Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Address Search: 950 N TYNDALL AV
Search
Parcel Attributes
Parcel | 12404097C 12404097A |
---|---|
Jurisdiction | Tucson |
City of Tucson Zoning | UC-1, C-1, UC-1 |
Tucson Ward | Ward 6 |
Tucson Registered Neighborhood | West University |
Pima County Data | Assessor, Recorder, Treasurer, ... |
Parcel Map | Map |
Annexations & Original City Zoning (OCZ)
Address: 950 N TYNDALL AV
Date - 11/14/2024 5:42 p.m.
Total Number Of Annexations & Original City Zoning (1)
Plan | Description | Annexation Ordinance | Effective Date | OCZ Ordinance |
---|---|---|---|---|
1/4 Mile Each Direction (N, E, S, W) | 202 | None |
Rezoning Cases
Date - 11/14/2024 5:42 p.m.
Total Number Of Rezone Cases - (1)
Case No. | Description | New Zone | Status | Status Date |
---|---|---|---|---|
C9-12-01 | C9-12-01 Main Gate Dist. (UOD) | UOD | Effectuated | 01/05/2012 |
Special Development Requests & Requirements
Address: 950 N TYNDALL AV
Date - 11/14/2024 5:42 p.m.
Total Number Of Special Development Permits - (5)
Activity Number | Status | Apply Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
H000007450 | CLOSED | 08/14/2015 | N/A | Historical Information | ||
T16SA00348 | APPROVED | 08/09/2016 | 11/17/2017 | Overlay Zone | The Project will be located on the current Chase Bank parking lot at the southeast corner of First St. and Tyndall Ave.The Property is zoned C-1 and in the Main Gate Overlay District (“MGOD) and is requesting the MGO zoning option, as it encourages the heights and density appropriate for student housing near the University.The Project’s 10-story design complies with the MGOD’s allowed height. Approved with conditions: 1. The red accent feature that wraps around the entire building (the "Red Strip") as a key design element, shall be constructed of one material. The applicant or its successor will repaint the red accent strip every seven (7) years, or as otherwise reasonably required to remedy significant color fading of the accent strip. 2. The applicant will enter into an agreement with the Islamic Center (ICT) of Tucson to memorialize any terms agreed to by the parties. The Agreement should address concerns raised by the ICT, including the 3. establishment of primary points of contacts during both construction and after the Project opens, alcohol service at the Property, rooftop pool location and hours, and events that may conflict with the ICT's Friday prayers. 4. The applicant shall present/provide an updated graphic of the rooftop design which retains the transition buffers between the rooftop amenity area and the building edges, especially on the Project's north edge facing the ICT. 5. The applicant shall submit a project Communications Plan ("Plan"). The Plan shall describes how the applicant or its successor property owner or its managing team will provide Project's neighbors (such as: ICT, West University Neighborhood Association, and the Marshall Foundation) the primary contact persons for the Project, both during construction and management. | |
T17SA00233 | COMPLETE | 05/31/2017 | N/A | Zoning Adminstration Letter | ||
T18SA00402 | FINAL | 09/13/2018 | N/A | Zoning Adminstration Letter | TEMPORARY NOISE EXEMPTION | |
T19SA00397 | COMPLETE | 09/26/2019 | N/A | Zoning Adminstration Letter | ZONING LETTER |
Permits
Address: 950 N TYNDALL AV
Date - 11/14/2024 5:42 p.m.
