Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T17CM00004
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
06/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LEVEL 5 NORTH OK TO POUR | |
06/04/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LEVEL #4, SOUTH; 22 COLUMNS AT GL: F.8-L/2-8; 2/F.8-L; SHEAR WALLS #11, 12, 13. OK TO PLACE CONCRETE. AFTER HOURS INSPECTION 5-2-18. APA ACCOUNT TO BE CHARGED $165. | |
05/14/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LEVEL 3 SOUTH FROM F8 TO M AND 2 TO 8 SLAB OK TO POUR | |
05/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
02/15/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/14/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/13/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/12/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/08/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/06/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SPOT FOOTINGS 4.5/E.5 AND E.8; 5/E.3 TO G.4 | |
02/02/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL 8/D.4-D.5, 3 COLUME GL 7/D.9,E.7,F.8. WALL FOOTER AT G.4 | |
02/02/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
02/01/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
01/31/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
01/30/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 3 columes GL F.7, E.8, F.8. | |
01/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS F.6/D AND F.8/D.5 OK TO POUR | |
01/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | IVRS - AP canceled | |
01/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ELEVATOR SHAFT FOOTING OK TO POUR WITH ENGINEER APPROVAL | |
01/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | POUR 1 OF BASEMENT FLOOR OK TO POUR CHANGED FROM AP TO PA BY BSTEVENS ON 5/16/18 | |
01/04/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOUTH 1/3 OF FLOOR PROGRESSING, RE-CALL FOR TOMORROW | |
12/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS D.1/3.9 AND B/4.7 OK TO POUR | |
12/27/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | COL'S NOT READY, WILL RE-INSPECT TOMORROW AM | |
12/21/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS FOR COLUMNS D.1/3.9 & B/4.7 ALSO SHEARALL SW3 OK TO POUR | |
12/20/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS B.2/20,21,30,39,47,48,51,52,53 ALL OK TO POUR | |
12/19/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COL'S 4/E.4,E.8,F.7 AND 4/E.3-F.6 ALSO SW3 OK TO POUR | |
12/18/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FTG 3/D AND COL. FTG. C.1 NORTH TO CORNER THEN WEST TO 4.2 COL. FTGS. AND PREIMETER FTG. OK TO POUR | |
12/15/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
12/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | NORTHWEST CORNER SPREAD FOOTONGS OK TO POUR | |
12/12/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS B.2, B.1 / 4.5, 5.7,6.2 G.4/5, D.6/3 ALL OK TO POUR | |
12/11/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | nothing to inspect. | |
12/08/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS FOR COLUMNS 4.5/F.7,G.2 AND G.4/5 OK TO POUR. SHEARWALLS 10,11,12 OK TO POUR. |
|
12/06/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS H5 AND H5.7 OK TO POUR FOOTING. | |
12/05/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | EAST SIDE PERIMETER FOOTING OK TO POUR. FOOTING AT SW 12 OK TO POUR, COLUMNS 3/E.6 AND 3/G.2 OK TO POUR | |
12/04/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHEARWALL FOOTING POUR TODAY OK | |
12/01/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SHEARWALLS 10 AND 11 FOOTING GRIDLINE G-J.4 / 2.5 TO 4.5 AND COLUMN FOOTINGS G, H, J.4 / 1.9, 3, 4, 4.7, 5.7, 6.8, 7.3, 7.6 / L TO J.4 OK TO POUR. | |
11/30/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SAME AS YESTERDAY | |
11/29/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GL 4.5 SOUTH END EAST TO CORNER AND NORTH TO GL F, OK TO POUR AFTER SCRAPPING OUT FOOTINGS. WILL RE-VISIT ON 11/30 PRIOR TO POUR. | |
11/28/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
11/27/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FROM COLUMN 81 SOUTH TO CORNER AND EAST TO GRID LINE 4.5, OK TO POUR PERIMETER FOOTING AND WEST AND SOUTH SPOT FOOTINGS. SOME CLEANUP REQUIRED PRIOR TO POUR. | |
11/14/2017 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | CONTRACTOR CANCELLED. | |
11/13/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | ||
11/09/2017 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | rebar not in place. | |
11/01/2017 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | THIS SITE VISIT WAS TO DISCUSS THE FOUNDATION SCHEDULING TO BEGIN NEXT WEEK. ALL INSPECTIONS FROM THIS DATE FORWARD WILL BE ON THIS PERMIT ONLY. |