Permit: T17CM00004
Permit Details
Apply Date:
01/03/2017
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
STUDENT HOUSING TOWER
Architects:
- LUIS CRUZ-MARTINEZ
Contractors:
- 3411 BUILDERS INC **APA**
Permit Reviews
Permit Number - T17CM00004
Permit Status: C of o
Permit Description: STUDENT HOUSING TOWER
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/03/2017 | PLANS OK TO SUBMIT - COMM | 02/22/2017 | COMPLETED |
| 01/23/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 04/04/2018 | COMPLETED |
| 01/25/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 05/23/2019 | COMPLETED |
| 02/06/2018 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 02/23/2018 | COMPLETED |
| 02/22/2017 | 3RD PARTY REVIEW - COMMERCIAL | 09/18/2017 | COMPLETED |
| 04/04/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 04/05/2018 | COMPLETED |
| 05/10/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 06/07/2018 | COMPLETED |
| 05/23/2019 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 05/23/2019 | COMPLETED |
| 05/23/2019 | POST 3RD PARTY REVIEW | 07/29/2019 | COMPLETED |
| 06/07/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 06/08/2018 | COMPLETED |
| 06/14/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 06/27/2018 | COMPLETED |
| 06/14/2018 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 06/27/2018 | COMPLETED |
| 07/29/2019 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 07/29/2019 | COMPLETED |
| 08/23/2019 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 08/23/2019 | COMPLETED |
| 08/23/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 08/23/2019 | COMPLETED |
| 08/28/2019 | 3RD PARTY REVIEW - REVISION/OTHER | 08/28/2019 | COMPLETED |
| 09/04/2019 | 3RD PARTY REVIEW - COMMERCIAL | 09/30/2019 | COMPLETED |
| 09/18/2017 | POST 3RD PARTY REVIEW | 10/27/2017 | COMPLETED |
| 10/17/2018 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 10/31/2018 | COMPLETED |
| 10/18/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 10/31/2018 | COMPLETED |
| 10/31/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 11/13/2018 | COMPLETED |
| 11/13/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 12/03/2018 | COMPLETED |
| 12/03/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 12/03/2018 | COMPLETED |
| 12/03/2018 | 3RD PARTY REVIEW - REVISION/OTHER | 12/10/2018 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T17CM00004
Permit Status: C of o
Permit Description: STUDENT HOUSING TOWER
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/03/2017 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T17CM00004
Permit Description: STUDENT HOUSING TOWER
Total Completed Inspections - 49
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/20/2017 | PLUMBING - ROUGH, SOIL | BSTEVENS | Approved | OIL SEPERATOR AND LIFT STATION TANKS OK TO BACKFILL. |
| 12/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | BSTEVENS | Approved | COLUMNS D.1/3.9 AND B/4.7 OK TO POUR |
| 01/17/2018 | ELECTRIC - UFER | BSTEVENS | Approved | |
| 05/23/2018 | PLUMBING - SEWER HCS CONNECT | BSTEVENS | Approved | |
| 07/18/2018 | ELECTRIC - CONSTRUCTION POWER | JBURGE | Approved | POWER SERVICE LINE FOR TMPORARY MAN-LIFT. **CALLED IN TO TEP AT 1020 HOURS TIS DATE. |
| 09/05/2018 | PLUMBING - ABOVE CEILING | BSTEVENS | Approved | LEVELS B1 & B2 ROUGH PLUMBING TEST APPROVED. |
| 09/20/2018 | FIRE SPKLR - UG PIPING FLUSH | CBASALDUA | Approved | |
| 10/05/2018 | ELECTRIC - UNDERGROUND | BSTEVENS | Approved | North half of roof deck ok to pour |