Total Number Of Permits - (35)
Permit | Status | Apply Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
TC-COM-1024-02058 | Inspections | 10/25/2024 | 04/27/2025 | Commercial Building | REPLACE A DEFECTIVE BUSS BARR PIECE IN A MULTIMETER PACK WITH A LIKE FOR LIKE OEM PART. METER PACK IS FOR 3 UNITS WITH PARTIAL POWER. 1003-1007-1009 | |
DP16-0151 | Complete | 08/23/2016 | 03/24/2020 | Development Package | SITE/GRADING/SWPPP - STERLING - TYNDALL AVENUE (MGD)Originally approved: 12/27/2016 (25 pages) | |
TR-UTL-0724-01253 | Withdrawn | 07/01/2024 | N/A | Right-of-Way (ROW) - Utility | A.3029338-1: Access of ex MH 6229 for splicing | |
TR-UTL-0724-01254 | Complete | 07/01/2024 | 11/06/2024 | Right-of-Way (ROW) - Utility | A.3029338-2: Access of ex MH 7031 & 7607 for splicing | |
T19OT00520 | Issued | 06/11/2019 | 12/08/2019 | Sign - Permanent | 2-ILLUM UC SIGN | |
T19FC00209 | Expired | 03/22/2019 | 04/10/2020 | Fire Construction Permit | Fire Alarm & Detection Systems - Install an Emergency Radio Communications Enhancement System in this 10-story Student Housing Building; Fire Alarm Systems - New Sq Ft: 20000; Fire Alarm Systems - # New Stories: 1; Additional Inspections: 10 | |
T16CM09380 | L OF C | 12/15/2016 | 03/23/2020 | COMBO | FOUNDATION FOR FUTURE STUDENT HOUSING TOWER | |
T16RW02814 | FINAL | 11/18/2016 | 01/18/2017 | ROW | UPGRADE EXISTING 4" WATER MAIN TO NEW 8" DIP UPGRADE IS NECESSARY TO FACILITATE A NEW HIGH RISE STUDENT HOUSING BUILDING LOCATED AT 950 N TYNDALL PROJECT MUST BE PERFORMED DURING THE HOLIDAY BREAK FOR THE UNIVERSITY OF ARIZONA | |
T16RW03222 | FINAL | 12/19/2016 | 01/20/2017 | ROW | Air-vacuum Excavation of 4 utility potholes, 12" x 12" in size, for Tucson student housing project consultant Rick Engineering | |
T17CM00004 | C OF O | 01/03/2017 | 03/28/2020 | COMBO | STUDENT HOUSING TOWER | |
T17CM03952 | L OF C | 05/18/2017 | 03/22/2020 | COMBO | NEW PRIVATE SEWER LINE | |
T17CM04644 | FINAL | 06/15/2017 | 05/29/2018 | COMBO | CONSTRUCTION TRAILER FOR TEMP POWER | |
T17CM05056 | FINAL | 06/29/2017 | 06/03/2018 | COMBO | TEMPORARY PWR FOR MAN LIFT REFERENCE TEMP #3 . | |
T17RW01074 | FINAL | 03/07/2017 | 03/11/2017 | ROW | POTHOLING 2 LOCATIONS ON 1ST ST, 3 LOCATIONS ON TYNDALL. | |
T17RW04903 | FINAL | 11/02/2017 | 12/03/2017 | ROW | Closure of Tyndall Ave between 1st and 2nd for installation of tower crane. Closure to start at noon, Friday, 11/3 and be open by 5pm, Sunday, 11/5 | |
T18BU00321 | FINAL | 05/23/2018 | 02/08/2020 | POOL/SPA | SEMI PUBLIC POOL | |
T18FC00045 | FINAL | 01/16/2018 | 07/08/2020 | FIRECONS | INSTALL NEW FIRE SPRINKLER SYSTEM THROUGHOUT THE BUILDING AND GARAGE. | |
T18FC00196 | FINAL | 03/07/2018 | 03/16/2019 | FIRECONS | UNDERGROUND FIRE LINE FOR FUTURE BUILDING | |
T18FC00625 | FINAL | 07/31/2018 | 12/14/2020 | FIRECONS | NEW FIRE ALARM SYSTEM | |
