| 07/08/2019 |
PLUMBING - INTERMEDIATE |
|
Approved |
Units number 807, 907, 1007. |
| 06/07/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Units 507,607,707, 1003. |
| 06/05/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Level #10; Rooms: 1001; 1002; 1004; 1005; 1006; 1017. |
| 05/31/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Units 207, 307, 407, 1008, 1009, 1010, 1011. |
| 05/29/2019 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
Contractor cancelled. |
| 05/28/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Level #9; Rooms 903, 906. Level #10; Rooms #1012 through 1016. |
| 05/24/2019 |
PLUMBING - INTERMEDIATE |
|
Cancelled |
Inspector could not get back to west side site early enough for inspection. Trucky cancelled instead. |
| 05/17/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Units 901, 902, 904, 905, 906, 908. Level 2 study room. |
| 05/15/2019 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
not complete |
| 05/10/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Unit number 909, 910, 911 and 917 |
| 05/09/2019 |
PLUMBING - INTERMEDIATE |
|
Cancelled |
Cancel by contractor. Too late in the day |
| 05/02/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Units 912, 913, 914. 915, 916 |
| 05/01/2019 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
canceled by contractor |
| 04/30/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
DWV on 9th and 10th floors |
| 04/29/2019 |
PLUMBING - INTERMEDIATE |
|
Cancelled |
|
| 04/23/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
First level, fitness center and restrooms, main lobby, manager, leasing office and bookkeeper, rooms Number 113 114 115 116 and 119A, Break room mechanical room and lounge area. |
| 04/22/2019 |
PLUMBING - INTERMEDIATE |
|
Cancelled |
Cancel by contractor |
| 04/12/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
DWV units 910 thru 917 and study. Units 1010 thru 1017 and study. |
| 04/09/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Units 101 and 102 |
| 03/27/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Eighth floor units 801 through 806 and unit 808 |
| 03/22/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Unit number 809 through 816. |
| 03/21/2019 |
PLUMBING - INTERMEDIATE |
|
Cancelled |
Canceled per contractor |
| 03/14/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Seventh floor units 701 through 706 and 708 |
| 03/11/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
7th floor units 709 thru 716. |
| 03/05/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Seventh floor DWV’s |
| 03/05/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Unit number 608 |
| 02/28/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
For unit 609, 615 and 617 |
| 02/28/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Drain waste vent inspections on floors six and 74 units 709 through 716 and 609 through 616 |
| 02/27/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Six floor rooms 610 through 614. |
| 02/26/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Inspections for room 103 |
| 02/21/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Fifth floor, unit 501 through 506 and 508 |
| 02/20/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Fifth floor unit 509 through 516. |
| 02/19/2019 |
PLUMBING - INTERMEDIATE |
|
Cancelled |
|
| 02/15/2019 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
Broken pipe on sixth floor. |
| 02/08/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Level four intermediates complete |
| 02/05/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Level four apartments 8, 9 and 10 intermediate inspections all Approved. Levels two and three remaining items of framing and intermediate inspections approved |
| 02/04/2019 |
PLUMBING - INTERMEDIATE |
|
Cancelled |
canceled by the contractor |
| 02/01/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Level four unit 411 412 413 414 415 only |
| 01/25/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Units 301 through 306 and 308, unit number 304 a sanitary sweep is required.. |
| 01/23/2019 |
PLUMBING - INTERMEDIATE |
|
Cancelled |
Cancel by contractor |
| 01/17/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Unit number 309 and number 310 the pro vent is in the fire shaft |
| 01/09/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Room 203 washer box needs Santee fitting |
| 01/04/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Unit numbers 209 through 216 |
| 12/03/2018 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Drain waste and vent on second floor third floor fourth floor and fifth floor has marked on inspectors plumbing plan. |
| 01/30/2018 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
|
| 01/09/2018 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
EAST HALF OF TOTAL DRAIN SYSTEM AND DOMESTIC DRAIN FROM F7 MORTH TO A |