| 10/15/2018 | FIREWALL/FIREBARRIER/FIRESTOP | BSTEVENS | Approved | LEVEL 2 & 3 shaft at NE stairway & SE stairway ok to cover |
| 10/25/2018 | SHEET ROCK NAILING | BSTEVENS | Approved | Stairwell shaft East - levels 2&3 south and west walls and levels 4&5 East wall ok to cover. |
| 11/06/2018 | STEM WALL/RETAINING WALL | BSTEVENS | Approved | curb walls and CMU starter walls on level 12 OK to pour. |
| 12/03/2018 | PLUMBING - INTERMEDIATE | ESTEVENS | Approved | Drain waste and vent on second floor third floor fourth floor and fifth floor has marked on inspectors plumbing plan. |
| 12/05/2018 | EXT METAL CLIPS/EXT SHEATHING | ESTEVENS | Approved | Levels eight and seven exterior sheathing Okay to cover. |
| 12/13/2018 | BUILDING PRE-SLAB | IVR USER | Approved | IVRS - AP canceled |
| 12/19/2018 | REINFORCED MASONRY PRE-GROUT | ESTEVENS | Approved | Stairwell A masonry top out |
| 12/20/2018 | FRAMING | ESTEVENS | Approved | Fire caulk on fifth floor shafts, all except north west corner |
| 12/27/2018 | ELECTRIC - INTERMEDIATE | ESTEVENS | Approved | Canceled by contractor |
| 02/04/2019 | FIRE SPKLR - UG, PIPING, HYDRO | jvincent | Approved | approved per C.B. See permit #T18FC00196 |
| 07/23/2019 | GAS CLEARANCE | ESTEVENS | Approved | |
| 07/23/2019 | PLUMBING - GAS PRESS TEST FNL | ESTEVENS | Approved | South west gas clearance required. |
| 07/29/2019 | TEP CLEARANCE - PM | ESTEVENS | Approved | UNIT #917 CODE ECO |
| 07/29/2019 | MECHANICAL - UNDERGROUND | ESTEVENS | Approved | |
| 07/29/2019 | PLUMBING - ROOF DRAINS | ESTEVENS | Approved | Inspected at intermediate. |
| 07/29/2019 | PLUMBING - YARD WTR LINE/TEST | ESTEVENS | Approved | |
| 07/29/2019 | BUILDING - PROGRESS | ESTEVENS | Approved | |
| 07/29/2019 | STUCCO MESH | ESTEVENS | Approved | |
| 07/29/2019 | U VALUE FOR WINDOW | ESTEVENS | Approved | |
| 07/29/2019 | ROOF NAILING | ESTEVENS | Approved | |
| 08/21/2019 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | Level 9 mezzanine units, moved pancake units from closet to main common area. Submit as built plans to city. |
| 08/21/2019 | BUILDING ABOVE CEILING | ESTEVENS | Approved | Level 9 mezzanine units, moved pancake units from closet to main common area. Submit as built plans to city. |
| 09/13/2019 | ZONING - FINAL | NR | Approved | |
| 09/20/2019 | MECHANICAL - PROGRESS | ESTEVENS | Approved | |
| 09/20/2019 | MECHANICAL - INTERMEDIATE | ESTEVENS | Approved | |
| 09/20/2019 | PLUMBING - PROGRESS | ESTEVENS | Approved | |
| 09/20/2019 | ELECTRIC - PROGRESS | ESTEVENS | Approved | |
| 09/20/2019 | ELECTRIC - CABLE DROP | ESTEVENS | Approved | |
| 09/23/2019 | PLUMBING - GAS PRESSURE TEST | ESTEVENS | Approved | |
| 09/24/2019 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | |
| 09/24/2019 | ELECTRIC - OUTDOOR LIGHTING | ESTEVENS | Approved | |
| 09/24/2019 | OUTDOOR LIGHTING FINAL | ESTEVENS | Approved | |
| 09/24/2019 | PLUMBING - FINAL | ESTEVENS | Approved | |
| 09/24/2019 | ELECTRIC - FINAL | ESTEVENS | Approved | |
| 09/25/2019 | FIRE - FINAL | JPEELDAVIS | Approved | OK FOR COFO FIRE ALARM PERMIT TO REMAIN OPEN |
| 09/25/2019 | FIRE - LANE SIGNS | JPEELDAVIS | Approved | |
| 09/25/2019 | FIRE SPKLR - FINAL | JPEELDAVIS | Approved | |
| 09/25/2019 | FIRE SPKLR - OH PIPING & HYDRO | JPEELDAVIS | Approved | |
| 09/25/2019 | ENGINEERING - FINAL | DROBERTS | Approved | PENDING ALL OTHER INSPECTIONS |
| 09/30/2019 | BUILDING - FINAL | JGARCIA | Approved | |
| 09/30/2019 | MECHANICAL - FINAL | JGARCIA | Approved | AIR BALANCE REPORT TO BE SUBMITTED UNDER NEW PERMIT#T19CM07116 |