Status: Approved

Inspection History: PLUMBING - INTERMEDIATE

Date Description Inspector Results Comments
12/11/2020 PLUMBING - INTERMEDIATE Approved
11/12/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. South portion of garage level waste and vent lines at 2 1/2”-6” lines at GL: C-D/5-6; C-G/3-4.5.
11/10/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled, will reschedule for 12 November.
11/06/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Garage level (South); waste and vent lines at 2 1/2”-8” lines at GL: C-H/3-7.
11/04/2020 PLUMBING - INTERMEDIATE Partial Approval Room Units. 112; 113; 114; 115; 201; 211; 212; 216.
10/23/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Room Units 301; 311; 312; 316; 401; 411; 415. Ok to insulate and cover walls.
10/06/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Room Units 202; 203; 217; 218; 219; 302; 303; 317; 318; 319.
10/01/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Level #4; Room Units 402; 403; 416; 417; 418.
09/29/2020 PLUMBING - INTERMEDIATE Partial Approval Partial: Stack 5; 7; 8; 9 Room Units 120; 121; 232; 233; 325; 333; 423; 427. Restrooms 159; 160; 161; 162; 167.
09/22/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. All the above Room Units are the same as above.
09/21/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled all inspections for this date.
09/15/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Apartments: 204. 205; 224; 228; 229; 230; 304, 305; 324; 328,; 329; 330 Gas pressure test for gas line. Guage at 30 psi. RFI #284 for relocation of gas lines.
09/09/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Levels 1-4; Hallways at GL: B-N/3-6
09/04/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Apartments 232; 233; 333; 460
09/03/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Stack #13; Apartments 112; 211; 212; 216; 311; 312; 316; 411; 415. Note: RFI #175; dated 3 September; Ok to set water closets at less than 15” from vanity (13.5”).
09/02/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Stack #11; Apartments 114; 115; 203; 218; 219; 303; 318; 319; 403; 417; 417. Retail space #101. Stack #12; Apartments 113; 201; 202; 217; 301; 302; 317; 401; 401; 416, Retail space 101-A.
09/01/2020 PLUMBING - INTERMEDIATE Denied Denied. Stack #11; system leaking. Stack #12; system leaking.
08/31/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled will reschedule for 1 September
08/25/2020 PLUMBING - INTERMEDIATE Partial Approval Partial. Room Units: 122; 123; 226; 227; 326; 327.
08/19/2020 PLUMBING - INTERMEDIATE Cancelled CA
1- Contractor cancelled the inspection request
08/13/2020 PLUMBING - INTERMEDIATE Partial Approval partial
1- This inspection is for the Commercial unit 127 and Residential rooms 120,224,22,229,324,327,328,423,427,428 only.
2- DWV water head test provided.
3- Overhead and in wall domestic water distribution is okay to cover.
08/12/2020 PLUMBING - INTERMEDIATE Not ready for Inspection NR
1- Work is incomplete.
08/06/2020 PLUMBING - INTERMEDIATE Partial Approval partial
08/05/2020 PLUMBING - INTERMEDIATE Not ready for Inspection NR
08/04/2020 PLUMBING - INTERMEDIATE Cancelled CA
1- Contractor cancelled the inspection request.
08/03/2020 PLUMBING - INTERMEDIATE Partial Approval partial
07/30/2020 PLUMBING - INTERMEDIATE Cancelled CA
1- Contractor cancelled the inspection request
07/29/2020 PLUMBING - INTERMEDIATE Cancelled CA
1- Contractor cancelled the inspection request.
07/24/2020 PLUMBING - INTERMEDIATE Partial Approval partial
1- DWV water test provided for Stack 10 all floors.
2- Overhead and in wall domestic water distribution is okay to cover.
3- This inspection is for Commercial rooms 102,153 Stack 10 and for Residential rooms 204,205,304,305,404,405 only.
07/22/2020 PLUMBING - INTERMEDIATE Partial Approval partial
1- DWV Stack 5 2nd floor is okay, water head test provided.
07/21/2020 PLUMBING - INTERMEDIATE Partial Approval partial
1- This inspection is for Stack 5 rooms 236,3,238,435,436

Drop to add an attachment
Attachments
07/17/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Not ready. Contractor cancelled.
07/13/2020 PLUMBING - INTERMEDIATE Partial Approval partial
1- This inspection is for Stack #4 rooms 135,206,207,242,306,307,342,406,407,440 only.
07/07/2020 PLUMBING - INTERMEDIATE Partial Approval partial
07/06/2020 PLUMBING - INTERMEDIATE Not ready for Inspection NR
05/28/2020 PLUMBING - INTERMEDIATE Partial Approval 1- This inspection is for rooms 142,209,219,249,309,310,349,409,410,447 only.
Okay to cover.
Note; Plumbing DWV system rework for rooms 134,141,241,248,341,348,439, & 446 are okay to cover, DWV water test provided.
05/13/2020 PLUMBING - INTERMEDIATE Partial Approval Clear electric ECO
Switch Gear S1 South Suite 166, and House Panel HPS1 South Level 1 only.
05/05/2020 PLUMBING - INTERMEDIATE Partial Approval 1- This inspection is for rooms 121,122,123,225,226,227,325,326,327,424 only.
03/16/2020 PLUMBING - INTERMEDIATE Not ready for Inspection Work is incomplete
03/10/2020 PLUMBING - INTERMEDIATE Partial Approval 1- Electric conductors and boxes are okay to cover rooms 209, 249, 309, 349, 409, 447 only.
2- DWV system water test provided and okay to cover in rooms 209, 210, 250, 309, 310, 350, 409, 410, 448 only.
03/06/2020 PLUMBING - INTERMEDIATE Cancelled
03/05/2020 PLUMBING - INTERMEDIATE Not ready for Inspection 1- DWV water test was in the process of filling.
03/04/2020 PLUMBING - INTERMEDIATE Not ready for Inspection 1- Contractor agreed to reschedule the inspection request due to heavy work load.
02/24/2020 PLUMBING - INTERMEDIATE Partial Approval
02/21/2020 PLUMBING - INTERMEDIATE Partial Approval DVW ONLY. Units 146, 254, 354, 452.
10/31/2018 PLUMBING - INTERMEDIATE Partial Approval The construction authorization from the Pima County Department of Environmental Quality has been issued. P18SD00112
10/26/2018 PLUMBING - INTERMEDIATE Prior to Intermediates * PRIOR TO A COT INTERMEDIATE INSPECTION:

A DEQ CONSTRUCTION AUTHORIZATION (C.A.) IS REQUIRED FOR A NEW PRIVATE MANHOLE PROPOSED OVER AN EXISTING PRIVATE SEWER PER DP/SITE UTILITY PLANS.