Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T16CM01533
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/11/2020 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
06/17/2020 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
10/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Ramp and bike storage area at grid line 4 D. | |
08/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Steel reinforcement okay for the Helical pads located at grid line 2 between grid lines G and H. 2- Steel reinforcement is okay for the curbs between grid lines 2 and 3 and K to H. |
|
07/19/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Steel reinforcement provided and okay for the Electric Room exterior wall between grid line 3- B to 3 and between grid line B- 3 to 4. | |
07/10/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- level 1 Curb between grid lines 7/B-61 and B.2. B4/44.5 and B/5-5.5 2- level 1 Curb between grid line 6/C-F-E. 3- Stairway wall at elevated deck between grid line C. 05, C.1/4.1-4.4 |
|
07/03/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK to pour short stairs at garage ramp from level 1 to level 2 and from level 2 to level 3. Complete installing rebar at stair nosings before pour. | |
06/24/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 2nd level of podium and NW section of retaining wall footings ok to pour. | |
06/21/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Ramp deck elevation 58-4" perdetails 165 & 164 Helical pads per detail 146 GL 2 from K-H.7 |
|
06/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Pop outs GL 8 from E-M per detail 167 Curb per detail 115 at north stairwell |
|
06/19/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Garage ramp /elevated deck. Line 3-4, C.4 to D.2 | |
06/18/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Curb per detail 115 GL F- G from 4-6 | |
06/17/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | CANCELED | |
06/14/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Curb per detail 115 GL 7 from J-I.5 & GL 6 from J% I.5 | |
06/13/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Curbs per detail 115 GL 7 from N-J & GL E-J from 3-6 F-4 footer GL D from 3-4 |
|
06/06/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Curb per detail 115 GL 3 -5 from J-L only |
|
06/05/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Level one curbs OK From gridline L to N and from 3 to 5.8. | |
06/04/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | no new work ready today | |
05/28/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Epoxy placement for rebar dowels are okay in curbs between grids N to 5.5 and between L and N and from 3 to 5.5 2- Steel reinforcement provided and okay in West ramp wall between 4-B to D.1 and level 1 to level 2. |
|
05/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Steel reinforcement provided and okay from grit line 4.4 to 8 and B to E only. | |
05/03/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | parking garage wall from B to C on gridline 4 to elevation 54 or approximately 7’. | |
05/02/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Steel reinforcement provided for vertical walls located between grid line 4.4 from D.5 to C.3 and D.5 from 3 to 4 and grid line 4 from D.5 to C.3 only | |
04/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | French drain in parking garage ok, Terracon inspected this. | |
04/29/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | West ramp footing per detail 122 GL 3 from B-D.5 |
|
04/17/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Elevator walls bottom lift only | |
04/16/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Level 1 podium deck pour GL 5-8 from 10’ south of GL I - 10’ south oh GL K.9 on,y | |
04/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | South stairwell walls up to nineties only South elevator walls to slab height except nineties |
|
04/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- Steel reinforcement provided and okay for concrete between Grid lines K.5 to N and 5 thru 8 only. | |
04/05/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Steel reinforcement provided and okay between Grid line K.5 to N and grid line 3 to 5 only. | |
04/04/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Steel reinforcement for the sub level slab is okay from column F.6 to E.2 for grid line #3 to grid and F.6 to B for 5 to 8 only. | |
03/28/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | remaining garage footings, and elevator wall basement level OK | |
03/14/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | South stairwell walls up 90’s only and south exterior elevator up to 90’s finished floor height | |
03/14/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | South stairwell walls up to nineties only South elevator walls to slab height except nineties |
|
03/13/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Column 5.6/J.1 | |
03/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
03/08/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Footer B.1/6.4 | |
03/06/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | F.6/5.6, F.6/4.6& E.9/3.6 | |
03/05/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 1- steel reinforcement provided for 8- column footings. | |
03/01/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | F-1 footers H/6.4, H/5.6, H/4.6 F-1 footers I.4/5.6,I.4/4.6, I.4/3.6 F-1 footers J.1/5.6 Elevator pit per detail 104 |
|
02/28/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Column line M.5 both columns. column line L.6 and Line K.9 three columns each on the north side. J.1 to M.5 Row 3.6 and row 4.6 four mats each Row skipping mat L6 3.6. | |
02/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL 5.6/J.8, K.9, L.6, M.5 AND GL 6.4/J.4, J.8, K.9, L.6, M.5 AND GL 7/J.1, I.4, I.8, K.9 COLUMN FOOTINGS OK TO POUR. | |
02/15/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | cancel by Dennis | |
02/04/2019 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
01/31/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | F3 footers at north stairwell F2 footers with CW 2 walls GL N from 4.75 - 3, GL 3 from D.5 - N & GL D.5 from 3 - 3.6 |
|
01/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | no work | |
01/17/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | from 1.4 to left or south to corner B 7 | |
01/16/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK from Gridline 1.4 on 8 to stairwell garage level retaining walls. | |
01/15/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | superintendent just wanted to meet and ask questions about required inspections scheduling and critical path |