Inspection History: EXT METAL CLIPS/EXT SHEATHING
| Date |
Description |
Inspector |
Results |
Comments |
| 07/29/2019 |
EXT METAL CLIPS/EXT SHEATHING |
|
Approved |
|
| 05/01/2019 |
EXT METAL CLIPS/EXT SHEATHING |
|
Partial Approval |
Floors 9 and 10 |
| 12/05/2018 |
EXT METAL CLIPS/EXT SHEATHING |
|
Partial Approval |
Levels eight and seven exterior sheathing Okay to cover. |
| 12/04/2018 |
EXT METAL CLIPS/EXT SHEATHING |
|
Partial Approval |
Sixth floor exterior walls sheathing attachment OK |
| 11/06/2018 |
EXT METAL CLIPS/EXT SHEATHING |
|
Not ready for Inspection |
|
| 10/12/2018 |
EXT METAL CLIPS/EXT SHEATHING |
|
Partial Approval |
LEVEL 5 EXTERIOR DRYWALL AND FRAMING OK TO COVER. |
| 10/03/2018 |
EXT METAL CLIPS/EXT SHEATHING |
|
Partial Approval |
4th floor exterior ok to cover |
| 09/13/2018 |
EXT METAL CLIPS/EXT SHEATHING |
|
Partial Approval |
EXTERIOR FRAMING AND SHEATHING OK ON LEVEL 3 |
| 08/30/2018 |
EXT METAL CLIPS/EXT SHEATHING |
|
Partial Approval |
LEVEL 2 EXTERIOR WALLS OK TO COVER |