T18RW00126 | FINAL | 01/04/2018 | 04/30/2019 | ROW | BARRICADING FOR CONCRETE TRUCKS 2/15/18 Modifying hours to include overnight work (6p - 6a) on either 2/15 or 2/16 for concrete pour per approved TNE. 2/28/18 Added 2 concrete pours on 3/22 and 3/26 3/20/18 Added a concrete pour on 3/30 per approved TNE 12/27/2018- FULL CLOSURE FOR CRANE REMOVAL 12/29-12/30/18; 24 HOUR 04/11/2019 FULL CLOSURE ON TYNDALL AV | |
T18RW01532 | FINAL | 04/05/2018 | 06/13/2018 | ROW | New Water service and meter and Fire Hydrant | |
T18RW01907 | FINAL | 04/27/2018 | 09/11/2018 | ROW | (Install 8"-10" sanitary sewer)1st Street to 5th Street along Euclid St. approximately 12' deep includes: 1,444 of 10" new sewer main Installing 4 new manholes boring 130 across University Blvd on Euclid St and all other associated work Tyndall Ave. 1st St to 2nd St along Tyndall Ave. includes: installing 2 manholes and all other associated work approximately 8' deep. ALL WORK PER APPROVED RWRD PLAN G-2016-073 MORATORIUM ON PAVEMENT CUTS; ADDITION PAVERS REQUIRED SEE APPROVED PLAN, | |
T19CM01193 | FINAL | 02/19/2019 | 03/18/2020 | COMBO | MECH,ELECTRIC WORK FOR FUTURE TENANT | |
T19CM01364 | C OF O | 02/25/2019 | 07/06/2020 | COMBO | BANK | |
T19CM07043 | FINAL | 09/26/2019 | 07/08/2020 | #609 | COMBO | TI: BATHROOMS FOR ADA |
T19CM07116 | FINAL | 09/30/2019 | 09/01/2020 | COMBO | MECH COMPLAINCE PERMIT RELATED TO T17CM00004 | |
T19FC00379 | FINAL | 05/17/2019 | 06/24/2020 | FIRECONS | Fire Alarm TI on 1st Floor - 27 Devices | |
T19FC00400 | FINAL | 05/28/2019 | 03/15/2020 | FIRECONS | Install new Fire Sprinkler Heads to new grid ceiling | |
T19OT00175 | FINAL | 02/22/2019 | 11/16/2019 | SIGN | 4- ILLUM WALL SIGNS | |
T19OT01140 | FINAL | 12/06/2019 | 09/02/2020 | SIGN | 2-ILLUM WALL SIGN | |
T19RW01796 | FINAL | 04/03/2019 | 06/03/2019 | ROW | Starting on the East side of N Tyndall and South of E 1st Street trench/bore going North 206' and place Cox Vault. | |
T19RW03710 | FINAL | 06/28/2019 | 07/29/2019 | ROW | Full closure for replacement of pavement along Tyndall, including new asphalt paving, vertical concrete curbs, concrete sidewalks, sidewalk scuppers, curb cuts, tree grates and vegetation, all per DP16-0151 | |
T19RW06491 | FINAL | 10/24/2019 | 12/25/2019 | ROW | JOB WILL REQUIRE ACCESS TO MH#7607 TO SPLICE FIBER | |
T22OT00431 | FINAL | 06/14/2022 | 01/23/2023 | SIGN | sign on canopy face on west elevation - over ROW - has TRE | |
T22RW03168 | FINAL | 08/31/2022 | 10/01/2022 | ROW | Emergency window removal. Need to remove before it falls, will be placing lift in front of building. They will have spotters on the ground to direct pedestrian traffic. ** PROOF OF NOTIFICATION IS REQUIRED AT THE TIME OF THE PRECONSTRUCTION MEETING. |
Record Requests
Address: 950 N TYNDALL AV
Date - 11/14/2024 5:42 p.m.
Total Number Of Requests - (1)
Request Number | Status | Request Date | Completed Date | Type | Description |
---|---|---|---|---|---|
REQ-0824-05624 | Complete | 08/20/2024 | 08/20/2024 | Requests | A.3029338-1: Access of ex MH 6229 for splicing |